The State Ex Rel. Gaylor Inc v. Goodenow

Decision Date29 April 2010
Docket NumberNo. 2010-0330.,2010-0330.
Citation928 N.E.2d 728,2010 Ohio 1844,125 Ohio St.3d 407
PartiesThe STATE ex rel. GAYLOR, INC.v.GOODENOW, Dir., et al.
CourtOhio Supreme Court

The Copley Law Firm, L.L.C., Michael F. Copley, Kenley S. Maddux, Mark E. Landers, Columbus, and Adam F. Florey, for relator.

Ron O'Brien, Franklin County Prosecuting Attorney, and Nick A. Soulas Jr., First Assistant Prosecuting Attorney, and Anthony E. Palmer Jr. and Patrick J. Piccininni, Assistant Prosecuting Attorneys, for respondents.

PER CURIAM.

{¶ 1} This is an action for a writ of mandamus ordering a board of county commissioners, the individual commissioners, and the director and assistant director of the county department of public facilities management to consider whether a low bid for a construction contract on a public-works project is the best bid without reliance on their unlawful finding that the low bidder had previously violated prevailing-wage law and to reinstate the bid and reconsider it under the applicable criteria. Because the company submitting the low bid has established its entitlement to the requested extraordinary relief based on our recent decision in State ex rel. Associated Builders & Contrs. of Cent. Ohio v. Franklin Cty. Bd. of Commrs., 125 Ohio St.3d 112, 2010-Ohio-1199, 926 N.E.2d 600, we grant the writ.

Facts

{¶ 2} Franklin County is constructing a new animal shelter and adoption center. The Franklin County Department of Public Facilities Management issued an invitation to bid for the electrical-systems package of the project. At Section 8.2.4 of the county's invitation to bid, the construction manager is required to obtain from the lowest responsive bidder any information the project representative “deems appropriate to the consideration of factors showing that such Bidder's bid is the best,” including 25 specified criteria.

{¶ 3} One of these 25 criteria is listed in Section 8.2.4.15 as [i]nformation that the Bidder has not been debarred from public contracts or found by the state (after all appeals) to have violated prevailing wage laws more than three times in a two-year period in the last ten years.” Notwithstanding the language in the county's invitation to bid, the county treats the prevailing-wage violations of Section 8.2.4.15 as dispositive, and it ignores other factors once it determines that a bidder has violated prevailing-wage laws more than three times in a two-year period in the last ten years.

{¶ 4} Relator, Gaylor, Inc. (“Gaylor”), is a commercial electrical company with locations in several states, including Ohio. On November 23, 2009, Gaylor submitted the lowest bid for the project's electrical-systems contract.

{¶ 5} By letter dated December 28, 2009, respondent Richard E. Myers, the assistant director of the Franklin County Department of Public Facilities Management, notified Gaylor that the county had rejected its bid because Gaylor “has been found by the State of Ohio to have violated the State's prevailing wage laws more than three times in a two-year period within the last ten years” and was thus ineligible for the award. The county's determination that Gaylor had violated prevailing-wage law was based on its own review and investigation of Ohio Department of Commerce records, even though the department has never found that Gaylor violated prevailing-wage law. All of Gaylor's alleged violations were unintentional underpayments that it had settled without admitting liability and without any administrative or judicial finding of liability.

{¶ 6} Pursuant to Section 8.3.1.1 of the county's invitation to bid, Gaylor submitted a written protest to the county's rejection of its bid and requested a meeting on its protest. The meeting was held on January 14, 2010, and Gaylor submitted additional evidence to support its contention that it had never been found by the state to have violated prevailing-wage law. On February 9, 2010, respondent James A. Goodenow, director of the Franklin County Department of Public Facilities Management, denied Gaylor's protest and affirmed the county's rejection of its bid on the electrical-systems portion of the county animal-shelter project. The county's rejection of Gaylor's bid was based solely on the county's interpretation of Section 8.2.4.15 despite having no evidence that Gaylor had been found by any administrative or judicial authority to have violated prevailing-wage law; the county did not consider any of the other criteria.

{¶ 7} On February 22, Gaylor filed this original action for writs of prohibition and mandamus against the individual Franklin County commissioners as well as the director and assistant director of the Franklin County Department of Public Facilities Management. Gaylor also filed a motion for an emergency stay and an expedited alternative writ. The next day, February 23, the Franklin County Board of Commissioners awarded the electrical-systems contract for the county animal-shelter project to Jess Howard Electric, Inc., for about $100,000 more than Gaylor's bid, executed the contract, and issued a notice to the company to proceed.

{¶ 8} On March 12, we dismissed Gaylor's prohibition claim and denied its motion for an emergency stay and expedited alternative writ insofar as the motion was based on the prohibition claim. State ex rel. Gaylor, Inc. v. Goodenow, 124 Ohio St.3d 1511, 2010-Ohio-919, 923 N.E.2d 154. We also granted an alternative writ on Gaylor's mandamus claim, allowed Gaylor to file an amended complaint to name the Franklin County Board of Commissioners as an additional respondent, and stayed respondents from “enforcing or proceeding on their decisions disqualifying relator's bid and awarding the contract to an alternate contractor pending the court's resolution of relator's mandamus claim.” Id. Gaylor filed an amended complaint to name the board as a defendant, and we extended the stay to the board. State ex rel. Gaylor, Inc. v. Goodenow, 124 Ohio St.3d 1513, 2010-Ohio-959, 923 N.E.2d 156. Upon respondents' motion for clarification of the stay, we specified that respondents “are precluded from taking any action or authorizing any contractor to act in connection with this case until further order of this court.” State ex rel. Gaylor, Inc. v. Goodenow, 124 Ohio St.3d 1515, 2010-Ohio-1030, 923 N.E.2d 157.

{¶ 9} The parties have now submitted evidence and briefs on Gaylor's remaining mandamus claim. This case is now before the court for our consideration of the merits. Because respondents claim that no construction on the county animal-shelter project can proceed until this case is resolved, we expedite our determination.

Legal Analysis
Mootness

{¶ 10} Respondents argue that this mandamus complaint should be dismissed as moot because the electrical-systems contract has already been awarded to another contractor. A ‘case is moot when the issues presented are no longer “live” or the parties lack a legally cognizable interest in the outcome.’ Los Angeles Cty. v. Davis (1979), 440 U.S. 625, 631, 99 S.Ct. 1379, 59 L.Ed.2d 642, quoting Powell v. McCormack (1969), 395 U.S. 486, 496, 89 S.Ct. 1944, 23 L.Ed.2d 491. “It is not the duty of the court to answer moot questions, and when, pending proceedings * * * in this court, an event occurs, without the fault of either party, which renders it impossible for the court to grant any relief, it will dismiss the petition * * *.” Miner v. Witt (1910), 82 Ohio St. 237, 92 N.E. 21, syllabus.

{¶ 11} Conversely, if an actual controversy exists because it is possible for a court to grant the requested relief, the case is not moot, and a consideration of the merits is warranted. Allen v. Totes/Isotoner Corp., 123 Ohio St.3d 216, 2009-Ohio-4231, 915 N.E.2d 622, ¶ 18 (O'Connor, J., concurring); State v. Consilio, 114 Ohio St.3d 295, 2007-Ohio-4163, 871 N.E.2d 1167, ¶ 7. In a construction-related case, if an unsuccessful bidder seeking to enjoin the construction of a public-works project fails to obtain a stay of the construction pending judicial resolution of its claims challenging the decision, and construction commences, the unsuccessful bidder's action will be dismissed as moot. See generally TP Mechanical Contrs., Inc. v. Franklin Cty. Bd. of Commrs., Franklin App. No. 08AP-108, 2008-Ohio-6824, 2008 WL 5381926, ¶ 20, and cases cited therein.

{¶ 12} This case is not moot. Gaylor filed this action challenging the county's rejection of its low bid on the electrical-systems contract for the county animal-shelter project and sought a stay of respondents' actions on February 22, which was before the board awarded the contract to another contractor. And although the board did, in fact, award the electrical-systems contract to another bidder on February 23, which preceded our March 12 stay, respondents have introduced no evidence that the other contractor commenced construction pursuant to the awarded contract before we issued the stay.

{¶ 13} In this regard, respondents claim in their merit brief that “construction activities were commenced by Jess Howard Electric prior to the stay being issued” and cite an affidavit attached to their emergency motion for an expedited briefing schedule to support this statement. But the cited evidence for this statement does not support it; instead, it merely states that the court's stay of the electrical-systems contract effectively prevented other contractors from proceeding. Gaylor previously rebutted a comparable unsupported claim made by respondents in their motion for clarification by stating in its memorandum in opposition: [The county] argues that * * * another contractor started performing the work ( with no evidence that that has happened ).” (Emphasis added.) Yet respondents still failed to submit evidence that the other bidder had commenced construction on the electrical-systems contract before we issued the stay. And the contractor that was awarded the project did not seek leave to intervene in this case to oppose...

To continue reading

Request your trial
42 cases
  • Bryan v. Chytil
    • United States
    • Ohio Court of Appeals
    • November 10, 2021
    ... ... The Adena ... Road property abuts Adena Mansion State Park and totals ... approximately 29 acres that contains a single-family ... 359, 366, 89 N.E.2d 459, (1949); State ex rel. Cincinnati ... Enquirer v. Lyons, 140 Ohio St.3d 7, 2014-Ohio-2354, 14 ... consideration of the merits is warranted." State ex ... rel. Gaylor v. Goodenow, 125 Ohio St.3d 407, ... 2010-Ohio-1844, 928 N.E.2d 728, ¶ ... ...
  • Med. Mut. of Ohio v. FrontPath Health Coal.
    • United States
    • Ohio Court of Appeals
    • January 27, 2023
    ... ...           {¶ ... 11} "Ohio is a notice-pleading state." ... Maternal Grandmother v. Hamilton Cty. Dept. of Job and ... Family ... tests the sufficiency of the complaint." State ex ... rel. Hanson v. Guernsey Cty. Bd. of Commrs., 65 Ohio ... St.3d 545, 548, 605 ... State ex rel. Gaylor, Inc. v. Goodenow, 125 Ohio ... St.3d 407, 2010-Ohio-1844, 928 N.E.2d ... ...
  • State v. McCall
    • United States
    • Ohio Court of Appeals
    • December 11, 2020
    ...the issues presented are no longer 'live' or the parties lack a legallycognizable interest in the outcome."'" State ex rel. Gaylor, Inc. v. Goodenow, 125 Ohio St.3d 407, 2010-Ohio-1844, 928 N.E.2d 728, ¶ 10, quoting Los Angeles Cty. v. Davis, 440 U.S. 625, 631, 99 S.Ct. 1379, 59 L.Ed.2d 642......
  • City of Dublin v. Friedman
    • United States
    • Ohio Court of Appeals
    • December 19, 2017
    ...relief." Joys v. Univ. of Toledo , 10th Dist. No. 96APE08–1040, 1997 WL 217581 (Apr. 29, 1997). See also State ex rel. Gaylor, Inc. v. Goodenow , 125 Ohio St.3d 407, 2010-Ohio-1844, 928 N.E.2d 728, ¶ 11. Thus, to ascertain whether the present appeal is moot, we must determine whether it wou......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT