Weeks Marine, Inc. v. Fireman's Fund Ins. Co.

Citation340 F.3d 233
Decision Date25 July 2003
Docket NumberNo. 02-40825.,02-40825.
PartiesWEEKS MARINE, INC., Plaintiff-Appellant, v. FIREMAN'S FUND INSURANCE COMPANY, Defendant-Appellee.
CourtUnited States Courts of Appeals. United States Court of Appeals (5th Circuit)

Alan H. Goodman (argued), Leland Gray Horton, Lemle & Kelleher, New Orleans, LA, for Plaintiff-Appellant.

Nancy Hesse Hamren (argued), Coats, Rose, Yale, Ryman & Lee, Houston, TX, for Defendant-Appellee.

Appeal from the United States District Court for the Eastern District of Texas.

Before JOLLY, WIENER, and BARKSDALE, Circuit Judges.

WIENER, Circuit Judge:

Plaintiff-Appellant Weeks Marine, Inc.("Weeks") appeals the district court's order denying its motion for summary judgment and granting Defendant-Appellee Fireman's Fund Insurance Company's ("FFIC") motion for summary judgment. We reverse and remand for entry of judgment in favor of Weeks.

I. FACTS AND PROCEEDINGS

This surety contract dispute arises from dredging work that Weeks Marine completed for now-bankrupt shipbuilder Friede Goldman Offshore Texas, L.P. ("Friede Goldman"). In April 1998, Petrodrill Construction, Inc. ("Petrodrill") contracted with Friede Goldman ("the shipbuilding contract") for the construction of a semi-submersible drilling vessel ("Hull 1829"). In conjunction with the shipbuilding contract, FFIC issued an $84 million Labor and Material Payment Bond ("the bond") to Friede Goldman. Under the terms of the bond, FFIC as surety and Friede Goldman as principal are "held and firmly bound unto Petrodrill Construction" as owner and obligee, for "the use and benefits of claimants." A "claimant" is defined in the bond as

one having a direct contract with the Principal or with a Subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the Contract, labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the Contract.

Friede Goldman began construction of Hull 1829 at its shipyard in Pascagoula, Mississippi but eventually elected to complete construction at another shipyard in Orange, Texas. The parties vigorously dispute the cause of the move: FFIC maintains that Friede Goldman merely wanted to "keep that [Texas] yard busy"; Weeks asserts that the move was "necessary," but offers no further explanation. It is undisputed, however, that all parties (including FFIC) expressly approved the move. In fact, Petrodrill and Friede Goldman agreed to a $3 million increase in the contract price, and FFIC consented to a corresponding increase in the amount of the bond. These modifications were memorialized in "Amendment No. 2" to the shipbuilding contract.

In connection with the move, Friede Goldman subcontracted with Weeks to dredge a slip extension at the Texas shipyard. Weeks completed the dredging work and submitted an invoice to Friede Goldman in the amount of $654,671. To date, Weeks has not been paid for the dredging work; Friede Goldman filed for Chapter 11 bankruptcy protection several months after Weeks completed the dredging and is not a party to this suit.

Shortly after Friede Goldman filed for bankruptcy protection, Weeks filed suit against FFIC, invoking diversity jurisdiction and alleging that FFIC, as surety, is liable for the "labor performed and materials furnished" to Friede Goldman in connection with its performance of the shipbuilding contract. FFIC denied liability and the parties filed cross-motions for summary judgment. The district court granted FFIC's motion, concluding that "making FFIC pay Weeks would not serve the Bond's overriding purpose of preventing the attachment of liens to Petrodrill's new vessel." Weeks now appeals the denial of its motion and the grant of FFIC's motion.

II. ANALYSIS
A. Standard of Review

We review a grant of summary judgment de novo, applying the same standard as the district court.1 A motion for summary judgment is properly granted only if there is no genuine issue as to any material fact.2 An issue is material if its resolution could affect the outcome of the action.3 In deciding whether a fact issue has been created, we view the facts and the inferences to be drawn therefrom in the light most favorable to the nonmoving party.4

B. Merits

The sole issue presented in this appeal is whether Weeks's dredging of a slip extension at Friede Goldman's Orange shipyard is "labor" "used or reasonably required for use" in building Hull 1829. The construction of an unambiguous surety agreement is a question of law.5 Surety agreements, like other contracts, are "interpreted to ascertain the obligations intended by the parties, gathered from the instrument as a whole."6 The liability of a surety is determined by the language of the bond.7 When, as here, the surety agreement is related to another contract, the two instruments must be read together to determine the parties' intent.8

With these general rules of contract interpretation in mind, our analysis begins with the written terms of both the shipbuilding contract and the payment bond. The shipbuilding contract called for Friede Goldman to construct Hull 1829 for Petrodrill and perform all associated engineering, launching, and testing of the completed vessel. This contract defines "materials" as "all material and supplies, including without limitation all machinery, equipment, outfittings and spare parts ... to the extent that same have been appropriated to, or incorporated in, the Vessel." The shipbuilding contract does not define "labor."

The bond prescribes the obligations of FFIC. The bond states expressly that FFIC is liable only if Friede Goldman fails "promptly [to] make payment to all claimants" "for all labor and material used or reasonably required for use in the performance of the Contract." As noted earlier, the term "claimants" is defined in the bond, which also defines "labor and material" to include "water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the Contract."

Even though they arrive at widely varying interpretations, both parties assert that the terms of these agreements are unambiguous. FFIC argues that the dredging work is not covered under the bond because Weeks did not provide "materials" that were incorporated in the vessel but undertook a capital improvement to Friede Goldman's shipyard. Weeks agrees that the dredging was not "materials" as defined in the shipbuilding contract, but insists that the work was "labor" "used" in the construction of the vessel. Weeks asserts that it qualifies as a "claimant" under the bond because (1) it had a direct contract with Friede Goldman; (2) it provided "labor"; and (3) the labor was used in the performance of the shipbuilding contract.

Our resolution of this contract dispute rests on the plain language of the bond and the uncontroverted record evidence. We have seen that, under the bond, a "claimant" is "one having a direct contract with the Principal [Friede Goldman] ... for labor, materials or both, used or reasonably required for use in the performance" of the shipbuilding contract. The parties do not dispute that Weeks had a direct contract with Friede Goldman or that Weeks provided "labor." Rather, FFIC contends that the labor Weeks provided was not used "in the performance of the contract." For at least three reasons, we disagree.

First, in support of summary judgment, Weeks submitted the affidavit of Friede Goldman officer John Haley who stated that "[t]he labor and materials provided by Weeks" were "required by [Friede Goldman] for the performance and completion of Hull 1829." FFIC submitted no contradictory evidence on this crucial point.9 Second, FFIC itself acknowledged (in a letter to Weeks's counsel denying the claim) that the dredging was "required in order to fulfill [Friede Goldman]'s obligation under the [Petrodrill] contract." Third, and most importantly, all of the parties, including FFIC, expressly contemplated the move before it took place, explicitly acceded to it, and increased the purchase price and bond accordingly, as documented in Amendment No. 2. Whether the move was necessary, or even prudent, is irrelevant; it was unquestionably made "in performance of the contract."

Finding little support in the express terms of the bond, FFIC relies on cases arising under the Miller Act and analogous state statutes to support its argument that dredging is a capital improvement and is not encompassed by a standard labor and material bond. Under these cases, "material" includes "things which will be incorporated into the project itself, such as steel beams, brick, window frames, flooring and roofing."10 "Materials" also includes products that are not ultimately integrated into the project, but that are "reasonably expected to be consumed, or substantially consumed, in the performance of the work."11 Thus, capital equipment, including items that can be removed and used on subsequent projects, are not "materials"; only those consumable items that will "have no utility or economic value to the contractor after the completion of the work" are covered under statutory bonds as "materials."12

FFIC's reliance on these authorities is misplaced for several reasons. First, and most importantly, Weeks is seeking payment for "labor," not "materials." Weeks agrees that the pipes, tools, and heavy machinery used to dredge the slip are not "materials" covered by the bond; Weeks only seeks payment for labor, and then only labor that was "used or reasonably required for use" in Friede Goldman's performance of the shipbuilding contract. Perhaps understandably, FFIC largely ignores this fundamental distinction.13

Second, even if we were to accept FFIC's capital-improvement argument, the competent summary judgment evidence reveals that Weeks's dredging was not a capital improvement to Friede Goldman's shipyard. In a...

To continue reading

Request your trial
180 cases
  • Kothmann Enterprises, Inc. v. Trinity Industries
    • United States
    • U.S. District Court — Southern District of Texas
    • September 30, 2005
    ...540 (5th Cir.2005). "An issue is material if its resolution could affect the outcome of the action." Weeks Marine, Inc. v. Fireman's Fund Ins. Co., 340 F.3d 233, 235 (5th Cir.2003) (citing Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986)). If the mov......
  • Suzlon Wind Energy Corporation v. Shippers Stevedoring Company
    • United States
    • U.S. District Court — Southern District of Texas
    • January 27, 2009
    ...affect the outcome of the action.'" DIRECTV, Inc. v. Robson, 420 F.3d 532, 536 (5th Cir.2005) (quoting Weeks Marine, Inc. v. Fireman's Fund Ins. Co., 340 F.3d 233, 235 (5th Cir.2003)). "If the moving party fails to meet its initial burden, the motion for summary judgment must be denied, reg......
  • Lindquist v. City of Pasadena, Tex.
    • United States
    • U.S. District Court — Southern District of Texas
    • September 10, 2009
    ...affect the outcome of the action.'" DIRECTV, Inc. v. Robson, 420 F.3d 532, 536 (5th Cir.2005) (quoting Weeks Marine, Inc. v. Fireman's Fund Ins. Co., 340 F.3d 233, 235 (5th Cir.2003)). "If the moving party fails to meet its initial burden, the motion for summary judgment must be denied, reg......
  • Martin v. Tex. Dept. of Protect. and Regul. Srvcs., Civ.A. H04-4160.
    • United States
    • U.S. District Court — Southern District of Texas
    • December 16, 2005
    ... ... Boudreaux v. Swift Transp. Co., Inc., 402 F.3d 536, 540 (5th Cir.2005). "An issue is ... could affect the outcome of the action." Weeks Marine, Inc. v. Fireman's Fund Ins. Co., 340 ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT