Vern J. Oja & Associates v. Washington Park Towers, Inc.

Decision Date22 September 1977
Docket NumberNo. 44501,44501
Citation569 P.2d 1141,89 Wn.2d 72
CourtWashington Supreme Court
PartiesVERN J. OJA & ASSOCIATES, a partnership, Respondent, v. WASHINGTON PARK TOWERS, INC., Petitioner, Cawdrey & Vemo, Inc., Manson Construction & Engineering Co., Respondents, Larsen Construction Company, Inc., Fifth West, Inc., and R. C. Hedreen Co., Inc., Defendants.

Murray, Dunham & Waitt, Robert K. Waitt, Barry M. Johnson, Seattle, for petitioner.

Schweppe, Doolittle, Krug, Logerwell & Cohen, Tausend, Beezer & Beierle, Warren A. Doolittle, Seattle, for respondent.

DOLLIVER, Associate Justice.

We granted the petition for review in order to review the opinion of the Court of Appeals in Oja & Associates v. Washington Park Towers, Inc., 15 Wash.App. 356, 549 P.2d 63 (1976). The facts as set out herein are substantially as stated by the Court of Appeals, and are as follows:

The Lakeview Lanai, a 42-unit apartment building located in Seattle, was constructed in 1959 and purchased by respondent, Oja & Associates, in 1964. Thereafter Washington Park Towers, Inc., the appellant and petitioner, as owner of property adjacent to the Lakeview Lanai, entered into a contract with Cawdrey & Vemo, Inc., for the construction of a condominium apartment building. Cawdrey & Vemo engaged Manson Construction & Engineering Company to drive the pilings necessary to support the planned building. Manson worked from August 1966 to September 1966. There was no construction activity at the site from September 1966 until October 1967. During this period, Cawdrey & Vemo and Manson were relieved of their responsibilities. Work resumed on the project in the fall of 1967, and Larsen Construction Company completed the pile driving between approximately November 1967 and April 1968. The building was completed in 1969. Oja & Associates filed this action on March 2, 1971, to recover for damage allegedly sustained by the Lakeview Lanai as a result of the pile driving and other construction activity associated with the condominium apartment building. Washington Park Towers, Cawdrey & Vemo, Manson, Larsen, Fifth West, Inc., and R.C. Hedreen Co., Inc., were named as defendants. The claims against Cawdrey & Vemo and Manson were dismissed with prejudice on motions for summary judgment. On April 17, 1974, judgment was entered on a jury verdict against Washington Park Towers for $73,100. In a special verdict, the jury attributed 70 percent of the damage to the pile driving which occurred between August and September of 1966, and the remaining 30 percent to the pile driving which occurred between November 1967 and April 1968. Washington Park Towers appealed; Oja cross-appealed.

The first issue before us is whether respondent Oja & Associates' claim was barred by the statute of limitations. Although the parties agree the 3-year statute of limitations for damages to real property (RCW 4.16.080) applies to respondent's claim, the question is when the claim "accrued" within the meaning of RCW 4.16.010 which provides in part Actions can only be commenced within the periods herein prescribed after the cause of action shall have accrued . . .

(Italics ours.) This action was filed on March 2, 1971. In order to be within the statutory period, the respondent's cause of action would have to have "accrued" after March 2, 1968. Petitioner's pile driving took place in August and September 1966 and again between November 1967 and April 1968. The building was completed in 1969.

Under petitioner's theory, the statute of limitations was triggered no later than September, 1966, when the first substantial damage occurred. If the cause of action accrued when the first substantial damage was done, under petitioner's theory no damage or at a maximum only 30 percent of the damage occurred within the statute of limitations' period. Under the respondent's theory, however, the claim for damages did not accrue until the completion of the construction project; consequently, 100 percent of the damage would have occurred within the period of the statute of limitations.

We agree with the position taken by the Court of Appeals and by the respondent Oja & Associates: The damages flowed from the pile driving as a whole and the cause of action accrued when the building was completed. We have reexamined the statute of limitation cases which have been before this court, as urged by respondent, and find this view to be consistent with these cases. See Gillam v. Centralia, 14 Wash.2d 523, 128 P.2d 661 (1942); Papac v. Montesano, 49 Wash.2d 484, 303 P.2d 654 (1956); Cheskov v. Port of Seattle,55 Wash.2d 416, 348 P.2d 673 (1960); Gazija v. Nicholas Jerns Co., 86 Wash.2d 215, 543 P.2d 338 (1975); Haslund v. Seattle, 86 Wash.2d 607, 547 P.2d 1221 (1976). In those cases involving damage to real property arising out of construction or activity on adjacent property, the cause of action accrues at the time the construction is completed if substantial damage has occurred at that time. If the damage has not occurred when the construction is completed the action accrues when the first substantial injury is sustained thereafter. In the instant case, substantial damage had occurred when the project was completed. The respondent was entitled to wait until the completion of the construction project before filing a cause of action so that it might determine the full extent of the damages. See Gillam v. Centralia,supra. A different rule would force a plaintiff to seek damages in installments in order to comply with the statute of limitations.

Petitioner argues Gillam, Papac and Cheskov should be distinguished since they all involve situations in which a governmental entity damaged real property without first going through a condemnation proceeding. We agree with the Court of Appeals that this distinction is not determinative.

The next issue before us is whether the trial court erred in applying strict liability to a pile driving activity. In the past, this court has found strict liability where damage was caused to plainti...

To continue reading

Request your trial
28 cases
  • Schuck v. Beck
    • United States
    • Washington Court of Appeals
    • 19 Octubre 2021
    ...Erickson Paving Co. v. Yardley Drilling Co. , 7 Wash. App. 681, 502 P.2d 334 (1972) (blasting); Vern J. Oja & Associates v. Washington Park Towers, Inc. , 89 Wash.2d 72, 569 P.2d 1141 (1977) (pile driving); Siegler v. Kuhlman , 81 Wash.2d 448, 502 P.2d 1181 (1972) (transporting gas as freig......
  • Lewis v. Krussel, 24599-0-II.
    • United States
    • Washington Court of Appeals
    • 16 Junio 2000
    ...authorities cited by Lewis and Teitzel do not apply in the fallen tree context. See, e.g., Vern J. Oja & Assoc. v. Washington Park Towers, Inc., 89 Wash.2d 72, 76-77, 569 P.2d 1141 (1977) (holding that pile driving on construction site was abnormally dangerous activity warranting strict lia......
  • Hurley v. Port Blakely Tree Farms L.P.
    • United States
    • Washington Court of Appeals
    • 7 Agosto 2014
    ...Erickson Paving Co. v. Yardley Drilling Co., 7 Wash.App. 681, 502 P.2d 334 (1972) (blasting); Vern J. Oja & Assoc. v. Washington Park Towers, Inc., 89 Wash.2d 72, 569 P.2d 1141 (1977) (pile driving); Siegler v. Kuhlman, 81 Wash.2d 448, 502 P.2d 1181 (1972) (transporting gas as freight by tr......
  • Johnson for Galdeira v. Robert's Hawaii Tour, Inc.
    • United States
    • Hawaii Court of Appeals
    • 25 Abril 1983
    ...592 P.2d 613 (Utah 1979); Vern J. Oja and Associates v. Washington Park Towers, Inc., 15 Wash.App. 356, 549 P.2d 63, aff'd, 89 Wash.2d 72, 569 P.2d 1141 (1976). As in all actions involving discretion, the trial court will not be overturned on appeal absent an abuse thereof. Appellant must s......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT