State ex rel. Hooten Const. Co., Inc. v. Borsberry Const. Co., Inc.

Decision Date21 February 1989
Docket NumberNo. 17711,17711
Citation108 N.M. 192,1989 NMSC 7,769 P.2d 726
PartiesThe STATE of New Mexico, ex rel. HOOTEN CONSTRUCTION COMPANY, INC., and Hooten Construction Company, Inc., a New Mexico corporation, Plaintiffs-Appellees, v. BORSBERRY CONSTRUCTION COMPANY, INC., a Texas corporation, Defendant-Appellant, and Mid-Continent Casualty Company, an Oklahoma corporation, Defendant.
CourtNew Mexico Supreme Court
OPINION

SOSA, Chief Justice.

In accordance with the provisions set forth in our Uniform Arbitration Act, NMSA 1978, Sections 44-7-1 through -22, Borsberry Construction Company, a general contractor, appeals the order of confirmation of an arbitration award in favor of the subcontractor, Hooten Construction Company, and judgment entered thereon. Implicit in the appeal is a claim of error in the denial by the district court of Borsberry's application to vacate, modify, or correct the award filed pursuant to Sections 44-7-12 and -13.

In July 1986, Borsberry contracted with the State for construction of a road in Dona Ana County and entered into a subcontract with Hooten for performance of certain work on the project. The subcontract provided for the submission to arbitration of any controversies arising between the parties with regard to matters covered by the subcontract. In December 1986, a dispute concerning claimed amounts due Hooten for work performed on the project resulted in a two-day arbitration hearing. The panel of three arbitrators unanimously awarded Hooten damages in the amount of $126,709 on September 4, 1987.

The district court entertained competing applications on the award, determined Borsberry failed to prove statutory grounds for vacation, modification, or correction, and granted Hooten's application for confirmation of the award. See NMSA 1978, Secs. 44-7-11 to -14. We affirm the district court's confirmation of the arbitration award and judgment entered thereon.

Once an arbitration award is entered, the finality that courts should afford the arbitration process weighs heavily in favor of the award. Foster v. Turley, 808 F.2d 38, 42 (10th Cir.1986). Courts are justified in exercising great caution when asked to set aside an arbitration award, which is the product of the theoretically informal, speedy and inexpensive process of arbitration, freely chosen by the parties. Ormsbee Dev. Co. v. Grace, 668 F.2d 1140, 1147 (10th Cir.), cert. denied, 459 U.S. 838, 103 S.Ct. 84, 74 L.Ed.2d 79 (1982). All doubts are to be resolved in favor of arbitrability. Id. Furthermore, the district court's review of an arbitration award is limited by the statutory grounds set forth in our Uniform Arbitration Act. See NMSA 1978, Secs. 44-7-12, -13; Foster, 808 F.2d at 42 (judicial review of arbitration award is narrowly limited). It is not the function of the court to hear the case de novo and consider the evidence presented to the arbitrators. Foley Co. v. Grindsted Prods., Inc., 233 Kan. 339, 348-49, 662 P.2d 1254, 1262 (1983); see also Ormsbee, 668 F.2d at 1147 (court not entitled to judge arbitration award independently). In reaching its determination on Borsberry's application to vacate, modify, or correct the award, the court properly conducted an evidentiary hearing and entered findings of fact and conclusions of law upon each issue raised in the application. See Malibu Pools of New Mexico, Inc. v. Harvard, 97 N.M. 106, 637 P.2d 537 (1981) (district court must consider all evidence relevant and material to applicant's bases for vacation of arbitration award).

This court is required by Section 44-7-19(B) to take the appeal "in the manner and to the same extent as from orders or judgments in a civil action." We will not disturb findings made by the district court which are supported by substantial evidence. Elephant Butte Resort Marina, Inc. v. Wooldridge, 102 N.M. 286, 694 P.2d 1351 (1985). Substantial evidence means such relevant evidence as a reasonable mind might accept as adequate to support a conclusion. Id. at 291, 694 P.2d at 1356. This court will indulge all reasonable inferences and resolve all disputed facts in favor of the trial court findings. Tapia v. Panhandle Steel Erectors Co., 78 N.M. 86, 89, 428 P.2d 625, 628 (1967). Moreover, in reviewing an attack upon a finding, it is the supporting evidence, not that adverse to the findings, that ordinarily determines the issue. Gish v. Hart, 75 N.M. 765, 768, 411 P.2d 349, 352 (1966).

The issues raised by Borsberry are identical to those raised in its application to vacate, modify, or correct, and, we are mindful that on appeal it is not our function to reweigh the evidence and substitute our judgment for that of the district court. See Elephant Butte Resort Marina, Inc., 102 N.M. at 291, 694 P.2d at 1356. Borsberry contends the district court erred in not vacating the arbitration award, claiming it successfully proved the following statutory grounds for vacation of the award: (1) the Section 44-7-12(A)(1) ground for procurement of an award by undue means based upon Borsberry's characterization that a memorandum of law submitted to the arbitration panel by Hooten was an improper ex parte communication; (2) the Section 44-7-12(A)(3) ground that the arbitrators exceeded their authority based upon (a) an allegation that the arbitrators refused to award completion costs, (b) an award of damages for work performed (preblading) which was allegedly not specified in the subcontract, (c) an award of water expense damages, and (d) an order of payment by a fixed date, and (3) the Section 44-7-12(A)(4) ground that the arbitrators refused to postpone the hearing at Borsberry's request until work on the project could be completed in order to more accurately determine damages. In other words, Borsberry claims error in most of the findings of fact and conclusions of law entered by the district court. An additional issue raised on appeal is whether the district court abused its discretion in awarding prejudgment interest.

The following is a summary of the findings material to Borsberry's first claim that the memorandum of law submitted by Hooten was an improper ex parte communication which constituted a sufficient basis to vacate the award under Section 44-7-12(A)(1): Four days after the conclusion of the arbitration hearing, Hooten mailed a "Memorandum of Law Concerning Recovery of Damages for Breach of Contract" to the arbitrators and to opposing counsel. Borsberry did not consent to the submission of the memorandum. Arbitrator Livingston testified that he received and looked at the memorandum but did not consider it in arriving at his decision. While in session, the panel, consisting of arbitrators capable and experienced in the type of construction work that was involved in the controversy between the parties, did not read, review or discuss the memorandum. Although the arbitrators were in deliberations on the date Borsberry received the memorandum, Borsberry did not request the panel to give it an opportunity to file a responsive memorandum. In sum, the district court found that, based upon the evidence submitted, the arbitrators were not affected by the memorandum in making the award.

Borsberry, however, continues to claim prejudice, asserting that it received inadequate notice of the submission of the memorandum, and urges this court to adopt a per se rule of impropriety as stated in Hewitt v. Village of Reed City, 124 Mich. 6, 82 N.W. 616 (1900). In Hewitt, after "the parties expressly agreed that neither was to be represented by counsel, thereby stipulating to exclude all legal arguments or briefs," the court rendered the arbitrator's award void based upon an improper ex parte presentation of a list of authorities by the village to the arbitrator after final submission. Id. at 8, 82 N.W. at 616-17. Deeming necessary strict compliance with "the spirit of the terms of the submission," the court held irrelevant the issue of whether the arbitrator was influenced by the ex parte communication. Presumably, because this case predates the Uniform Arbitraton Act, the Michigan Supreme Court in this case of first impression was apparently setting down a hard and fast rule to be followed in arbitration proceedings with regard to the submission of material to arbitrators.

In the more recent case of Foley Co. v. Grindsted Products, Inc., 233 Kan. 339, 662 P.2d 1254 (1983), factually identical to the case at bar, the district court found that the submission of a letter brief by a subcontractor to the arbitration panel did not constitute an ex parte communication. In confirming the award, the court found persuasive the facts that the letter brief had been submitted in response to the contractor's statement at the arbitration hearing that it would be submitting a brief, that the arbitrators did not review or discuss the brief, that the brief was delivered to opposing counsel as well as to the panel, and that the contractor eventually failed to file a brief, respond, or object to the subcontractor's submission of one.

In the instant case, the district court observed that had a record of the arbitration hearing been made, "[it] would probably have reflected that every one of these things was specifically argued to the arbitrators. They were certainly the kinds of things that you could have argued to the arbitrators." Noting that both parties had a full and fair opportunity to present evidence to the arbitrators and that Borsberry had received a copy of the memorandum, the court concluded that "[a]ny presumption that the Memorandum constitutes...

To continue reading

Request your trial
22 cases
  • 1996 -NMSC- 78, Sims v. Sims
    • United States
    • New Mexico Supreme Court
    • December 6, 1996
    ...contrary to the logical conclusions demanded by the facts and circumstances of the case. State ex rel. Hooten Constr. Co. v. Borsberry Constr. Co., 108 N.M. 192, 193, 769 P.2d 726, 727 (1989); State v. Simonson, 100 N.M. 297, 301, 669 P.2d 1092, 1096 (1983); Flinchum Constr. Co. v. Central ......
  • United Technology and Resources, Inc. v. Dar Al Islam
    • United States
    • New Mexico Supreme Court
    • January 12, 1993
    ...arbitration award is narrowly limited by the statutory grounds established in the Act. State ex rel. Hooten Constr. Co. Inc. v. Borsberry Constr. Co. Inc., 108 N.M. 192, 193, 769 P.2d 726, 727 (1989). Section 44-7-11 of the Act Upon application of a party, the court shall confirm an award, ......
  • National Ave. Bldg. Co. v. Stewart
    • United States
    • Missouri Court of Appeals
    • July 31, 1998
    ...Harsen v. Board of Education, 132 N.J.Super. 365, 333 A.2d 580, 591 (Law Div.1975); New Mexico, ex rel. Hooten Constr. Co. v. Borsberry Constr. Co., 108 N.M. 192, 769 P.2d 726, 729-30 (1989); Durant v. Motor Vehicle Accident Indemnification Corp., 15 N.Y.2d 408, 260 N.Y.S.2d 1, 207 N.E.2d 6......
  • Fernandez v. Farmers Ins. Co. of Arizona
    • United States
    • New Mexico Supreme Court
    • July 7, 1993
    ...This process allows for the informal, speedy, and inexpensive final disposition of disputes, State ex rel. Hooten Constr. Co. v. Borsberry Constr. Co., 108 N.M. 192, 193, 769 P.2d 726, 727 (1989), and also aids in relieving the judiciary's heavily burdened caseload, see United Technology, 1......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT