Wes Podany Const. Co., Inc. v. Nowicki, s. 83-1657

Decision Date24 July 1984
Docket NumberNos. 83-1657,83-2083,s. 83-1657
Citation120 Wis.2d 319,354 N.W.2d 755
PartiesWES PODANY CONSTRUCTION CO., INC., a Wisconsin corporation, Plaintiff- Appellant, v. Walter A. NOWICKI, and Parnell Woods Association, a condominium association, Defendants, Thomas Bauman and Barbara Bauman, his wife, Defendants-Respondents. WES PODANY CONSTRUCTION CO., INC., a Wisconsin corporation, Plaintiff- Appellant, v. Walter A. NOWICKI, and Parnell Woods Association, a condominium association, Defendants, Raymond W. Quandt and Ruth Quandt, his wife, Defendants-Respondents.
CourtWisconsin Court of Appeals

Review Denied.

Jerome E. Randall, Milwaukee, for plaintiff-appellant.

Piette, Knoll & Nelson, S.C., Milwaukee, for defendants-respondents Thomas and Barbara Bauman and Raymond and Ruth Quandt; Thomas H. Knoll, Milwaukee, of counsel.

Before DECKER and MOSER, JJ., and MICHAEL T. SULLIVAN, Reserve Judge.

MOSER, Judge.

This is an appeal from separate summary judgments dismissing Wes Podany Construction Co., Inc.'s (Podany) lien foreclosure actions against two condominium properties in the Parnell Woods Condominiums, one owned by Thomas and Barbara Bauman (Baumans) and the other by Raymond W. Quandt and Ruth Quandt (Quandts). Podany appeals.

On January 1, 1979, Podany entered into a contract with Walter A. Nowicki (Nowicki) to provide masonry work and materials for the condominium project. During the time Podany supplied his materials and accomplished his masonry work, Nowicki sold Unit 1 in Building 16 to the Baumans. The Baumans' deed was recorded in the register of deeds office on October 15, 1979. Nowicki sold Unit 1 in Building 11 to the Quandts and the deed was recorded on December 10, 1979. Podany completed the work on or about December 14, 1979. On February 20, 1980, he gave Nowicki a notice of intent to file a lien claim against the condominium properties in Buildings 11 and 16 as required under sec. 779.06(2), Stats. On May 12, 1980, Podany filed his lien pursuant to sec. 779.06(1) and (3), Stats., 1 for the separate amounts of $2,151 and $2,577.44 against the Quandts' and the Baumans' units respectively.

On September 26, 1983, and on November 16, 1983, Podany filed his summonses and complaints for foreclosure against the Baumans' and the Quandts' condominium units. 2 The record does not disclose whether the Baumans answered the complaint, but the Quandts did answer. Both the Baumans and the Quandts moved for summary judgment on the basis that they, as owners, received no notice of intent to file a lien claim under sec. 779.06(2), Stats. Both trial courts granted summary judgment.

There is no question that at the time Podany contracted for and commenced the mason work on Units 11 and 16 Nowicki was the owner of the premises. It is less clear from the record when Podany did the last work on these premises, but there is no question as to whether Podany's last work was completed within five months prior to the notice of intent to file lien sent to Nowicki. It is undisputed that the lien was filed within thirty days after the notice of intent was served upon Nowicki or within six months after the last work was completed on the units as required by law. Likewise, it is undisputed that separate foreclosure complaints against the unit owners were filed within two years after the last work on the subject property.

The sole issue on this appeal is whether the notice of intent to file a lien under sec. 779.06(2), Stats., served on Nowicki was effective to allow a lien foreclosure against the Baumans' and the Quandts' condominium units.

Both trial courts held that because no notice of intent to file a lien was provided to the Baumans and the Quandts as required under sec. 779.06(2), Stats., and because they were the owners on the day the notice of intent to file a lien was served on Nowicki, no lien foreclosure could be brought against the Baumans and Quandts. Therefore, they dismissed the complaints via summary judgment.

Podany argues that the notice of intent to file a lien under sec. 779.06(2), Stats., must be served on the owner of the premises who was owner at the time the prime contractor first furnished work or materials on the premises. This party remains the owner, he argues, regardless of any transfer of ownership between the date of the first furnishing of work or materials and the date of the service of the notice of intent to file a claim for lien, unless the material and labor contractor had actual or constructive notice of any conveyance within that period. He cites as authority the supreme court decision in Duitman v. Liebelt. 3 The Baumans and Quandts argue that Duitman is not authority for the instant case because the statute on which that decision was based is no longer the Wisconsin law. 4

Construction liens for work and materials are purely statutory and cannot be maintained beyond the extent of the legislative grant conferred. 5 One pursuing rights under the Wisconsin construction lien law must follow the statute or lien rights fail. 6 Nevertheless, our lien laws are remedial in character and are to be liberally construed to give effect to the legislative intent of protecting the claims of tradesmen, laborers and materialmen for work and materials supplied. 7

The 1957 statutes separated lien rights of contractors and subcontractors. 8 In 1967 the state legislature removed this difference in situations where labor and material suppliers work directly for the owner; the legislature established those suppliers as prime contractors. 9 In 1979 the whole subject of liens was transferred to ch. 779 of the statutes. 10 In the 1967 revision there were some changes, including the creation of the notice of intent to file for lien under sec. 289.06(2), Stats. (1967), which remained the same under sec. 779.06(2), Stats. (1979). The notice required under sec. 289.02(2), Stats. (1965), was merged into sec. 289.06, Stats. (1967), and sec. 779.06, Stats. (1979). 11 Generally stated, after the 1967 changes, a prime contractor for an owner was required to meet the notice of intent to file a lien and lien filing requirements to preserve his lien, provided that he hired no subcontractors to fulfill the work and materials requirements of his contract. 12 To protect his prime contractor's lien after 1968, and to this date, the contractor for an owner is required to follow the mandates of what is presently sec. 779.06, Stats. 13

The term "prime contractor" was introduced to the lien statutes in sec. 289.01(2), Stats. (1967), partially to avoid the anomalous treatment of construction contractors. The term encompasses only those persons who deal directly with the owner. It further recognizes the distinction between prime contractors who contract to improve the land of someone else and the owner who does the general contracting for improvements of his own land. Both, in fact, are prime contractors. Under prior law, and in a factual situation like that in Duitman, a subcontractor might suddenly find himself a contractor if he dealt with an owner who happened to be his general contractor. 14

It is long-established law in Wisconsin that a contractor does not lose his lien rights if, after he commences work, the owner with whom he contracted conveys the property to another, provided the contractor has no actual or constructive notice of the conveyance, and further provided that he complies with the then extant lien statute notice provisions. 15 The critical date for the contractor to check ownership or title to property on which he is working or supplying materials is the first day the contractor supplies either materials or work, because his lien rights arise on that date. 16 He is not required to search the title for new conveyances of the property each time he furnishes further labor and material under his original contract. 17 In other words, the common law interpretation of sec. 292.02(1), Stats. (1957), under Duitman is good law today when applied to sec. 799.06(2), Stats. (1979).

Because sec. 289.02(1) of the 1957 statutes, on which the Duitman case was based, was merged into the successor notice statutes, a contractor's lien rights will prevail against a subsequent owner or owners. The contractor will prevail provided he commenced work before the transfer of title, if he met the statutory requirements to perfect his lien and if he acted without actual or constructive notice of the title transfer. That contractor is entitled to foreclose his lien rights if he gave the notice of intent to file his lien and filed his lien within six months of the day the last work was performed under his contract with the original owner. It matters not that the new owners, in this case the Baumans and the Quandts, received no notice of intent to file a claim for lien under sec. 779.06(2), Stats., because Podany, as a prime contractor, gave a proper notice to Nowicki, the owner at the time he commenced his prime contract work. There is nothing in the trial court record that shows Podany had any actual or constructive notice of a change of ownership from Nowicki to the Baumans or the Quandts. Under Duitman, Podany was not obligated to check the current owner every time he did some masonry work. Nowicki owned the condominiums at the time Podany was required to check their ownership and it is undisputed that Nowicki entered into the masonry contract. Therefore, under these facts, there could be only one owner, within the statutory meaning, to whom notice was necessary and that was Nowicki. 18 Podany also complied with the timely filing of his lien and foreclosed his lien within the proper statutory period.

Because the lien law is remedial to protect prime contractors like Podany, the trial courts erred in granting summary judgment to the Baumans and the Quandts and the matter is remanded for trial. We note that Podany requests a remand...

To continue reading

Request your trial
10 cases
  • Great Lakes Excavating, Inc. v. Dollar Tree Stores, Inc.
    • United States
    • Wisconsin Supreme Court
    • June 22, 2022
    ...Inc. v. Spirit Master Funding VIII, LLC, 2017 WI App 42, ¶2, 377 Wis. 2d 149, 900 N.W.2d 94 (quoting Wes Podany Constr. Co. v. Nowicki, 120 Wis. 2d 319, 324, 354 N.W.2d 755 (Ct. App. 1984) ); see also Goebel v. Nat'l Exchangors, Inc., 88 Wis. 2d 596, 606, 277 N.W.2d 755 (1979) ; Tri-State M......
  • American Wood Dryers, Inc. v. Bombardier Capital
    • United States
    • U.S. District Court — Western District of Wisconsin
    • November 26, 2002
    ...See Goebel v. National Exchangors, Inc., 88 Wis.2d 596, 606, 277 N.W.2d 755, 760 (1979); see also Wes Podany Construction Co., Inc. v. Nowicki, 120 Wis.2d 319, 324, 354 N.W.2d 755, 758 (1984) ("One pursuing rights under the Wisconsin construction lien law must follow the statute or lien rig......
  • Torke/Wirth/Pujara, Ltd. v. Lakeshore Towers of Racine
    • United States
    • Wisconsin Court of Appeals
    • January 10, 1995
    ...of Korndoerfer and all subcontractors." Siesel agrees with the trial court's determination, citing Wes Podany Constr. Co. v. Nowicki, 120 Wis.2d 319, 324, 354 N.W.2d 755, 758 (Ct.App.1984), for the proposition that Wisconsin's lien laws should be liberally construed to give effect to the le......
  • Hubbell Steel Corp. v. WP & L
    • United States
    • Wisconsin Court of Appeals
    • July 26, 1995
    ...effect to the legislative intent of protecting the claims of suppliers of work and materials. See Wes Podany Constr. Co. v. Nowicki, 120 Wis.2d 319, 324, 354 N.W.2d 755, 758 (Ct.App.1984). In the case of a private construction contract, a party who performs work or provides labor, materials......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT