Sterling Elec. Co. v. Kent

Decision Date19 January 1951
Docket NumberNo. 35322,35322
Citation45 N.W.2d 709,233 Minn. 31
PartiesSTERLING ELECTRIC CO. v. KENT et al.
CourtMinnesota Supreme Court

Syllabus by the Court

The filing of a mechanics' lien statement of record is not the commencement of an 'action or other proceeding * * * for the enforcement of such lien' within the meaning of M.S.A. § 514.07. Lien of subcontractor for labor and materials furnished in improvement of real property Held valid and enforceable under § 514.07 and § 514.08 where proper statement of claim therefor was filed within 15 days after completion of its subcontract, distinguishing Clark v. Anderson, 88 Minn. 200, 92 N.W. 964, decided under L.1899, c. 277.

Kelly, Berglund & Johnson and Fred N. Furber (of Fowler, Youngquist, Furber, Taney & Johnson), all of Minneapolis, for appellant.

Wagner & Bailey, Minneapolis, for respondent.

CHRISTIANSON, Justice.

This is an appeal from an order denying appellant's motion for a new trial after findings for plaintiff in an action to foreclose a mechanic's lien filed by plaintiff against appellant's property.

Appellant owns the premises upon which its hospital is located in the city of Minneapolis. It entered into a contract with defendant Kent Engineering Company (hereinafter called Kent) for the installation of a new generator and boiler in its hospital. Kent subcontracted part of the work to plaintiff. Pursuant to its subcontract, plaintiff furnished and installed certain electrical materials, wiring, and devices in connection with said installation, including a generator switchboard and motors and controls for the new boiler. The last item of labor and materials furnished by plaintiff toward this improvement was on October 8, 1947. The reasonable value of the labor and materials so furnished by plaintiff amounted to $10,983.90. Kent paid plaintiff only $1,000, leaving a balance of $9,983.90 due plaintiff therefor.

On October 23, 1947, plaintiff filed a proper mechanic's lien statement with the registrar of titles against the property it had improved. On September 30, 1948, appropriate proceedings were instituted by plaintiff to foreclose and enforce its mechanic's lien. After trial of the foreclosure action, the trial court made findings and conclusions in favor of plaintiff and ordered that judgment of foreclosure be entered. A default money judgment was also ordered against the general contractor. The property owner alone appeals.

The sole question presented is whether a mechanic's lien statement filed by a subcontractor within 15 days after completion of his subcontract is ineffectual and invalid under M.S.A. § 514.07.

Appellant takes the position that § 514.07 prohibits the filing of a mechanic's lien statement until at least 15 days have elapsed after the completion of the contract upon which the lien is based, and that plaintiff's lien is invalid and unenforceable because its lien statement was filed within 15 days after the completion of its subcontract.

Section 514.07 provides in part: '* * * The owner, within 15 days after the completion of the contract, may require any person having a lien hereunder, by written request therefor, to furnish to him an itemized and verified account of his lien claim, the amount thereof, and his name and address; and No action or other proceeding shall be commenced for the enforcement of such lien until ten days after such statement is so furnished.' 1 (Italics supplied.)

The only provision of our lien law expressly governing the time within which lien statements must be filed appears in § 514.08. 2 Its provisions are plain and explicit: 'The lien shall cease at the end of 90 days after doing the last of such work, or furnishing the last item of such skill, material, or machinery, Unless within such period a statement of the claim therefor, be filed for record * * *.' (Italics supplied.) Section 514.08 expressly authorizes the filing of a lien statement at any time within 90 days after the lien claimant has contributed his last item of labor or material. See, Lamoreaux v. Andersch, 128 Minn. 261, 269, 150 N.W. 908, 912, L.R.A. 1915D, 204; A. Y. McDonald Mfg. Co. v. Lima, 187 Minn. 240, 242, 244 N.W. 804, 805.

Prior to 1905, a 'contractor' was expressly prohibited by L.1899, c. 277, from filing a mechanic's lien statement prior to the expiration of 15 days from the completion of his contract. Clark v. Anderson, 88 Minn. 200, 92 N.W. 964. However, this prohibition was omitted in the revision of our laws in 1905. See, R.L.1905, § 3510. The statutory language quoted from § 514.07 has been the same ever since the 1905 revision. Likewise, the provisions of § 514.08 prescribing the time within which a lien statement can be filed have remained the same for more than 45 years. See, R.L. 1905, § 3511.

Sections 514.07 and 514.08 were reenacted in their present form when our revised statutes, M.S.A., were adopted in 1945. The filing of lien statements has been governed exclusively by § 514.08 since 1905.

As stated by this court in Re Estate of Cravens, 177 Minn. 437, 440, 225 N.W. 398, 399: 'In re-enacting a statute, intention to change meaning may as clearly appear from the omission of old as by adding new language.' Moreover, where the meaning of a revised statute is free from ambiguity, the prior law cannot be resorted to for the purpose of creating ambiguity. The change in the prior law, when clear and unambiguous, must be given full effect. Champ v. Brown, 197 Minn. 49, 266 N.W. 94; State v. Stroschein, 99 Minn. 248, 109 N.W. 235. See, Rice v. City of St. Paul, 208 Minn. 509, 295 N.W. 529.

Appellant contends, however, that the...

To continue reading

Request your trial
7 cases
  • Anderson v. Federated Mut. Ins. Co.
    • United States
    • Minnesota Court of Appeals
    • 15 Enero 1991
    ...by adding new language. (In re Estate of Cravens, 177 Minn. 437, 440, 225 N.W. 398, 399 (1929), quoted in Sterling Electric Co. v. Kent, 233 Minn. 31, 34, 45 N.W.2d 709, 711 (1951)); see also Garberg v. County of Hennepin, 294 Minn. 450, 455, 202 N.W.2d 220, 223 (1972). The predecessor act ......
  • Northwest Wholesale Lumber, Inc. v. Citadel Co., C5-89-1866
    • United States
    • Minnesota Court of Appeals
    • 12 Junio 1990
    ...time period is the means of perfecting a mechanics' lien claim. Minn.Stat. Sec. 514.08 (Supp.1983); Sterling Electric Co. v. Kent, 233 Minn. 31, 34, 45 N.W.2d 709, 711 (1951). Once a lienholder has filed the lien statement and served a copy of it on the property owner, the action to enforce......
  • Eclipse Architectural Grp., Inc. v. Lam
    • United States
    • Minnesota Supreme Court
    • 2 Mayo 2012
    ...the lien, but to preserve and continue it.” Hill v. Lovell, 47 Minn. 293, 294, 50 N.W. 81, 81 (1891); accord Sterling Elec. Co. v. Kent, 233 Minn. 31, 34, 45 N.W.2d 709, 711 (1951) (explaining that filing a lien statement “is not the commencement of an action or proceeding to enforce the li......
  • U.S. Sprint Communications Co., Ltd. v. Commissioner of Revenue, C5-97-1993
    • United States
    • Minnesota Supreme Court
    • 21 Mayo 1998
    ...N.W.2d 23, 26 (Minn.1981) (there is no room for judicial construction when the statute speaks for itself); Sterling Elec. Co. v. Kent, 233 Minn. 31, 34, 45 N.W.2d 709, 711 (1951) (where the meaning of a revised statute is free from ambiguity, prior law cannot be resorted to for purpose of c......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT