Stover v. City of Springfield

Citation152 S.W. 122,167 Mo. App. 328
PartiesSTOVER et al. v. CITY OF SPRINGFIELD et al.
Decision Date02 December 1912
CourtCourt of Appeal of Missouri (US)

A contract for the construction of a district sewer fixed the price per lineal foot for all excavation of 6 feet and under 8 feet at 30 cents; 8 feet and under 10 feet, 25 cents; * * * 16 feet and under 18 feet, 60 cents, etc.; price per lineal foot for rock trench per foot in depth, 25 cents; and declared that only such ledge rock, limestone as required blasting for removal should be estimated as rock excavation, and should be paid for by the lineal foot, depth of earth excavation to cease where rock excavation began. The evidence showed that in the doing of the work rock was found at the bottom of the ditch, but at what section or how deep the excavations were at places where rock was found was not shown. Held, that parol evidence of the practice in the city to allow the 25 cents per lineal foot for rock excavation in addition to the amount charged had earth extended to the bottom was admissible to show that the contractor was entitled to charge for excavation in accordance with such practice.

9. EVIDENCE (§ 448) — PAROL EVIDENCE — INTENTION OF PARTIES.

A contract must be construed as a whole, and, where its terms are clear when so construed, the court must declare as a matter of law the meaning of the contract, but, where it is not clear, parol testimony may be resorted to to show the condition of the matter about which the contract was made.

10. CONTRACTS (§ 170) — CONSTRUCTION — CONTEMPORANEOUS CONSTRUCTION.

The court in construing an ambiguous contract may consider the construction placed on it by the parties themselves, as an aid in determining the intention of the parties by the language used.

11. MUNICIPAL CORPORATIONS (§ 518) — PUBLIC IMPROVEMENTS — SPECIAL TAX BILLS.

The court, foreclosing special tax bills not paid within six months as provided by law, properly computes interest at 15 per cent. to the date of judgment; but the judgment will bear but 6 per cent. interest from its rendition.

Nixon, P. J., dissenting.

Appeal from Circuit Court, Greene County; James T. Neville, Judge.

Action by J. P. Stover and others against the City of Springfield and another. From a judgment for defendants, plaintiffs appeal. Affirmed.

Henry C. Young, of Springfield, for appellants. Barbour & McDavid, of Springfield, for respondents.

COX, J.

Action by certain property owners to cancel special tax bills issued to defendant Plummer as contractor in payment for the construction of a district sewer in the city of Springfield. The defendants in their answer alleged compliance with the law and ordinances of the city and asked for a foreclosure of the lien of the tax bills issued against the property of the plaintiffs. The trial court found for the defendants, except that he reduced the amount of each bill 10 per cent. and then ordered foreclosure for the remainder of the tax bills. Plaintiffs have appealed.

The questions upon which plaintiffs rely for a reversal of the judgment are: First. That the contract for putting in the sewer was let at a price in excess of the preliminary estimate of the city engineer. Second. That material changes were made in the construction of the sewer after the contract was let, by the addition of laterals not called for in the contract and by omitting other parts that were called for in the contract. Third. That there was a change of grade after the contract was made. Fourth. That there was a double charge for excavating by charging for both dirt and rock in the same part of the ditch. Fifth. That the court erred in excluding certain testimony offered by the plaintiffs.

As to the first point, we do not think the contention is sustained by the testimony. The estimate of the engineer itemized the work and the cost. He estimated that it would require 1,705 lineal feet of 8-inch pipe including Y's, branches and joints, two lamp holes, two flush tanks, four manholes, etc. The excavation was classified and a separate estimate put upon all excavations including back filling, 6 feet and under 8 feet being in one class; 8 feet and under 10 feet in...

To continue reading

Request your trial
21 cases
  • Haeussler Investment Company v. Bates
    • United States
    • Missouri Supreme Court
    • December 30, 1924
    ...v. Paving Co., 214 Mo. 1; Steffen v. Fox, 124 Mo. 630; St. Louis v. Ruecking, 232 Mo. 325; Johnson v. Duer, 115 Mo. 366; Stover v. Springfield, 167 Mo.App. 328; Meyers v. Wood, 173 Mo.App. 564. (12) Before a of equity will enjoin the collection of the tax on account of its being excessive, ......
  • Missouri Service Co. v. City of Stanberry
    • United States
    • Missouri Supreme Court
    • July 30, 1937
    ... ... statute there cited are sufficient, we think, to indicate ... that this point raised by the appellants has no merit. [See, ... also, Stover v. City of Springfield, 167 Mo.App. 328, 152 ... S.W. 122.] ...          V ... Question is raised as to the propriety of the city's ... ...
  • Gratz v. City of Kirkwood
    • United States
    • Missouri Court of Appeals
    • April 7, 1914
    ...Ordinance No. 572. Webb City v. Aylor, 163 Mo.App. 155; Cravens v. Ins. Co., 148 Mo. 583; Gratz v. Wycoff, 165 Mo.App. 196; Stover v. Springfield, 167 Mo.App. 328. (3) There no lack of definiteness in Winter's contract in respect to line, grade, form or dimensions of the work. Sec. 16 of Or......
  • Alsmeier v. Adams
    • United States
    • Indiana Appellate Court
    • July 1, 1914
    ...every purpose and use intended under the ordinance and contract as originally made. This court, in the case of Stover v. City of Springfield, 167 Mo. App. 328, 152 S. W. 122, held that such a change would not invalidate tax bills, and to the same effect is the decision of the St. Louis Cour......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT