Underwater Eng'g Servs., Inc. v. Util. Bd. of Key W., 3D14–2011.
Decision Date | 11 May 2016 |
Docket Number | No. 3D14–2011.,3D14–2011. |
Parties | UNDERWATER ENGINEERING SERVICES, INC., etc., Appellant, v. UTILITY BOARD OF the CITY OF KEY WEST, Appellee. |
Court | Florida District Court of Appeals |
Palmer Law Group and Andrew J. Palmer, Fort Lauderdale; Burlington and Rockenbach, Philip M. Burlington and Adam J. Richardson, West Palm Beach, for appellant.
Robert C. Tilghman and Nathan Eden, for appellee.
Before EMAS, LOGUE and SCALES, JJ.
EMAS
, J.
Appellant/Plaintiff, Underwater Engineering Services, Inc. (“Underwater”), appeals from a final judgment, entered after a nonjury trial, in favor of Appellee Utility Board of the City of Key West (“the Utility Board”) on Underwater's breach of contract claim, as well as the Utility Board's counterclaim. We hold that there is competent substantial evidence in the record to support the trial court's determination in favor of the Utility Board on Underwater's breach of contract claim and affirm that portion of the final judgment. We further hold that the trial court erred in entering judgment in favor of the Utility Board on its counterclaim, as the evidence establishes that Underwater was not provided the contractually-required notice and opportunity to cure the alleged defects before the Utility Board hired a different contractor to correct and repair Underwater's work. We therefore reverse that portion of the final judgment and remand for entry of final judgment in favor of Underwater on the Utility Board's counterclaim.
This action arises from a construction contract (“the Contract”) between Underwater and the Utility Board. The Utility Board hires contractors as needed to inspect over-the-water concrete and steel poles, and to perform necessary maintenance and repairs. The inspections may reveal issues affecting or compromising the structural integrity of the poles; they may require the pouring of a concrete collar around the base of the pole for additional support, or the application of a particular coating to areas needing repair or to areas where a prior coating application may have deteriorated.
In May 2004, the Utility Board issued a call for bids on a project entitled “Repair Over the Water Transmission Pole Foundations.” The project involved, among other things, structural concrete repairs, coating repair and new coating placement. Specifically, the successful bidder was to repair approximately fifty-seven concrete pole structures supporting electric transmission lines running from Key West to the Seven Mile Bridge. Pursuant to the bid schedule, the Contract was a unit-price contract—the bid price was not a lump sum, but was instead broken down into subparts for each item of work or material to be used—and the bidders proposed a price per unit. Following the bidding process, Underwater was awarded the Contract, which was executed in October of 2004, and a Notice to Proceed was issued in January 2005. The final contract price (based on the unit prices bid by Underwater) was $767,585.50.
The Contract contained the following relevant provisions:
Ed Giesler was the project engineer and Underwater's primary contact with the Utility Board. Tom Fettig was Underwater's project manager. Pursuant to the Contract, the preconstruction inspection of the Seven Mile Bridge area occurred on June 22 and 23, 2005. The inspection was conducted by the Utility Board's resident engineering representative, Anchor Structural, represented by Wayne Fey and Mark Demarest.
Underwater's primary claim against the Utility Board concerns an item designated as “MIS4” and described as “Concrete Coating Repair.” In the blank bid schedule, the Utility Board estimated the quantity of MIS4 units to be 200 square feet. Underwater's bid stated it would perform MIS4 at a unit price of $110, so the total price of the concrete coating repair (based on the estimated 200 square feet x $110/square feet) was $22,000.
On June 23, 2005, a consultant on the project sent an email to Giesler and Dale Finigan, also with the Utility Board, explaining he was trying to get the Utility Board a revised estimate. The consultant indicated that based on the inspections performed on June 22, 2005, they had a “rough handle on the amount that the units will change on the upper portion of the project.” In response to a question from the consultant, Finigan advised he was okay with building a contingency amount into the numbers, but noted it should be “a reasonable amount.” Though the emails contained no dollar amounts or quantities, no one from the Utility Board followed up or requested clarification or additional specificity.
The final Preconstruction Inspection Report for the fifty-seven poles in the Seven Mile Bridge area was sent by Underwater to the Utility Board on June 29, 2005. In the cover letter, Fettig wrote: The report details the repair work, including the MIS4 coating work on fifty-seven poles, but it contains no numbers or costs, either estimated or actual. Though Underwater's CEO testified that calculating the amount of coating to be applied to the poles is a matter of “basic math,” the detailed formula he provided at trial was contained nowhere in the Preconstruction Inspection Report, and the parties disagree as to who was responsible for making these calculations.
At some point during July 2005, Fettig, Underwater's project manager and the person responsible for making this project profitable for Underwater, prepared two spreadsheets. These spreadsheets compared the revenue anticipated by the project as originally estimated and agreed to by the Utility Board with the revenue it could realize if the coating was increased from 200 square feet to 5,006 square feet. Using the original estimate for coating, Underwater faced a loss of approximately $168,891.71. However, by increasing the amount of coating from 200 square feet to 5,006 square feet, Fettig's spreadsheet showed Underwater's revenue on the project would increase by $528,660.00 and yield a profit of $433,579.29. Though Fettig and other members of Underwater thought it prudent to advise the Utility Board of this significant change in the total footage and resulting increase in cost, Dean Reynolds, Underwater's branch manager, told Fettig not to do so. Even though Fettig testified that he personally believed this overrun should have been revealed to the Utility Board, he also indicated that this overrun did not technically require a change order because the parties were operating under a unit-price contract. The differential in the cost did not relate to the unit price of the coating (which remained the same), but instead related to the total square footage of the poles to be coated. Fey, on the other hand, as president of Anchor Structural, testified that an increase in the amount of coating, which consequently increased the contract price by more than $500,000.00 would “absolutely” and “without a doubt” require a change order.1 However, no change order was ever submitted to the Utility Board, nor was any authorization sought from the Utility Board before Underwater proceeded...
To continue reading
Request your trial-
Taylor Indus. Constr., Inc. v. Westfield Ins. Co.
...allegedly defective work of which Taylor was notmade aware or given the opportunity to correct. See Underwater Eng'g Servs., Inc. v. Util. Bd., 194 So.3d 437, 445-46 (Fla. 3d DCA 2016) (court erred in finding in favor of defendant where defendant did not give plaintiff the opportunity to re......
-
Pardes v. Pardes
...they are clearly erroneous. Thus, they are reviewed for competent, substantial evidence." Underwater Eng'g Servs., Inc. v. Utility Bd. of City of Key West, 194 So. 3d 437, 444 (Fla. 3d DCA 2016) (additional citations omitted).This case, however, is atypical in one important respect: It was ......
-
City of Key W. v. Key W. Golf Club Homeowners' Ass'n, Inc.
...they are clearly erroneous.' Thus, they are reviewed for competent, substantial evidence." Underwater Eng'g Servs., Inc. v. Util. Bd. of the City of Key West, 194 So. 3d 437, 444 (Fla. 3d DCA 2016) (citation omitted). "[A]n appellate court is not free to substitute its judgment for the trie......
-
Pardes v. Pardes
... ... evidence." Underwater Eng'g Servs., Inc. v ... Utility Bd. of ... ...