Westec Const. Management Co. v. Postle, No. 01CA1055

Decision Date07 November 2002
Docket Number No. 01CA1632., No. 01CA1055
Citation68 P.3d 529
PartiesWESTEC CONSTRUCTION MANAGEMENT COMPANY, Plaintiff and Counterclaim Defendant-Appellee and Cross-Appellant, v. POSTLE ENTERPRISES I, INC., Defendant and Counterclaim Plaintiff-Appellant and Cross-Appellee.
CourtColorado Court of Appeals

York & Gregory, P.C., Glenn W. Gregory, Denver, Colorado, for Plaintiff and Counterclaim Defendant-Appellee and Cross-Appellant.

Berg Hill Greenleaf & Ruscitti, LLP, Kathleen M. Morgan, George V. Berg, Jr., Heidi C. Potter, Boulder, Colorado, for Defendant and Counterclaim Plaintiff-Appellant and Cross-Appellee.

Opinion by Judge DAVIDSON.

In this breach of contract action, defendant, Postle Enterprises I, Inc., appeals from the trial court's judgment on remand determining that it failed to mitigate its damages against plaintiff, Westec Construction Management Company. Westec separately appeals the trial court's awards of postjudgment interest, attorney fees, and costs to Postle, and Postle cross-appeals the calculation of per diem interest. The two appeals have been consolidated. We affirm in part, reverse in part, and remand.

In 1995, Westec contracted to build a fastfood restaurant for Postle. Although Postle was responsible for the cost of marking the property boundaries under the contract, Westec hired a surveyor to set the property pins. After the foundation was built, Westec discovered that it was in the wrong location and encroached on neighboring property, and Westec stopped construction. Westec disclaimed any liability for the mistake, but the surveyor acknowledged its error.

With minimal involvement from Westec, Postle and the surveyor began discussing possible remedies. Within a few days, the surveyor obtained an estimate from Westec and agreed to pay the cost of demolishing and relocating the foundation, with any consequential damages to be negotiated later. Postle rejected the offer, indicating that it would settle only the entire controversy, including its claims for lost profits, staffing costs, and other damages caused by the delay in completion. The parties also discussed the possibility of acquiring part of the neighboring property, which Postle viewed as the more expedient option.

After the surveyor requested an estimate, Westec sent Postle a change order that increased the contract sum by over $60,000 and the contract time by forty-six days, and Westec indicated that it could commence work on the project the following week if given notice to proceed. Postle did not sign the change order or give Westec notice to proceed, but continued to negotiate with the surveyor.

The following month, Postle's lender notified it that a continued construction stoppage would constitute a default and indicated that if Postle did not reach an agreement with the surveyor and move forward with the demolition and reconstruction, the lender would accelerate the balance of the loan. Postle did not respond, and the property was ultimately foreclosed upon.

Subsequently, Westec redeemed the property, and the surveyor purchased part of the neighboring lot and suggested that Postle allow construction to commence in the present location and negotiate consequential damages later. Postle rejected the offer, but eventually, after this lawsuit was filed, Westec conveyed the property to Postle, and construction was recommenced. The restaurant was completed approximately twenty-seven months after the date called for in the contract.

Westec sued Postle for payment under the contract, and Postle counterclaimed for breach of contract. Westec's claims for payment were settled before trial. After a bench trial, the court entered judgment for Postle in the amount of $168,371, which primarily represented damages for relocation of the foundation, staffing costs, and lost profits. However, the court refused to award any additional damages to Postle for the twenty-seven-month delay because Postle failed to give notice to Westec as provided in a provision of the contract.

Postle appealed, and another division of this court determined that the failure to give notice was not a proper basis to limit those damages. The division remanded the case for a determination of whether Postle otherwise failed to mitigate those damages and for an award of prejudgment interest. Westec Constr. Mgmt. Co. v. Postle Ents. I, Inc., (Colo.App. No. 98CA1997, Jan. 27, 2000)(not published pursuant to C.A.R. 35(f))(Westec I).

On remand, the trial court again found that Postle had failed to mitigate its damages and, accordingly, awarded no additional damages. The trial court awarded prejudgment interest and subsequently awarded certain postjudgment costs and attorney fees, as well as postjudgment interest on the prejudgment interest from the date of the original judgment.

Postle appeals from the trial court's determination that it failed to mitigate its damages and the calculation of the per diem amount of postjudgment interest. Westec appeals the award of postjudgment interest on the prejudgment interest and the amount of attorney fees and costs awarded. We reverse those parts of the judgment awarding postjudgment interest prior to the date of the judgment on remand and calculating the per diem amount, and otherwise we affirm.

I.

Postle contends that because allowing demolition and reconstruction of the foundation would have required it to sign Westec's change order, the trial court erred in concluding that Postle failed to mitigate its damages. Postle argues that signing the change order would have required it to abandon a right of action against Westec and, therefore, was not a reasonable mitigation alternative as a matter of law. We disagree.

A party seeking recovery under a contract has a duty to mitigate its damages. La Casa Nino, Inc. v. Plaza Esteban, 762 P.2d 669 (Colo.1988). "The defense of failure to mitigate damages applies when a plaintiff has failed to exercise reasonable care and diligence to minimize or lessen damages occasioned by defendant's conduct." Berger v. Sec. Pac. Info. Sys., Inc., 795 P.2d 1380, 1385 (Colo.App.1990).

"A plaintiff's failure to mitigate damages is excused, however, if mitigation would require inordinate or unreasonable measures or if there were reasonable grounds for the failure to mitigate." Fair v. Red Lion Inn, 943 P.2d 431, 437 (Colo.1997). For example, a party "need not accept a modified contract in mitigation of its damages when the modified offer includes abandonment of any right of action for a prior breach as a condition of acceptance." Stanspec Corp. v. Jelco, Inc., 464 F.2d 1184, 1187 (10th Cir.1972).

Ultimately, whether a party made reasonable efforts to mitigate its damages is a determination of fact, which will not be disturbed on appeal unless it is clearly erroneous. See Fair v. Red Lion Inn, supra.

In determining that Postle failed to mitigate its damages, the trial court noted that Postle:

declined to authorize the work to correct the placement of the footings and foundation, declined to accept the offer by [surveyor] to pay for the necessary demolition and reconstruction, declined to accept [surveyor's] offer to preserve the issue of all consequential damages and began negotiations with [surveyor] to purchase the additional lot and demanded resolution of all consequential damages prior to commencing the correction of the construction problem. This continued through April of 1996. At that point in time, Postle was estimating its consequential damages in the amount of $385,000 to $485,000. The Court further finds that Postle's estimates at that juncture were based upon estimates only and were not based upon fact nor could they have been until after a determination had been made concerning actual consequential damages or losses sustained as a result of the delays.... The Court finds that Postle delayed the matter to achieve its goal of receiving the conveyance of the lot that the foundation encroached upon.

These findings are supported by the record and are not clearly erroneous. Postle's evidence indicates that its primary concern with the change order was that it believed it should not have to pay for relocating the foundation and could not afford to do so. Although Postle also provided testimony that it objected to extending the contract, Postle did not give Westec any other form of notice to proceed, nor did it negotiate or object to the form of the change order. It also failed to indicate to the surveyor that the change order was the reason for its refusal to give Westec notice to proceed, and it failed to provide requested documentation to the surveyor for its claimed expenses. Westec introduced testimony indicating that it would have begun construction if Postle had orally agreed to accept and use the surveyor's funds to pay Westec for the relocation, that it was concerned only with payment, not with attempting to obtain a waiver from Postle, and that Postle never expressed any concerns about waiving its rights under the contract. Additional testimony indicated that Postle wanted to wait to get the land from the surveyor rather than immediately correct the location of the foundation.

Postle attempts to frame the issue, however, as a question of law, contending that the trial court erroneously rejected the proposition that a party need not accept, as mitigation, a modification offer that is conditioned on the abandonment of a right of action. Postle points to the following language in the court's order:

Throughout the trial, Postle complained that [it] could not accept the offer of [surveyor] to resolve the misplaced foundation issue without a resolution of all the issues because of the potential of waiver of consequential damages. Postle's assertion is an incorrect statement of the law. A damaged party entitled to the benefit of a contract, as Postle was here with Westec, is under a duty to mitigate damages and
...

To continue reading

Request your trial
4 cases
  • People v. Shifrin
    • United States
    • Colorado Court of Appeals
    • February 27, 2014
    ...controversy is only one factor for the court to consider in awarding fees. See id. at 147 ; see also Westec Constr. Mgmt. Co. v. Postle Enters. I, Inc., 68 P.3d 529, 536 (Colo.App.2002) (fact that plaintiff's postjudgment attorney fees exceeded the difference between the amount of its origi......
  • Thompson v. United Sec. Alliance, Inc.
    • United States
    • Colorado Court of Appeals
    • September 8, 2016
    ...to the entry of the judgment on remand, the trial court lacks jurisdiction to award such interest." Westec Constr. Mgmt. Co. v. Postle Enters. I, Inc. , 68 P.3d 529, 535 (Colo. App. 2002). ¶ 36 Accordingly, because the Thompson III mandate did not direct the district court to award postjudg......
  • U.S. Welding, Inc. v. Advanced Circuits, Inc.
    • United States
    • Colorado Supreme Court
    • June 18, 2018
    ..."inherent in settlement is a forfeiture of legal rights and such a forfeiture is not required."); Westec Constr. Mgmt. Co. v. Postle Enters. I, Inc., 68 P.3d 529, 532 (Colo. App. 2002) ("[A] party need not accept, as mitigation, a modification offer that is conditioned on the abandonment of......
  • Stewart Title Guar. Co. v. Williams
    • United States
    • U.S. District Court — District of Colorado
    • October 25, 2012
    ...affirmative defense). "A party seeking recovery under a contract has a duty to mitigate its damages." Westec Constr. Mgmt. Co. v. Postle Enters. I, Inc., 68 P.3d 529, 532 (Colo. App. 2002). "The defense of failure to mitigate damages applies when a plaintiff has failed to exercise reasonabl......
1 books & journal articles
  • Unique Construction Defect Damages Mitigation Issues
    • United States
    • Colorado Bar Association Colorado Lawyer No. 44-2, February 2015
    • Invalid date
    ...repair and builder's failure to respond to owners' alternate proposed dates). [46] Cf. Westec Constr. Mgmt. Co. v. Postle Enters. I, Inc., 68 P.3d 529, 533 (Colo.App. 2002) (party " need not accept a modified contract in mitigation of its damages when the modified offer includes abandonment......