State ex rel. Elsass v. Shelby Cty. Bd. of Commrs.

Decision Date15 August 2001
Docket NumberNo. 00-2051.,00-2051.
Citation751 NE 2d 1032,92 Ohio St.3d 529
PartiesTHE STATE EX REL. ELSASS ET AL., APPELLANTS, v. SHELBY COUNTY BOARD OF COMMISSIONERS ET AL., APPELLEES.
CourtOhio Supreme Court

Elsass, Wallace, Evans, Schnelle & Co., L.P.A., and Stanley R. Evans, for appellants.

James F. Stevenson, Shelby County Prosecuting Attorney, and Michael F. Boller, Assistant Prosecuting Attorney, for appellees.

Per Curiam.

Appellant Robbie May Elsass has a life estate, and her son and daughter-in-law, appellants Murray E. Elsass and Janet E. Elsass, have a remainder as tenants in common in real property located in Dinsmore Township, Shelby County, Ohio, which is within the Shelby Soil and Water Conservation District ("district"). Appellants lease the property to others for agricultural purposes, i.e., growing crops. The Elsass property is located in the southeast area of a watershed in which rain falling in the area generally flows from the northwest to the southeast and drains into Loramie Creek, the eastern boundary of the Elsass property.

Around 1990 or 1991, Timothy A. Byrd, the drainage coordinator for the district, received complaints from Clarence King and his wife about a standing water problem on their property, which is located northwest of and upstream from appellants' property. A lack of maintenance of a downstream area of the watershed that is upstream from appellants' property, including a rotted culvert pipe underneath a driveway on the King property, caused much of the flooding problem. At that time, appellants had both surface and subsurface drains on their property, and they claim that they had no drainage problem during this period.

In response to the complaints, Byrd contacted the property owners in the watershed, and a meeting was held in September 1993. Because the property owners could not agree about forming a private group to rectify the drainage problems in the watershed, Byrd advised them to petition the district. The property owners, including appellant Murray E. Elsass, then signed a petition requesting that the district assist them in the planning and construction of works of improvement needed to "[i]mprove drainage an[d] reduce flooding" in the watershed. Although no construction plans had been drafted for the project at the time the petition was signed, Byrd explained to the property owners present at the meeting, including appellant Murray E. Elsass, that new surface and subsurface drains would have to be constructed on the property. On September 21, 1993, the district, through its board of supervisors, approved the project, which was known as the King-Elsass Ditch Drainage Improvement Project ("project").

The project was placed on a waiting list until 1997, and in July 1997, the district board of supervisors held a public meeting concerning the project. At this meeting, the details of the project were discussed. Appellant Murray E. Elsass attended the meeting and did not object to the proposed project.

On August 19, 1997, the board of supervisors of the district certified the project to appellee Shelby County Board of Commissioners ("board"). In accordance with R.C. 1515.20 through 1515.24, the board determined that construction of the project would improve water management and development of the lands therein, that the costs of the project would be less than the benefits, and that the project would benefit the land by promoting its economic, agricultural, and social development. The purpose of the project was to relocate the surface flow of water in the area by correcting drainage conditions upstream from appellants' property and channeling water through appellants' property and into the creek through a drainage pipe. On December 11, 1997, the board accepted the project as certified by the district and as recommended by the county engineer. The board authorized the advertisement and legal notice for bids to perform the work required for the project, which included the installation of about one thousand four hundred feet of corrugated plastic tubing and the construction of approximately 1,375 feet of surface drain and various erosion-control structures. The board subsequently awarded the contract to Ruhenkamp Farm Drainage, Inc. for approximately $26,000. The board then assessed property owners in the watershed to pay for the cost of the project pursuant to R.C. 1515.24. Appellants were assessed approximately $1,518.

At the request of appellant Murray E. Elsass, Ruhenkamp Farm Drainage, Inc. waited for appellants' tenant to harvest his crops before it began construction of the project in mid-August 1998. Appellees, the board and the individual commissioners, did not obtain an easement, right-of-way, or license from appellants before constructing the project. During the construction, the contractor entered appellants' property and installed surface and subsurface drains across and under the property. The surface drain or Swale constructed on appellants' property is approximately eight hundred fifty feet long and fifty feet wide, with a maximum depth of two and a half feet. The preexisting surface drain on appellants' property was straightened and deepened to make it easier to farm through and across the drain. The contractor also constructed a subsurface drain that followed the approximate path of the old underground drain on appellants' property and a rock shoot that emptied into Loramie Creek.

During the construction of the project, appellants did not complain about it, and Byrd explained to appellant Murray E. Elsass what the project would look like upon its completion. The contractor complied with appellant Murray E. Elsass's request to correct a farm driveway so that appellants' tenant would not tip his farm equipment. The project was completed in September 1998. The board paid the contractor after it was satisfied that the project was completed in accordance with plans presented by the district and the county engineer. Under R.C. 1515.29, the board has a continuing duty to maintain the completed improvement.

In October 1998, appellant Murray E. Elsass, through counsel, asserted that the drainage project had resulted in a "taking" of his real property and requested that the board compensate him. Appellants had not objected to the construction of the project before that time. Appellees refused to initiate appropriation proceedings or otherwise compensate appellants for their use of appellants' property in the construction of the project.

In July 1999, appellants filed a complaint in the Court of Appeals for Shelby County for a writ of mandamus to compel appellees to institute appropriation proceedings for the uncompensated taking of their property in connection with the project and for other relief. Appellees filed an answer claiming that appellants consented to the construction of the project and were therefore estopped from claiming damages from the county. In October 1999, the court of appeals ordered the parties to file all evidence on or before November 15, 1999.

On the date specified by the court, the parties submitted evidence. According to appellants' evidence, construction of the project on their property limited access to a bridge crossing Loramie Creek, concentrated the flow of water in specific areas of appellants' property, and diminished crop yields. In addition, appellant Murray E. Elsass specified that construction of the project limited appellants' ability to use their real property for nonagricultural purposes and inhibited future development. Conversely, appellees' evidence indicated that appellants' property was benefited by the project and that there was no limitation of access.

The court of appeals subsequently granted the parties' motions to submit additional evidence and to extend the time to file briefs. The additional evidence submitted by appellants included a November 1999 appraisal of the ditch project concluding that the highest and best use of the property, presently zoned "U-1 rural district," is its current agricultural use, that the project did not damage the residue of appellants' property, and that, at most, there could be a possible loss of $100 in crop yield in 1999 attributable to the project.

The parties filed briefs in December 1999, and in May 2000, appellants filed a motion for leave to submit additional evidence. The evidence consisted of photographs purporting to depict appellants' property at that time, i.e., after the crops had been harvested. The court of appeals denied appellants' May 2000 motion to submit this additional evidence.

In October 2000, the court of appeals denied the writ, concluding that any physical invasion of appellants' property occurred with their consent and by their invitation, that no fundamental attribute of appellants' ownership of their property was destroyed by the project, and that appellants' property still had an economically viable use.

This cause is now before the court upon the Elsasses' appeal of right, as is their request for oral argument.

Oral Argument

Appellants request oral argument, claiming that this appeal raises a substantial constitutional issue regarding the taking of private property without just compensation and is a matter of great public importance concerning the applicable standard to be applied in inverse condemnation cases. We deny appellants' request. We have resolved comparable cases without the necessity of oral argument. See, e.g., State ex rel. BSW Dev. Group v. Dayton (1998), 83 Ohio St.3d 338, 699 N.E.2d 1271. And more important, the parties' briefs are sufficient to resolve this appeal. See State ex rel. Abner v. Elliott (1999), 85 Ohio St.3d 11, 16, 706 N.E.2d 765, 769.

Submission of Evidence

Appellants contend that the court of appeals erred in denying their motion for leave to submit additional evidence outside the timetable set by the court for the submission of evidence. The admission of evidence is normally...

To continue reading

Request your trial
51 cases
  • Xxl of Ohio, Inc. v. City of Broadview Heights
    • United States
    • U.S. District Court — Northern District of Ohio
    • January 13, 2004
    ...a writ of mandamus, a remedy which the Ohio Supreme Court calls "extraordinary relief." State ex rel. Elsass v. Shelby County Bd. of Comm'rs, 92 Ohio St.3d 529, 534-35, 751 N.E.2d 1032, 1037 (2001); see discussion at Tri-Corp Mgmt. Co. v. Praznik, 33 Fed.Appx. 742, 749-50 (6th Cir.2002). Mo......
  • Mathews v. Ohio Pub. Emps. Ret. Sys.
    • United States
    • U.S. District Court — Southern District of Ohio
    • March 12, 2015
    ...of discretion’ means an unreasonable, arbitrary, or unconscionable decision.” Id. (quoting State ex rel. Elsass v. Shelby Cnty. Bd. of Commrs., 92 Ohio St.3d 529, 533, 751 N.E.2d 1032 (2001) ). Plaintiff could have filed a mandamus action to challenge the termination of his disability benef......
  • State v. Thomas C. Rector
    • United States
    • Ohio Court of Appeals
    • December 31, 2002
    ... ... discretion." State ex rel. Elsass v. Shelby Cty. Bd ... of Commrs. (2001), 92 Ohio ... ...
  • Coles v. Granville
    • United States
    • U.S. Court of Appeals — Sixth Circuit
    • May 22, 2006
    ...proceedings in a case where the plaintiffs alleged a physical taking of their property. See Elsass v. Shelby County Bd. of Comm'rs, 92 Ohio St.3d 529, 751 N.E.2d 1032, 1039 (2001). The Ohio Supreme Court has since addressed a physical and at least two regulatory takings cases, and in all th......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT