TDP Phase One, LLC v. Club at the Yard, LLC

Decision Date13 November 2020
Docket NumberNo. S-19-1198.,S-19-1198.
Citation950 N.W.2d 640,307 Neb. 795
Parties TDP PHASE ONE, LLC, appellee, v. The CLUB AT THE YARD, LLC, doing business as Rule G Night Club, and Eric F. Marsh, appellants.
CourtNebraska Supreme Court

David A. Domina, of Domina Law Group, P.C., L.L.O., Omaha, for appellants.

Gregory S. Frayser and Nathan D. Clark, of Cline, Williams, Wright, Johnson & Oldfather, L.L.P., Lincoln, for appellee.

Heavican, C.J., Miller-Lerman, Cassel, Stacy, and Freudenberg, JJ.

Freudenberg, J.

NATURE OF CASE

After its tenant failed to pay rent and refused to vacate the premises, a commercial landlord brought suit for restitution of premises pursuant to the forcible entry and detainer (FED) statutes, Neb. Rev. Stat. §§ 25-21,219 through 25-21,235 (Reissue 2016 & Cum. Supp. 2018). The landlord also brought claims for breach of the lease agreement and breach of the guaranty agreement. The tenant counterclaimed for breach of contract, breach of implied covenant of good faith and fair dealing, money had and received, and fraud in the inducement of the lease and guaranty agreements. The tenant also brought suit against the property management company and its owners, as third-party defendants, for civil conspiracy to tortiously interfere with a business expectancy and fraud in the inducement of the lease and guaranty agreements.

The tenant appeals from an order of summary judgment in favor of the landlord on its FED claim. The district court's order did not resolve the remaining claims of either the landlord or the tenant, and no request was made of the district court to issue a certification under Neb. Rev. Stat. § 25-1315 (Reissue 2016). We hold that this court is without jurisdiction over the present appeal.

BACKGROUND

TDP Phase One, LLC (TDP), a commercial landlord, entered into a 10-year lease agreement with The Club at the Yard, LLC, doing business as Rule G Night Club (Rule G), signed by its managing member and guarantor, Eric F. Marsh, in 2013. The property at issue is located in the "Railyard," an entertainment district in Lincoln, Nebraska, with a common area in the middle and tenants surrounding it. TDP owns the Railyard. The tenants surrounding the Railyard share costs of the common area, which they pay pursuant to the terms of their lease agreements. When Rule G failed to pay rent in April through July 2019, TDP prepared a 3-day notice to quit, mailing the notice to Marsh and hand delivering a copy to the attorney of record at all relevant times for Rule G. TDP then brought suit against Rule G, alleging restitution of the premises pursuant to §§ 25-21,219 through 25-21,235, as well as claims of breach of contract relating to both the lease and the guaranty agreements. TDP asserted that Rule G failed to pay rent in breach of its lease, that Marsh refused to pay the rent owed as Rule G's guarantor, and that Rule G refused to vacate the premises after TDP prepared and sent a 3-day notice to quit pursuant to § 25-21,221. In its restitution action, TDP sought restitution, costs, and such other relief as was just and equitable.

Rule G challenged proper notice pursuant to § 25-21,221 and raised various defenses, including waiver, prior material breach, and that Rule G was entitled to a setoff due to its overpayment of rent. Rule G also counterclaimed against TDP for (1) breach of contract, (2) breach of implied covenant of good faith and fair dealing, (3) money had and received, and (4) fraud in the inducement of the lease and the guaranty agreements. Finally, Rule G filed a third-party complaint against the management company for the property and its sole members, alleging they conspired to tortiously interfere with its business expectancies.

TDP moved for partial summary judgment, seeking a determination of its FED claim, asserting that there was no genuine issue of material fact as to its right to restitution of the premises. The court determined that Rule G failed to make all payments of rent due under the lease agreement and failed to deliver possession of the property within 3 days of the notice. The court found this entitled TDP to immediate restitution of the property.

In its order, the court rejected Rule G's claim that TDP did not satisfy the notice requirement required by § 25-21,221. It declined to construe § 25-21,221 as requiring notice to be served in the same manner as a summons in a civil action.

Further, the court was not persuaded by Rule G's arguments that TDP waived its FED claim by accepting rental payments after filing suit and that there was a genuine issue of material fact as to whether Rule G was entitled to a setoff for the overpayment of rent under the lease agreement. The court noted that the lease agreement clearly provided that the acceptance of rent is not a waiver of default and that setoff for overpayment of the rent was explicitly precluded by the lease agreement. The court further observed that Rule G's fraudulent inducement claims were barred by the statute of limitations. It did not address any other counterclaims or third-party claims.

Rule G and Marsh appeal the order granting summary judgment to TDP on its FED claim. However, neither sought a § 25-1315 certification from the district court.

ASSIGNMENTS OF ERROR

Rule G and Marsh assign that the district court erred in granting the partial summary judgment for TDP, because the district court erroneously (1) concluded overpayments could not be considered to prove that the rents were paid, (2) did not allow discovery concerning prepayments of rent and calculations of rent credits, (3) found proper presuit notice was given under § 25-21,221, and (4) granted summary judgment for restitution against a lease guarantor who is not a party in possession of the leased premises.

STANDARD OF REVIEW

The question of jurisdiction is a question of law.1

ANALYSIS

Before reaching the assignments of error asserted by Rule G and Marsh, this court must first determine whether it has jurisdiction over this appeal. It is the power and duty of an appellate court to determine whether it has jurisdiction over the matter before it, irrespective of whether the issue is raised by the parties.2 In doing so, we find that we lack jurisdiction over the present appeal, because it lacks certification under § 25-1315.

Section 25-1315(1) provides in full:

When more than one claim for relief is presented in an action, whether as a claim, counterclaim, cross-claim, or third-party claim, or when multiple parties are involved, the court may direct the entry of a final judgment as to one or more but fewer than all of the claims or parties only upon an express determination that there is no just reason for delay and upon an express direction for the entry of judgment. In the absence of such determination and direction, any order or other form of decision, however designated, which adjudicates fewer than all the claims or the rights and liabilities of fewer than all the parties shall not terminate the action as to any of the claims or parties, and the order or other form of decision is subject to revision at any time before the entry of judgment adjudicating all the claims and the rights and liabilities of all the parties.

Where the proceedings below involved multiple claims for relief or multiple parties, and the court has adjudicated fewer than all the claims or the rights and liabilities of fewer than all the parties, then, absent a specific statute governing the appeal providing otherwise,3 § 25-1315 controls and mandates that the order is not immediately appealable unless the lower court issues an "express direction for the entry of judgment" upon "an express determination that there is no just reason for delay."

This case involved both multiple claims for relief and multiple parties, and the order of restitution appealed from adjudicated both fewer than all the claims and the rights and liabilities of fewer than all the parties. TDP filed suit against Rule G for breach of contract, breach of guaranty, and restitution of premises. Rule G in turn brought several counterclaims, as well as a third-party complaint against the property's management company for fraud and tortious interference. TDP filed a motion for partial summary judgment, and the district court entered an order of restitution granting TDP restitution of the premises. This order disposed only of TDP's restitution-of-premises claim against Rule G. The district court has yet to adjudicate TDP's breach of contract and guaranty claims, Rule G's counterclaims against TDP, and Rule G's third-party claims against the property's management company.

The intent behind § 25-1315(1) was to prevent interlocutory appeals, not make them easier.4 Prior to the enactment of § 25-1315, an order that effected a dismissal with respect to one of multiple parties was a final, appealable order, and the complete dismissal with prejudice of one of multiple causes of action was a final, appealable order, but an order dismissing one of multiple theories of recovery, all of which arose from the same set of operative facts, was not a final order for appellate purposes.5 Section 25-1315 was an evident attempt by the Legislature to simplify the issue and clarify many of the questions regarding final orders when there are multiple parties and claims.6 It attempts to strike a balance between the undesirability of piecemeal appeals and the potential need for making review available at a time that best serves the needs of the parties.7

Certification of a final judgment must be reserved for the "unusual case" in which the costs and risks of multiplying the number of proceedings and of overcrowding the appellate docket are outbalanced by the pressing needs of the litigants for an early and separate judgment as to some claims or parties.8 The power § 25-1315(1) confers upon the trial judge should be used only in the "infrequent harsh case" as an instrument for the improved administration of justice, based on the likelihood of injustice or...

To continue reading

Request your trial
7 cases
  • Tegra Corp. v. Boeshart
    • United States
    • Nebraska Supreme Court
    • June 17, 2022
    ...505 (2020).5 Id.6 Tyrrell v. Frakes, supra note 1.7 Rafert v. Meyer , 298 Neb. 461, 905 N.W.2d 30 (2017).8 TDP Phase One v. The Club at the Yard , 307 Neb. 795, 950 N.W.2d 640 (2020).9 Id.10 Id.11 See Poppert v. Dicke , 275 Neb. 562, 747 N.W.2d 629 (2008).12 See, In re Estate of Larson , 30......
  • Mann v. Mann
    • United States
    • Nebraska Supreme Court
    • August 26, 2022
    ...at 9.21 See, e.g., Neb. Rev. Stat. §§ 25-311, 25-320, 25-701, and 25-705 (Reissue 2016).22 TDP Phase One v. The Club at the Yard , 307 Neb. 795, 801, 950 N.W.2d 640, 646 (2020).23 See, e.g., Thrift Mart v. State Farm Fire & Cas. Co. , 251 Neb. 448, 558 N.W.2d 531 (1997), overruled on other ......
  • Porter v. Porter
    • United States
    • Nebraska Supreme Court
    • May 7, 2021
    ...(Cum. Supp. 2020).3 Colwell v. Managed Care of North America , 308 Neb. 597, 955 N.W.2d 744 (2021).4 TDP Phase One v. The Club at the Yard , 307 Neb. 795, 950 N.W.2d 640 (2020).5 In re Change of Name of Whilde , 298 Neb. 510, 904 N.W.2d 707 (2017).6 Annot., 8 A.L.R.3d 1272, 1284 (1966).7 Se......
  • Tyrrell v. Frakes
    • United States
    • Nebraska Supreme Court
    • April 29, 2021
    ...Neb. Ct. R. App. P. § 2-111 (rev. 2017).6 Maria T. v. Jeremy S. , 300 Neb. 563, 915 N.W.2d 441 (2018).7 TDP Phase One v. The Club at the Yard , 307 Neb. 795, 950 N.W.2d 640 (2020).8 In re Estate of Marsh , 307 Neb. 893, 951 N.W.2d 486 (2020).9 Evans v. Frakes , 293 Neb. 253, 876 N.W.2d 626 ......
  • Request a trial to view additional results