Structure & Design v. Contemporary Concepts

Decision Date28 December 2004
Docket NumberNo. WD 63682.,WD 63682.
Citation151 S.W.3d 904
PartiesSTRUCTURE AND DESIGN, UNLIMITED, INC., Respondent, v. CONTEMPORARY CONCEPTS BUILDING AND DESIGN, INC., and Ozark Gardens Apartments, L.L.C., Appellants.
CourtMissouri Court of Appeals

Michael Carter, Ronald Carpenter, Camdenton, for Appellant.

Lewis Z. Bridges, Lake Ozark, for Respondent.

PAUL M. SPINDEN, Judge.

The parties to this lawsuit are disputing a mechanic's lien that Structure and Design Unlimited, Inc., attached to an apartment building in Miller County. As the contractor overseeing the building's relocation 800 yards to a new tract, Contemporary Concepts Building and Design, Inc., contracted in 2001 with Structure and Design to split the building into three units for the move and to reattach the units after the move. Contemporary Concepts terminated the contract before the project was complete on the ground that Structure and Design breached the contract by over-charging for labor.

After deciding that Structure and Design was over-charging, Contemporary Concepts refused to pay it the final two installments under the contract. Structure and Design filed a mechanic's lien for $71,059.23 on the building, owned by Ozark Gardens Apartment, L.L.C. Structure and Design also sued Contemporary Concepts, Ozark Garden, Central Bank of the Lake of the Ozarks, which held a mortgage interest in the building, and John Curran, trustee. Structure and Design dismissed its action against Central Bank and Curran, and, after trial, the circuit court entered judgment for Structure and Design but assessed damages at $34,151.23. The circuit court vitiated Structure and Design's lien on the building because the lien did not contain a "just and true account," and the circuit court rejected Structure and Design's request for attorney fees and interest.

Structure and Design appeals. We affirm the portion of the circuit court's judgment vitiating Structure and Design's lien. We reverse the circuit court's judgment and remand for it to enter a proper assessment of damages for breach of contract.

1. "Just and True Account"

The circuit court vitiated Structure and Design's lien on the ground that the lien did not contain a "just and true account." For Structure and Design to obtain a lien on the building, Section 429.080, RSMo 2000, required it to file with the circuit court clerk, "within six months after the indebtedness shall have accrued[,] ... a just and true account of the demand due [it] after all just credits have been given[.]" The circuit court concluded that Structure and Design's lien did not contain a just and true account:

[Structure and Design] included within its lien statement charges for rental property, which are not lienable items. (429.080 RSMo) In addition, the uncontradicted testimony at trial was that there were overbilled hours of $4,082.00 that were not related to this ... project (the work was actually done for Prewitt's Highway 54 Enterprises); that all hours shown on the lien statement were not correct ([Structure and Design's employee,] Diana Harrison [,] testified that she just didn't write in the correct name but put "new laborers" hours under "prior laborers" names[)]; that [Structure and Design] had agreed not to charge for any work done after September 21, 2003, [sic] and in fact did charge for work performed September 24, 2001-September 28, 2001.

Competent and substantial evidence supports the circuit court's judgment. In reviewing a decision concerning mechanic's liens, we are obligated to affirm the circuit court's judgment "unless there is no substantial evidence to support it, unless it is against the weight of the evidence, or unless it erroneously declares or applies the law." Commercial Openings, Inc. v. Mathews, 819 S.W.2d 347, 349 (Mo. banc 1991) (quotation omitted).

The circuit court correctly focused on whether or not Structure and Design's lien set forth a just and true account of the $71,059.23 that it claimed for the project. Without a just and true account, a lien claimant has no rights. See Sears, Roebuck and Company v. Seven Palms Motor Inn, Inc., 530 S.W.2d 695, 698 (Mo. banc 1975). The General Assembly did not define "just and true," and the courts have not been exacting in explaining their interpretations of the term. This court's Eastern District has set out the most definitive definition: "A lien statement may be regarded as just and true if it contains mistakes or errors of omission, as long as those inaccuracies are unintentional and are the result of honest inadvertence, accident, or oversight, and do not result from deliberate intention or design." Dave Kolb Grading, Inc. v. Lieberman Corporation, 837 S.W.2d 924, 933 (Mo.App.1992). Including nonlienable items does not necessarily vitiate the entire lien so long as the nonlienable items were included by honest mistake and can be separated from the lienable items. Sears, 530 S.W.2d at 698-99. The lienor bears the burden of proving that mistakes or omissions were "due to an honest mistake." City-Wide Asphalt Company, Inc. v. Industrial Paving, Inc., 838 S.W.2d 480, 482 (Mo.App.1992).

Rental equipment is not subject to a mechanic's lien. Bush Construction Machinery, Inc. v. Kansas City Factory Outlets, L.L.C., 81 S.W.3d 121, 126 (Mo.App.2002). Structure and Design acknowledges that it wrongly included rental equipment in its mechanic's lien, but it argues that its lien should be enforced because no one established that it had acted intentionally. Structure and Design misperceives the law. As the mechanic's lien claimant, Structure and Design had the burden of proving that it included rental equipment by honest mistake. City-Wide Asphalt, 838 S.W.2d at 482. Structure and Design did not produce any evidence that its error resulted from honest inadvertence.

Structure and Design failed to carry its burden. Because substantial evidence supported the circuit court's determination that Structure and Design's lien did not contain a just and true account, we affirm that portion of the judgment vitiating Structure and Design's lien.

2. Damages

Structure and Design next argues that substantial evidence did not support the circuit court's assessment of only $34,151.23 in damages, rather than granting its prayer for $68,771.23. The circuit court explained that it reduced the award because Structure and Design had charged too much.

First, the circuit court reduced the judgment by $12,903 because Structure and Design had billed laborers at $26 an hour rather than the agreed-upon rate of $23 an hour. Byno Davidson, who was Structure and Design's lead carpenter during this project and who supervised workers on the job site, testified that, based on his knowledge of the workers' knowledge and skill levels, several of the workers billed as carpenters were laborers or less skilled than others billed at the carpenter rate. In addition, Structure's lien claim provided hourly totals billed for each individual worker. This was enough evidence to support the circuit court's decision.

Next, the circuit court reduced the award by $1,870 for charges related to work Structure and Design did on an unrelated project. This reduction appears to be a mistake. Structure and Design originally prayed for $71,059.23. At trial, Structure and Design acknowledged several billing errors, including $1,870 improperly invoiced and $416 improperly billed for a worker. Structure and Design reduced the amount requested to $68,771.23 to credit Contemporary Concepts for these billing errors. Thus, the circuit court erred by further reducing the $68,771.23 by $1,870.

Third, the circuit court reduced the award by $5,000 because they were for charges for work done the week after the project was terminated. Structure and Design's brief does not address this reduction, so we do not.

Fourth, the circuit court reduced its judgment by $6,250, the amount that Structure and Design charged for work performed by Lester Pomykala on the project. According to Structure and Design's time records, Pomykala worked eight hours a day on nearly every day of the project, but Davidson testified that Pomykala did only "a little bit of work [on the job site]." Other evidence indicated that Pomykala did not work on the project. Structure and Design contended that this discrepancy resulted from its use of "floating men," or temporary workers whose names were not added to Structure and Design's books but who would work when named workers were not present. Structure and Design asserted that it would credit the regular employee with the hours on paper, but it would pay the floating man rather than the named worker. The circuit court, however, was not obligated to believe Structure and Design's explanation. Evidence supported the circuit court's decision to reduce Structure and Design's judgment by amounts charged for Pomykala's work.

Fifth, the circuit court reduced the judgment by $6,000, the amount...

To continue reading

Request your trial
12 cases
  • Scott v. Blue Springs Ford Sales, Inc.
    • United States
    • Missouri Court of Appeals
    • November 21, 2006
    ...our review of the error claimed in this point is not for an abuse of discretion. See Structure & Design Unlimited, Inc. v. Contemporary Concepts Bldg. & Design, Inc., 151 S.W.3d 904, 910 (Mo.App.2004) (recognizing that normally we review a trial court's decision as to a request for attorney......
  • Glenstone Block Co. v. Pebworth
    • United States
    • Missouri Court of Appeals
    • October 1, 2008
    ...of the evidence, or unless it erroneously declares or applies the law.'" Structure and Design, Unlimited, Inc. v. Contemporary Concepts Building and Design, Inc., 151 S.W.3d 904, 907 (Mo.App.2004) (quoting Commercial Openings, Inc. v. Mathews, 819 S.W.2d 347, 349 (Mo. banc 1991)). As previo......
  • Custom Constr. Sols. v. B & P Constr.
    • United States
    • Missouri Court of Appeals
    • November 28, 2023
    ... CUSTOM CONSTRUCTION SOLUTIONS, LLC, and CANNON DESIGN, INC., Plaintiffs/ Respondents, v. B & P CONSTRUCTION, INC., et al ... to provide data and analysis for the existing structure of ... the Railway Exchange Building. Geotechnology performed its ... Structure ... &Design, Unlimited, Inc. v. Contemp. Concepts Bldg ... &Design, Inc. , 151 S.W.3d 904, 910 (Mo. App. W.D ... ...
  • Western Blue Print Co. LLC v. Roberts
    • United States
    • Missouri Court of Appeals
    • April 29, 2011
    ...for the trial court's discretion, and we will affirm absent an abuse of that discretion. Structure & Design Unlimited, Inc. v. Contemporary Concepts Bldg. & Design, Inc., 151 S.W.3d 904, 910 (Mo. App. W.D. 2004).Legal Analysis I. Fiduciary Duty The Robertses argue that the trial court erred......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT