Triple A Contractors, Inc. v. Rural Water Dist. No. 4, Neosho County

Decision Date01 December 1979
Docket NumberNo. 49911,49911
Citation226 Kan. 626,603 P.2d 184
PartiesTRIPLE A CONTRACTORS, INC., Appellant, v. RURAL WATER DISTRICT NO. 4, NEOSHO COUNTY, Kansas, Appellee.
CourtKansas Supreme Court

Syllabus by the Court

The successful bidder for a public construction contract will not be granted equitable relief, by way of cancellation of the construction bid and the discharge and relief from its bid bond, because of a unilateral error in calculating costs.

Larry G. Pepperdine of Fisher, Patterson, Sayler & Smith, Topeka, argued the cause and was on brief, for appellant.

Charles F. Forsyth, Erie, argued the cause and was on brief, for appellee.

PER CURIAM:

This appeal is from a judgment denying equitable relief in the form of cancellation of a public construction bid and the discharge and release of the bid bond.

The only issue before us is whether the successful bidder for a public construction contract will be granted equitable relief by way of cancellation of the construction bid and the discharge and release of its bid bond because of a unilateral error in calculating costs.

On March 4, 1976, Rural Water District No. 4, Neosho County, Kansas, issued a notice to contractors that bids would be received for the construction of a water distribution and storage system. We are concerned here only with the water distribution system. The bids were to be accompanied by a check or bid bond in the amount of 5% Of the total bid. The stated purpose of the bid bond was to guarantee that the contractor would enter into a construction contract within ten days of the award of the contract.

The plaintiff company submitted its bid and a bid bond in the amount of $40,637.65. It might be explained here that the plaintiff company is a family corporation consisting of Glen Anderson and his five children. Steve Anderson, the twenty-seven year old son of Glen Anderson, was assistant general manager. The bid submitted by plaintiff was prepared by Steve Anderson.

The bids were opened on March 24, 1976. The plaintiff's bid was $812,753.00. This was $169,079.50 lower than the next lowest bid and $486,154.50 lower than the defendant's consulting engineer's estimate. Because of the wide variation between the low bidder and the second low bidder all parties concerned suspected an error. Glen and Steve Anderson spent two or three days going through the plans and cost estimate sheets looking for an error.

The error was found on March 27, 1976. The chief error had been made in transferring the calculated amount of shot rock from the adding machine tape to the bid project estimate sheets. Only 6,000 lineal feet of the 36,000 lineal feet had been carried over to the estimate sheets. Glen Anderson testified this was the sole purpose for requesting withdrawal of the bid. On March 29, 1976, defendant's consulting engineer talked to Glen Anderson about the bid. Glen Anderson informed the defendant's consulting engineer that an error had been made and he wished to withdraw the bid. No mention was made of the nature of the error.

On March 31, 1976, the plaintiff sent a letter to the defendant requesting withdrawal of the bid on the basis of gross error in cost estimating. Glen Anderson testified that he did not use the term "mathematical error" in the letter because he did not know the type of error was important. The defendant, the Rural Water District Board, voted to accept appellant's bid on April 21, 1976. Glen Anderson met with the board on May 4, 1976, and explained the exact nature of the error. At the meeting the plaintiff rejected the contract.

Plaintiff brought action in the district court, alleging a mistake in the form of a clerical error in the computation of the quantity of rock to be excavated and prayed that the acceptance of the bid be cancelled, its bid be rescinded and cancelled, and its bid bond be cancelled.

The district court in memorandum opinion stated as follows:

"The controlling question is whether a bidder on a construction contract can be relieved from obligation under his bid bond for his unilateral mistake in figuring his bid. No Kansas decision has been turned up and the authorities in other states are divided, probably the majority rule being that he can.

"As simple contract law the Kansas Supreme Court has consistently held that unilateral mistake will not excuse non performance."

The trial court followed the Kansas general rule that a unilateral mistake will not excuse nonperformance of a contract and denied the plaintiff any relief. The plaintiff has appealed.

Before we proceed with a discussion of the law we should be clear on the issue before us. There has been a great deal of confusion in the decisions because of the failure to distinguish between the contract involved in the bid and the construction contract which would result from the bid contract. The appellee is not attempting to hold the plaintiff to a construction contract which because of errors might result in a tremendous loss of an unknown amount. The appellee is holding appellant to his bid contract under which he can forfeit the bid bond in a known amount and be relieved of the obligations of the construction contract.

We have no Kansas case dealing with the effect of an error on a bid contract. However, we see no reason why our cases announcing the rule that in the absence of fraud a unilateral mistake will not excuse the nonperformance of a contract should not apply. See Snider v. Marple, 168 Kan. 459, 213 P.2d 984 (1950); Green v. Insurance Co., 112 Kan. 50, 209 P. 670 (1922); Commission Co. v. Mowery, 99 Kan. 389, 161 P. 634 (1916), Modified 99 Kan. 399, 162 P. 313 (1917); Griffin v. O'Neil, 48 Kan. 117, 29 P. 143 (1892).

The courts of other states are divided on the question. Appellant calls our attention to the general rule set forth in 52 A.L.R.2d 796, as follows:

"Equity will relieve from the consequences of a bid for a public contract which has been submitted as the result of a remediable unilateral mistake, although a contract has not been consummated, and the principles applied are generally similar to those applied in relieving against completed contracts resulting from unilateral mistake."

This may state the position of those state courts which have granted relief on a unilateral mistake. We are more impressed with a contrary decision in Colella v. Allegheny County, Aplnt., 391 Pa. 103, 107, 137 A.2d 265, 267 (1957), where the court denied relief under facts quite similar to those in the case before us and stated:

"If a person, firm or corporation submits a sealed bid on public works, the principle contended for by the contractor, namely, that after all the bids are opened he can withdraw his bid under the plea of a clerical mistake, would seriously undermine and make the requirement or system of sealed bids a mockery; it could likewise open wide the door to fraud and collusion between contractors and/or between contractors and the Public Authority. What is the use or purpose of a sealed bid if the bidder does not have to be bound by what he submits under seal? What is the use or purpose of requiring a surety bond as further...

To continue reading

Request your trial
7 cases
  • Marana Unified School Dist. No. 6 v. Aetna Cas. & Sur. Co., 2
    • United States
    • Arizona Court of Appeals
    • December 3, 1984
    ...(5th Cir.1969); Anco Construction Co., Ltd. v. City of Wichita, 233 Kan. 132, 660 P.2d 560 (1983); Triple A Contractors, Inc. v. Rural Water District No. 4, 226 Kan. 626, 603 P.2d 184 (1979); and City of Newport News v. Doyle & Russell, Inc., 211 Va. 603, 179 S.E.2d 493 (1971) where no stat......
  • State ex rel. Missouri State Highway Com'n v. Hensel Phelps Const. Co., 63307
    • United States
    • Missouri Supreme Court
    • June 8, 1982
    ...391 Pa. 103, 137 A.2d 265 (1958); Daddario v. Town of Milford, 296 Mass. 92, 5 N.E.2d 23 (1936); Triple A Contractors, Inc. v. Rural Water District, 226 Kan. 626, 603 P.2d 184 (1979). In Triple A Contractors, supra, the Kansas Supreme Court stated at 628, 603 P.2d If a person, firm or corpo......
  • Chas. H. Tompkins Co. v. Lumbermens Mut. Cas. Co.
    • United States
    • U.S. District Court — Eastern District of Virginia
    • March 16, 1990
    ...Independent School District No. 24 v. Weinmann, 243 Minn. 469, 68 N.W.2d 248 (1955). 9 See, e.g., Triple A Contractors, Inc. v. Rural Water District No. 4, 226 Kan. 626, 603 P.2d 184 (1979); City of Newport News v. Doyle & Russell, Inc., 211 Va. 603, 179 S.E.2d 493 10 See, e.g., L & M Enter......
  • Squires v. Woodbury
    • United States
    • Kansas Court of Appeals
    • December 24, 1980
    ...will not excuse the nonperformance of a contract, as applied in a construction bid bond situation. Triple A Contractors, Inc. v. Rural Water Dist. No. 4, 226 Kan. 626, 603 P.2d 184 (1979). While the above cases appear to announce the general rule, in Geiger v. Hansen, 214 Kan. 83, 87, 519 P......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT