Vill. of Medina v. Dingledine
Decision Date | 14 April 1914 |
Parties | VILLAGE OF MEDINA v. DINGLEDINE et al. |
Court | New York Court of Appeals Court of Appeals |
OPINION TEXT STARTS HERE
Appeal from Supreme Court, Appellate Division, Fourth Department.
Action by the Village of Medina against Frederick W. Dingledine and others and the Title Guaranty & Surety Company of Scranton, Pa. From a judgment of the Appellate Division (152 App. Div. 307,136 N. Y. Supp. 786), affirming a judgment on the report of a referee in favor of defendant, Title Guaranty & Surety Company, plaintiff appeals. Affirmed.
John J. Ryan, of Medina, for appellant.
George E. Dennison, of Utica, for respondent.
In May, 1907, the appellant, through its board of sewer commissioners, entered into a written contract with a firm of contractors to construct certain sewers for the price of $37,347 .50. Thereafter the respondent, in accordance with the requirements of said contract, entered into a bond as surety with the appellant in the penal sum of $18,673.75 for the faithful performance of said contract by the contractors. After performing a considerable amount of work and furnishing a considerable amount of materials in the performance of their undertaking said contractors became in default, and the appellant, as it was legally entitled to do, excluded them from performance of the contract and itself completed the latter at its own expense. Prior to doing this it had made payments to the contractors to the amount of $29,268.83, and, including these payments and the expense of the work which it performed in completing the contract, it has expended the sum of upwards of $7,000 over and above the amount to which the contractors would have been entitled for completing their work, and it seeks to recover this sum, together with certain penalties for delay from the respondent under the bond executed by it is aforesaid.
It is conceded, or at least undisputed, that the amount expended by appellant for the construction of said sewers, plus any sum which has accrued in its favor for penalties, does not exceed the contract price fixed for the construction and completion of such work, unless it is entitled to be credited with said sum of $29,268.83, paid to the contractors as aforesaid. If it be true that the amount thus expended by it, plus any possible sum due for penalties, does not exceed the price which it agreed to pay the contractors for constructing the sewers, it is plain that it has not suffered any damages for nonperformance of the contract which may furnish the basis for a claim against the respondent on its bond. The pivotal question whether it is entitled to be credited with the payments made to the contractors as a lawful expenditure in connection with the construction of the work involves a consideration and interpretation of section 3 of the Labor Law. Consol. Laws, c. 31. This section reads as follows: ...
To continue reading
Request your trial-
E. Williamson Roofing and Sheet Metal Co., Inc. v. Town of Parish
...likewise knew or should have known of the prevailing wage requirement and is chargeable with such knowledge ( Village of Medina v. Dingledine, 211 N.Y. 24, 28, 104 N.E. 1118; see also, Matter of Cam-Ful Indus. v. Roberts, 128 A.D.2d 1006, 1007, 513 N.Y.S.2d 539). Moreover, to allow recovery......
-
Brian Hoxie's Painting Co., Inc. v. Cato-Meridian Cent. School Dist.
...720; see also, Associated Bldrs. & Contrs. v. City of Rochester, 67 N.Y.2d 854, 501 N.Y.S.2d 653, 492 N.E.2d 781; Village of Medina v. Dingledine, 211 N.Y. 24, 104 N.E. 1118). Further, such shifting of the burden from the contractor to the public entity would directly contravene the basic o......
-
BOARD OF ED. CENT. SCH. DIST. NO. 2 v. Aetna Cas. & Sur. Co.
... ... 68 Civ. 1162 (S.D.N.Y. May 11, 1970). For New York law, the Court relied on Village of Medina v. Title Guaranty & Surety Co., 152 App.Div. 307, 136 N.Y.S. 786 (4th Dept. 1912), aff'd, 211 N.Y ... ...
- McNamara v. Gregory