Sustrik v. Jones & Laughlin Steel Corp.

Decision Date07 January 1964
Citation197 A.2d 44,413 Pa. 324
PartiesMike SUSTRIK and Katie Sustrik, his Wife, Appellants, v. JONES & LAUGHLIN STEEL CORPORATION.
CourtPennsylvania Supreme Court

Paul A. Simmons, Tempest & Simmons, Monongahela, for appellants.

Schmidt & Allison, H. Gilmore Schmidt, Washington, Pa., for appellee.

Before MUSMANNO, JONES, COHEN, EAGEN, O'BRIEN and ROBERTS, JJ.

EAGEN, Justice.

This is an action in trespass, in the nature of quare clausum fregit, wherein the lower court entered a compulsory nonsuit. Plaintiffs appeal.

The plaintiffs are the owners by the entireties of a tract of coal-bearing land in Washington County, Pennsylvania. The defendant-corporation is the owner of adjoining lands upon which is conducted a coal mining operation.

The plaintiffs charge the defendant with and seek recovery of damages, for the unlawful removal of a quantity of coal from underneath the surface of their land; in causing damage to buildings thereon due to a subsidence allegedly resulting from the removal of the coal; and, also for an unlawful trespass consisting of the installation of an underground sewer line which drains water from the defendant's mine across plaintiffs' property to a nearby creek. The present action was begun on June 12, 1959.

It appears that the plaintiffs instituted a similar action in February 1957, wherein they sought the recovery of damages from the same defendant for the removal and retention of the same coal involved herein. After several days of trial, that issue was settled and discontinued by agreement of the parties and approval of the court, conditioned upon the payment of a stipulated sum of money from the defendant to the plaintiffs. A draft in the sum agreed upon was delivered.

Subsequently, the plaintiffs attempted to disaffirm the settlement agreement and have the case reopened. The trial court refused the request. Its action was affirmed on appeal: Sustrick v. Jones & Laughlin Steel Corp., 189 Pa.Super. 47, 149 A.2d 498 (1959).

The present claim in so far as it involves the recovery of damages for the removal of the coal and damage to the buildings on plaintiffs' land is barred by the settlement and discontinuance of the 1957 action. As between the parties involved, the settlement and discontinuance had the same effect as the entry of a judgment for the defendant in the proceedings. As between the parties to the action, it is conclusive as to the cause of action asserted therein: Baumgartner v. Whinney, 156 Pa.Super. 167, 39 A.2d 738 (1944); Currier v. Bilger, 149 Pa. 109, 24 A. 168 (1892); Berg v. Cypher, 291 Pa. 276, 139 A. 844 (1927); Sale v. Ambler, 335 Pa. 165, 6 A.2d 519 (1939).

As to the coal for which recovery is sought, there can be no doubt but that the same identical question presented in the 1957 action is in relitigation here. The identity of the cause of action is obvious. It is one and the same in both suits. The 1957 action settled that issue once and for all. It cannot now be resurrected. See, Federal Land Bank of Baltimore v. Putnam, 350 Pa. 533, 33 A.2d 586 (1944); and London v. Philadelphia, 412 Pa. 496, 194 A.2d 901 (1963).

The same conclusion is inescapable as to the claim for damages involving the buildings injured by the subsidences. The basic cause of action in the 1957 case was the removal of the coal. See, Pantall v. Rochester & P. Coal & Iron Co., 204 Pa. 158, 53 A. 751 (1902). The present claim is premised upon the same violation of duty. While the relief sought is enlarged, no new cause of action is presented. The violation of duty in both actions was the removal of the coal, not the damages resulting therefrom. The damages sought are but a consequence of the original trespass. See Pantall v. Rochester & P. Coal & Iron Co., supra, Simodejka v. Williams, 360 Pa. 332, 62 A.2d 17 (1948); and London v. Philadelphia, supra. The final determination of the 1957 action precludes the plaintiffs from maintaining this suit, even though other grounds for relief are asserted than those presented in the original action. That action was conclusive, not only as to those matters that actually were litigated, but also of those matters which could have been litigated therein. Restatement, Judgments, § 63 (1942); Jones v. Costlow, 354 Pa. 245, 47 A.2d 259 (1946); Irwin Borough School District v. North Huntingdon Tp. S. D., 374 Pa. 134, 97 A.2d 96 (1953); and, Goldstein v. Ahrens, 379 Pa. 330, 108 A.2d 693 (1954).

The claim for damages based upon the trespass and installation of the sewer pipe is barred by the statute of limitations. This pipe was installed, according to plaintiffs' testimony, either in the year 1914 or 1915, more than forty years before the present...

To continue reading

Request your trial
3 cases
  • McNulty v. Casero
    • United States
    • U.S. District Court — District of Maryland
    • August 14, 2020
    ...courts adopt the First Restatement's approach to the continuing trespass doctrine. See, e.g. , Sustrik v. Jones & Laughlin Steel Corp. , 413 Pa. 324, 328, 197 A.2d 44 (1964) ; Allegheny County v. Merrit Constr. Co. , 309 Pa. Super. 1, 4, 454 A.2d 1051 (1982). A continuing trespass exists wh......
  • Jones v. Wagner
    • United States
    • Pennsylvania Superior Court
    • April 29, 1993
    ... ...         Id.; 3 see, Sustrik v. Jones and Laughlin Steel Corp., 413 Pa. 324, 197 A.2d 44 ... (1964) ... ...
  • Smith v. IW Levin and Co., Inc.
    • United States
    • Pennsylvania Commonwealth Court
    • June 10, 2002
    ...against the defendant, the agreement finalizes the parties' rights as would a judgment on the merits. See Sustrik v. Jones & Laughlin Steel Corp., 413 Pa. 324, 197 A.2d 44 (1964). ...