Venture Const. Co. v. Great Am. Mortg. Investors
Decision Date | 14 March 1975 |
Docket Number | No. 50014,No. 2,50014,2 |
Citation | 134 Ga.App. 440,214 S.E.2d 683 |
Parties | VENTURE CONSTRUCTION COMPANY v. GREAT AMERICAN MORTGAGE INVESTORS et al |
Court | Georgia Court of Appeals |
Cofer, Beauchamp & Hawes, Peyton S. Hawes, Jr., James H. Rollins, Atlanta, for appellant.
Alston, Miller & Gaines, Ronald L. Reid, Atlanta, for appellees.
Syllabus Opinion by the Court
Plaintiff, Venture Construction Company (hereafter called 'Construction Company') appeals from the grant of a motion for partial summary judgment to co-defendant Great American Mortgage Investors ('GAMI'). The motion was addressed solely to paragraph 12.
In its complaint Construction Company alleged that defendants GAMI and Foursquare Development Corporation were joint venturers in a condominium real property development. While defendants denied such joint venture relationship existed it was assumed arguendo in considering GAMI's partial summary judgment motion, that the joint venture did exist. Based, in part, upon this assumption, the facts giving rise to this appeal may be summarized as follows:
On January 14, 1972, Construction Company entered into a building contract with Foursquare. The parties stipulated the guaranteed maximum cost of the project would be $1,085,720.00, subject to adjustment in accordance with the terms of the contract. Following commencement of the construction, work continued thereon throughout 1972. However, various disputes subsequently arose between plaintiff and defendants concerning certain expenditures made by plaintiff at the direction of the defendants. To settle their differences with the goal of completing construction, they finally reached an agreement. The terms thereof were stated in a lengthy document approved February 2, 1973, which the parties designated by the term 'modification agreement.'
In part the modification agreement reads:
Following this contractual settlement of its dispute with defendants, plaintiff completed construction of the condominium project. Despite plaintiff's demand for payment, defendants refused to pay plaintiff any monies after September 12, 1973, when $26,478.00 remained owing under the original agreement. Moreover, defendants were unable to pay plaintiff the agreed amount of $72,251.68 established by the modification agreement as the increased cost over the original agreed maximum.
This suit was then instituted. Damages claimed are $26,478.00 under the original contract, $72,251.78 representing the cost increases of the change orders agreed to in the modification agreement, and $97,987.15 in '. . . additional direct costs for the completion of the work . . .' (R. 12). This last item is contested by GAMI on the basis that it was settled by the modification agreement and constituted an accord and satisfaction. The trial court sustained this contention. Construction Company has taken this appeal from that partial summary judgment. Held:
1. Appellant's able attorney ardently argues that the modification agreement was not supported by a valid consideration; that, therefore, the agreement amounted to a mere executory accord; that there had been no satisfaction of the accord; and that, accordingly, plaintiff is entitled to seek the 'additional direct costs' in paragraph 12 pursuant to a theory of implied contract. This argument is erroneous.
First, we do not construe paragraph 12 as setting forth a quantum meruit claim for relief. It neglects to mention implied contract; and, more importantly, it fails to disclose the 'reasonable value' of the services rendered. Second, even assuming that a quantum meruit claim is set forth, the claim must fail for the reasons presented below.
In Riley & Co. v. London Guaranty etc. Co., 27 Ga.App. 686, 109 S.E. 676, this court noted: ...
To continue reading
Request your trial- Kot v. Richard P. Rita Personnel System Intern., Inc.
-
Hardin v. Hunter, 70070
...a recovery in quantum meruit is not authorized where an express contract exists. See generally Venture Constr. Co. v. Great American Mtg. Investors, 134 Ga.App. 440, 444, 214 S.E.2d 683 (1975). " 'A recovery under quantum meruit must be based upon a promise, express or implied, to pay for t......
-
Owens v. Landscape Perfections, Inc., A94A2559
...to grant Owens' motion to dismiss or in entering judgment in favor of Landscape. Relying on Venture Constr. Co. v. Great American Mtg. Investors, 134 Ga.App. 440, 214 S.E.2d 683 (1975), Owens maintains that Landscape is not entitled to recover against her because Adams had an express oral a......
-
Walsey v. Alterman Foods, Inc.
...of an agreed and liquidated amount is tantamount to a new consideration, does not apply. See Venture Construction Co. v. Great American Mtg. Investors, 134 Ga.App. 440, 214 S.E.2d 683. The trial court did not err in rejecting the argument that there was a binding accord and satisfaction nor......
-
Construction Law - Brian J. Morrissey
...Sec. 9-2-7 (1982). 43. 215 Ga. App. at 643, 451 S.E.2d at 496 (quoting Venture Construction Co. v. Great American Mtg. Investors, 134 Ga. App. 440, 214 S.E.2d 683 (1975)). 44. 215 Ga. App. at 643, 451 S.E.2d at 496. 45. 215 Ga. App. 697, 452 S.E.2d 140 (1994). 46. Id. at 697, 452 S.E.2d at ......