Titan Const. Co. v. Mark Twain Kansas City Bank

Decision Date22 November 1994
Docket NumberNo. WD,WD
Citation887 S.W.2d 454
PartiesTITAN CONSTRUCTION COMPANY, Appellant, v. MARK TWAIN KANSAS CITY BANK, Respondent. 48841.
CourtMissouri Court of Appeals

Kevin E. Glynn, Kansas City, for appellant.

Charles A. Weiss, St. Louis, for respondent.

Before SPINDEN, P.J., and LOWENSTEIN and ELLIS, JJ.

SPINDEN, Presiding Judge.

This breach of contract dispute involves construction of a Kansas City apartment complex financed by Mark Twain Kansas City Bank. The bank took over the project and finished it when the developers, Bridgeport Ventures, defaulted. Mark Twain found the work of the general contractor, Titan Construction Company, to be unacceptable and fired it.

Titan claims that Mark Twain made fraudulent misrepresentations and breached its contract. Mark Twain countersued, charging Titan with breach of contract. The jury ruled for Mark Twain on Titan's breach of contract claim and against Titan on Mark Twain's counterclaim for breach of contract. The trial court entered summary judgment for Mark Twain on Titan's claim of fraud against the bank. Titan appeals, and we affirm.

The apartment complex's original developer was a six-person partnership known as Bridgeport Ventures. Thomas Saul, Titan's principal owner and president, was one of Bridgeport Ventures' partners. Mark Twain loaned Bridgeport Ventures $7.5 million for the project. The partners executed a note payable to the bank and secured it with a deed of trust on the property and each partner's personal guarantee. Each partner agreed to assign the construction contract to Mark Twain if Bridgeport Ventures defaulted on the loan.

Bridgeport Ventures and Titan agreed on August 14, 1986, that Titan would be general contractor for the project, and Titan began constructing the apartments. Bridgeport Ventures negotiated a new construction contract with Titan on March 23, 1987, raising the construction cost. In February 1988, Mark Twain agreed to increase its loan to Bridgeport Ventures to $8.2 million. Two days later, Saul withdrew as a partner of Bridgeport Ventures.

In 1987 and 1988, several subcontractors filed mechanic's liens against the project because Titan had not paid them. This placed Bridgeport Ventures in default under its loan agreement with Mark Twain. Although Titan provided a bond against the mechanic's lien claims, it did not pay the subcontractors.

On March 18, 1988, Bridgeport Ventures' remaining partners told Mark Twain that the partnership could not continue the project unless Mark Twain restructured the loan and forgave the interest. They also said that if the bank refused to do this, they would assign the construction contract to it.

Mark Twain did refuse and became actively involved in the project. It discharged the architects and hired Peckham, Guton, Albers & Viets, Inc., (PGAV) to replace them. Discussions between Mark Twain and Bridgeport Ventures continued, and Mark Twain warned that it might foreclose on the property.

On July 22, 1988, Mark Twain accepted a deed in lieu of foreclosure from the partners of Bridgeport Ventures. In exchange for the property and additional collateral pledged by individual partners, Mark Twain released Bridgeport Ventures from its obligations under the loan agreements. On the same day, Mark Twain and Titan entered into a separate contract in which they agreed to proceed under the terms of Titan's March 23, 1987, contract with Bridgeport Ventures. Mark Twain agreed to be responsible as the successor owner of the project, and Titan agreed to complete the project on or before December 1, 1988. Mark Twain retained McCormack, Baron & Associates, Inc., as its representative for the project. After discovering that critical as-built drawings were missing and that much of the completed work was unacceptable, McCormack Baron decided the project was not progressing satisfactorily. Some of the subcontractors had walked off the job, and Titan lost its bonding. A structural engineer hired by Mark Twain concluded that the buildings were not structurally sound because of concealed defects.

From July 22, 1988, to September 19, 1988, Mark Twain and Titan negotiated problems with schedules, payments, defective and incomplete work and deviations from the plans and specifications. After concluding that the deficient work was extensive and that Titan was not going to correct it, Mark Twain obtained certification from PGAV that good cause existed for terminating Titan's contract. On September 9, 1988, Mark Twain notified Titan of termination of their contract for default. Mark Twain sent Titan a second notice of termination on September 19, 1988.

After terminating Titan's services, Mark Twain formed a limited partnership with McCormack Baron called Bridgeport Apartments Associates. Mark Twain conveyed the property to Bridgeport Apartments Associates but retained a 99 percent ownership interest. McCormack Baron agreed to manage the property for Mark Twain. Mark Twain transferred the property to Bridgeport Apartments Associates on September 28, 1988, and recorded the action on September 30, 1988. Mark Twain hired Neighbors Construction Company to complete the project.

On November 18, 1988, Titan sued Mark Twain City Bank for declaratory judgment, breach of contract and fraud. Titan also sued McCormack Baron, Mark Twain Bank of St. Louis and PGAV for fraud. Mark Twain counterclaimed for breach of contract and filed a third-party claim against Titan's surety, Travelers Indemnity Company, for its refusal to honor a performance bond issued for the project. The circuit court granted summary judgment in favor of all defendants on Titan's fraud claim. Mark Twain and the other defendants settled with Travelers before trial. The breach of contract claims were tried to a jury in September 1993. The jury returned a verdict in favor of Mark Twain on Titan's claim and against Titan on Mark Twain's counterclaim. The trial court entered judgment on those verdicts and overruled all post-trial motions filed by Titan. This appeal followed.

In its first of four points on appeal, Titan contends that the trial court erred in overruling its motion for directed verdict, motion for new trial and motion for judgment notwithstanding the verdict because Mark Twain did not name McCormack Baron as a party to its counterclaim against Titan for breach of contract. Titan argues that because McCormack Baron was the general partner of the Bridgeport Apartments Associates which owned the Bridgeport Apartments project, Mark Twain had to include it as a necessary party.

"Contractual obligations 'can only be enforced by one who is a party to the contract or in privity with it.' " County Asphalt Paving Company v. 1861 Group, LTD., 851 S.W.2d 577, 582 (Mo.App.1993) (citation omitted). McCormack Baron was not a party to Titan's and Mark Twain's contract. After Bridgeport Ventures defaulted, Mark Twain succeeded to all of the rights of Bridgeport Ventures as project owner. Titan and Mark Twain entered into a separate agreement for Titan's completing the project. On September 9, 1988, Mark Twain notified Titan that it was in default. Titan ceased work on September 20, 1988, and, on September 28, 1988, Mark Twain conveyed the property to Bridgeport Apartments Associates without assigning its contract with Titan to the limited partnership. McCormack Baron was not a party to Mark Twain's contract with Titan and had no interest in the property when the contract was executed. McCormack Baron was not a necessary party to Mark Twain's counterclaim against Titan.

In its second point, Titan contends that the trial court erred in overruling its post-trial motions in which Titan requested a settlement credit and "set-off" of the $1.2 million Mark Twain received from Travelers before trial. Titan argues that allowing Mark Twain to keep both the settlement proceeds and the amount of the judgment gives it an unwarranted windfall in violation of the common law rule that a party may have only one satisfaction for a claim.

The common law defense of prior, full satisfaction is an affirmative defense which must be pleaded and proven. See Walihan v. St. Louis-Clayton Orthopedic Group, Inc., 849 S.W.2d 177, 180 (Mo.App.1993). An affirmative defense must be pleaded to give the plaintiff notice, and failure to plead it generally results in waiver. Lucas v. Enkvetchakul, 812 S.W.2d 256, 263 (Mo.App.1991).

Mark Twain settled with Travelers in May 1990, nearly three years before the trial. Titan did not plead the issue of prior satisfaction or the settlement agreement as an affirmative defense to Mark Twain's counterclaim. 1 Titan's...

To continue reading

Request your trial
2 cases
  • Eng v. Cummings
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • July 9, 2010
    ...to enter into a contract, and fraudulent misrepresentation based upon breach of a contract. See, e.g., Titan Constr. Co. v. Mark Twain K.C. Bank., 887 S.W.2d 454, 459 (Mo.Ct.App.1994). Fraud arising from the breach of a contract does not amount to an independent tort, but fraud inducing ent......
  • Groh v. Jpmorgan Chase Bank, N.A.
    • United States
    • U.S. District Court — Western District of Missouri
    • January 5, 2015
    ...of fact" absent an allegation that the promisor did not presently intend to perform. Titan Constr. Co. v. Mark Twain Kan. City Bank, 887 S.W.2d 454, 459 (Mo. Ct. App. 1994). Here, Chase Bank promised Groh that so long as he complied with the Loan Workout Plan's terms, it would provide him w......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT