United States v. Atlantic Dredging Co, 214

Citation40 S.Ct. 423,253 U.S. 1,64 L.Ed. 735
Decision Date26 April 1920
Docket NumberNo. 214,214
PartiesUNITED STATES v. ATLANTIC DREDGING CO. et al
CourtUnited States Supreme Court

Action in the Court of Claims to recover the sum of $545,121.72 from the United States on account of expenditures and loss caused, it is alleged, in the execution of a contract which it was induced to enter into by false and misleading statements of the officers of the United States in charge of excavations in the Delaware river.

In pursuance of advertisement by the United States through Col. Kuhn, the dredging company entered into a contract to do a certain part of the work for the sum of 12.99 cents per cubic yard, scow measurement.

Sealed proposals were required by the advertisement and it was stated that information could be had on application, and bidders were invited to base their dids upon the specifications, which had been prepared by, and were submitted by the government.

The specifications stated that the depth of the channel to be dredged was 35 feet, and under the heading 'Quality or Character of the Material' contained the following:

'The material to be removed is believed to be mainly mud, or mud with an admixture of fine sand, except from station 54 to station 55+144, at the lower end of West Horseshoe Range (the latter is not included in the contract) where the material is firm mud, sand, and gravel or cobbles.'

It was stated that——

'Bidders were expected to examine the work, however, and decide for themselves as to its character and to make their bids accordingly, as the United States does not guarantee the accuracy of this description.'

The further statement was that——

'A number of test borings have been made in all of the areas where dredging is to be done under these specifications, and the results thereof may be seen by intending bidders on the maps on file in this office. (See paragraph 17.) No guaranty is given as to correctness of these borings in representing the character of the bottom over the entire vicinity in which they were taken, although the general information given thereby is believed to be trustworthy.'

To ascertain the character of the material to be dredged the government officers had subjected the bottom of the river to certain borings, called, according to their manner of being made, 'test borings and wash borings,' and the results thereof were correctly reported and recorded on the log or field notes at the time—that is, that the probe had penetrated or had not penetrated but there was nothing on the map exhibited to bidders showing the field notes taken at the time the borings were made. It was hence shown that the material to be encountered was 'mainly mud or mud with an admixture of sand.' In other words, the map did not contain a true description of the character of the material which was to be encountered, and was encountered by the dredging company in the prosecution of the work. The material dredged, at certain places, differed from that shown on the map exhibited to bidders. The company made no independent examination, though it had time to do so, and in making its proposal it stated that it did so with full knowledge of the character and quality of the work required.

The proposals required the character and capacity of the plant proposed to be employed by the contractor to be stated and that it should be kept in condition for efficient work and be subject to the inspection and approval of the 'contracting officer.' In compliance with the requirement the plant was submitted to such officer and by him inspected and approved. It was efficient for dredging the character of material mentioned in the specifications and described on the map to which bidders were referred for information; it was not efficient for dredging the material actually found to exist, and the company secured the services of another concern to do the dredging for it, and that concern did all of the work that was done.

After the company, and the concern it had employed, had been at work for some time, it complained of the character of material which was being encountered, and a supplementary contract was entered into by it and the 'contracting officer.'

This contract recited that 'heavy and refractory material, consisting mainly of compacted sand and gravel, with a small percentage of cobbles had been encountered,' and provided that such material might be deposited in the Delaware river, instead of on shore, as provided in the original contract.

At the time of making the supplemental contract the company was not aware of the manner in which the 'test borings' over the area embraced in its contract had been made. Upon learning of this in December, 1915, it discontinued work and declined to do...

To continue reading

Request your trial
117 cases
  • UNITED STATES, ETC. v. Guy H. James Construction Co.
    • United States
    • U.S. District Court — Middle District of Tennessee
    • 5 Septiembre 1972
    ...rescind or abandon its duty to complete its performance under the contract upon defendant's breach. United States v. Atlantic Dredging Co., 253 U.S. 1, 40 S.Ct. 423, 64 L.Ed. 735 (1920). Instead, E & R attempted to complete performance and in its attempt to avoid the consequences of James' ......
  • McCree & Co. v. State
    • United States
    • Minnesota Supreme Court
    • 1 Agosto 1958
    ...233 U.S. 165, 34 S.Ct. 553, 58 L.Ed. 898; Cauldwell-Wingate Co. v. State, 276 N.Y. 365, 12 N.E.2d 443; United States v. Atlantic Dredging Co., 253 U.S. 1, 40 S.Ct. 423, 64 L.Ed. 735; Davis v. Com'rs of Sewerage, D.C.W.D.Ky., 13 F.Supp. 672.In 21 Minn.L.Rev. 70, 74, the authority supporting ......
  • Webb-Boone Paving Co. v. State Highway Com'n
    • United States
    • Missouri Supreme Court
    • 7 Junio 1943
    ... ... Simpson v ... United States, 172 U.S. 372; United States v ... Spearin, 248 ... 234, 35 S.Ct. 565; United States v. Atlantic Dredging ... Co., 253 U.S. 1, 43 S.Ct. 423; United ... ...
  • Sanford Const. Co. v. S & H Contractors, Inc.
    • United States
    • United States State Supreme Court — District of Kentucky
    • 6 Junio 1969
    ...§ 69d, p. 366. Anno.: Fraud--Waiver by Acts under Contract, 13 A.L.R.2d 807, 815, 846. Also see United States v. Atlantic Dredging Co., 253 U.S. 1, 11--12, 40 S.Ct. 423, 425, 64 L.Ed. 735 (1920); Woodmont, Inc. v. Daniels (CA10th) 274 F.2d 132, 139 (1960); Palmberg v. City of Astoria, 101 O......
  • Request a trial to view additional results
3 books & journal articles
  • The Economic Loss Rule in Construction Law
    • United States
    • ABA Archive Editions Library Construction Law
    • 1 Enero 2009
    ...by a troika of opinions from the U.S. Supreme Court in the second decade of the 20th century: United States v. Atl. Dredging Co . , 253 U.S. 1 (1920); Christie v. United States, 237 U.S. 234 (1915); and Hollerbach v. United States, 233 U.S. 165 (1914). For an excellent description of the ef......
  • The Economic Loss Rule in Construction Law
    • United States
    • ABA Archive Editions Library Construction Law
    • 22 Junio 2009
    ...by a troika of opinions from the U.S. Supreme Court in the second decade of the 20th century: United States v. Atl. Dredging Co . , 253 U.S. 1 (1920); Christie v. United States, 237 U.S. 234 (1915); and Hollerbach v. United States, 233 U.S. 165 (1914). For an excellent description of the ef......
  • The Construction Industry in the U.S. Supreme Court: Part 1, Contract Law
    • United States
    • ABA General Library The Construction Lawyer No. 41-2, April 2021
    • 1 Abril 2021
    ...for Shared Architectural and Engineering Services , 84 NEB. L. REV. 162, 173–82 (2005). 55. United States v. Atlantic Dredging Co., 253 U.S. 1 (1920). 56. Id. at 11. 57. Id. at 11–12. 58. Id. at 10. 59. See, e.g. , Helene Curtis Indus., Inc. v. United States, 312 F.2d 774 (Ct. Cl. 1963). Se......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT