Waite v. Samson Development Co., Inc.

Citation217 Neb. 403,348 N.W.2d 883
Decision Date18 May 1984
Docket NumberNo. 83-485,83-485
PartiesRoss WAITE, doing business as Waite Construction Company, Appellant, v. SAMSON DEVELOPMENT COMPANY, INC., a corporation, and Inland Insurance Company, Inc., a corporation, Appellees.
CourtNebraska Supreme Court
Syllabus by the Court

1. Pleadings: Causes of Action. Under the code system of pleading it is not necessary to state a cause of action or a defense in any particular form. It is only necessary to plead the facts, not the theory of recovery.

2. Pleadings: Demurrer. A petition is sufficient [as against a general demurrer] if from the statement of facts set forth therein the law entitles the plaintiff to recover.

3. Pleadings: Causes of Action. Pleadings are to be liberally construed, and if with such construction a petition states a cause of action against a defendant and in favor of the plaintiff, a demurrer thereto should be overruled.

4. Pleadings: Causes of Action. The prayer of a petition is not a part of the allegations of fact constituting the cause of action, and where the facts state a cause of action and are supported by the evidence, the court will grant proper relief, though it may not conform to the relief prayed for.

5. Causes of Action. The essential character of a cause of action or the remedy or relief it seeks, as shown by the allegations of the complaint, determines whether a particular action is one at law or in equity, unaffected by conclusions of the pleader or the prayer for relief.

Thomas A. Wagoner, Grand Island, for appellant.

James W. Hewitt, Lincoln, for appellee Inland Ins. Co., Inc. KRIVOSHA, C.J., WHITE and CAPORALE, JJ., and McCOWN and BRODKEY, JJ., retired.

McCOWN, Justice, Retired.

Plaintiff filed suit in the district court for Valley County against Samson Development Company, Inc. (Samson), and Inland Insurance Company, Inc. (Inland), to recover for work done on a construction project. He was unable to obtain service upon Samson, and the action proceeded against Inland only. The trial court entered summary judgment in favor of Inland, and the plaintiff has appealed.

The petition alleged (1) that Samson entered into a contract with Friesen Building Corporation in September 1973, whereby Friesen was to complete construction of a low-rent housing project on property owned by Samson in Ord, Nebraska; (2) that Friesen entered into a labor and material payment bond with Inland in October 1973 to cover the performance of the contract and that plaintiff was within the class of persons covered by that bond; (3) that Friesen engaged plaintiff to do certain work as a subcontractor on the project; (4) that plaintiff completed the work and that nothing remained to be done under his contract; (5) that he furnished labor to the property from July 22 to October 14, 1974; (6) that the defendant promised to pay the plaintiff for the labor but that there remained due $4,541.40; (7) that on January 14, 1975, plaintiff filed a mechanic's lien in the office of the register of deeds of Valley County, Nebraska; (8) that Samson and Friesen and the city housing authority were notified of the lien; (9) that an action by plaintiff against Friesen, filed March 20, 1975, resulted in a judgment against Friesen for $4,541.40, plus costs and interest from July 25, 1975, which judgment had not yet been satisfied; (10) that plaintiff had been notified by a June 30, 1975, letter that Samson had transferred the mechanic's lien to an undertaking filed with the clerk of the district court, as per Neb.Rev.Stat. § 52-121 (Reissue 1978) (since repealed); and (11) that the action fell under Neb.Rev.Stat. § 44-359 (Reissue 1978) as to Inland and that an attorney fee would therefore be proper. The prayer of the petition reads:

WHEREFORE, Plaintiff prays for judgment against the Defendants, and each of them, in the amount of $4,541.40 plus interest from the 25th day of July, 1975, and the costs of this action, including the $73.00 costs taxed by the District County Court of Valley County, Nebraska, and for an attorney's fee to be taxed to the Defendant, Inland Insurance Company, as per Section 44-359, R.R.S., 1943, as amended; that the same be declared to be a statutory lien upon the fund presently on deposit with the office of the Clerk of the District Court of Valley County, Nebraska, as provided by Section 51-121 and 122, R.R.S., 1943, as amended, and for such other, further and different relief as to the Court may seem just and equitable in the premises.

Attached to the petition was a copy of the mechanic's lien and a copy of the labor and material bond.

Inland admitted (1) the existence of the contract between Friesen and Samson; (2) the execution of the labor and material bond; (3) the oral contract between Friesen and plaintiff; and (4) that plaintiff filed a mechanic's lien and that notice of the lien was given certain parties. Inland denied (1) that plaintiff was within the class of persons protected by the labor and material bond; (2) that the plaintiff's work was completed; (3) that plaintiff furnished labor between July 22 to October 14, 1974; (4) that defendant agreed to pay plaintiff for labor and that $4,541.40 remained to be paid; (5) that the mechanic's lien was a claim against the material bond; (6) that plaintiff had filed suit and obtained judgment against Friesen; (7) that plaintiff was notified of the transfer of the mechanic's lien by letter from Samson dated June 30, 1975; and (8) that the case was a proper case for an attorney fee.

Inland further alleged that, since Samson had not been served and the surety on the transfer bond had not been joined, no proper action had been brought on the transfer bond within the time period of § 52-121 (since repealed) and that the benefits of the lien had been forfeited.

Two particular sections of the labor and material bond are directly relevant.

1. A claimant is defined as one having a direct contract with the Principal or with a Subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the Contract, labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the Contract.

2. The above named...

To continue reading

Request your trial
15 cases
  • Trieweiler v. Sears
    • United States
    • Nebraska Supreme Court
    • 17 Diciembre 2004
    ...the nature of an action is determined not by the prayer for relief but from the character of the facts alleged. Waite v. Samson Dev. Co., 217 Neb. 403, 348 N.W.2d 883 (1984). (The petitions in this case were filed prior to the effective date of the Nebraska Rules of Pleading in Civil Action......
  • McCurry v. School Dist. of Valley
    • United States
    • Nebraska Supreme Court
    • 26 Febrero 1993
    ...plan of transportation" for her. While it is not necessary to state a cause of action in any particular form, Waite v. Samson Dev. Co., 217 Neb. 403, 348 N.W.2d 883 (1984), and in actions not involving extraordinary remedies, general pleadings are to be liberally construed in favor of the p......
  • Cass Const. Co., Inc. v. Brennan
    • United States
    • Nebraska Supreme Court
    • 28 Febrero 1986
    ...not necessary to state a defense in any particular form so long as the facts supporting the assertion are stated. Waite v. Samson Dev. Co., 217 Neb. 403, 348 N.W.2d 883 (1984). Cass next contends that the district court erred when it determined that § 1-207 does not alter or abolish the doc......
  • Bowman v. City of York
    • United States
    • Nebraska Supreme Court
    • 13 Marzo 1992
    ...by the evidence, the court will grant proper relief, although it may not conform to the relief requested. See, Waite v. Samson Dev. Co., 217 Neb. 403, 348 N.W.2d 883 (1984); Standard Reliance Ins. Co. v. Schoenthal, 171 Neb. 490, 106 N.W.2d 704 One of the issues in State Bldgs. Div. v. Town......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT