WH Moseley Co., Inc. v. United States, 56-81.

Decision Date21 April 1982
Docket NumberNo. 56-81.,56-81.
PartiesW. H. MOSELEY COMPANY, INC. v. The UNITED STATES.
CourtU.S. Claims Court

John L. Runft, Boise, Idaho, attorney of record, for plaintiff. Runft, Stecher & Coffin, Ctd., Boise, Idaho, of counsel.

Sara V. Greenberg, Washington, D. C., with whom was Asst. Atty. Gen., J. Paul McGrath, Washington, D. C., for defendant.

Before FRIEDMAN, Chief Judge, and BENNETT and SMITH, Judges.

ON DEFENDANT'S MOTION FOR SUMMARY JUDGMENT

SMITH, Judge:

On March 23, 1982, we issued an order in this contract case, granting defendant's motion for summary judgment and dismissing the petition, in which order we stated that this opinion would follow. In that order we ruled, on the basis of our opinion in Paul E. Lehman, Inc. v. United States,1 that (1) certification of a claim pursuant to section 6(c)(1) of the Contract Disputes Act of 1978 (act)2 is a jurisdictional prerequisite to a direct challenge in this court of a contracting officer's decision, and that (2) the Government may not be estopped, by any asserted "waiver" by the contracting officer, of that statutory requirement, to claim that the proper certification is lacking.

Plaintiff's third contention, that it had in effect complied with the statutory certification requirements, was rejected in our order of March 23, 1982, with a statement that our rationale for that conclusion would be given in this opinion.

The facts necessary to our decision are as follows: plaintiff suggested certain changes in the performance requirements of a contract of January 31, 1978, it had with the Defense Logistics Agency and claimed that these changes entitle it to a monetary award based on the savings defendant realized from implementing the suggestions. Both parties agree that plaintiff's claim to the contracting officer was finalized well after the effective date of the act. There is no issue as to whether, if certification is not a barrier to plaintiff's claim, the claim meets the other prerequisites of the act.

Plaintiff argues that documents and letters submitted on its claim for the award, originally on June 15, 1979, and, in subsequent correspondence, including a supplementary memorandum and economic analysis, submitted on September 22, 1979, taken as a whole, amount to a certification. In its original memorandum in support of its claim, plaintiff adverted to the economic evaluation attached thereto prepared by Dr. Mitchell, an economist, as follows:

The economic evaluation in support of said memorandum prepared by Dr. John W. Mitchell, an economist, concludes with these words regarding his belief that the amount requested accurately reflects the amount for which the government is liable:
In this situation, the basic theory, the timing of events, actual rejection of low bids, the contrasts with other years, and the opinions of those in the industry would support the proposition that a savings resulted from the implementation of the Moseley Company suggestion. An average of the approaches would support a savings of about $1.87 million.

Section 605(c)(1) states that:

For claims of more than $50,000, the contractor shall certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of his knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.

To begin with, in light of our holdings above, and in Lehman, we must reject plaintiff's assertion that the statute leaves the determination of the adequacy of the certification to the contracting officer's discretion.

...

To continue reading

Request your trial
21 cases
  • California v. United States
    • United States
    • U.S. Claims Court
    • 31 Mayo 2020
    ...41 U.S.C. § 605(c)(1).'" D.L. Braughler Co., Inc. v. West, 127 F.3d 1476, 1480 (Fed. Cir. 1997) (quoting W.H. Moseley Co. v. United States, 230 Ct. Cl. 405, 677 F.2d 850, 852 (1982) (citing 41 U.S.C. § 605(c)(1)) (current version at 41 U.S.C. § 7103(b)(1) (2018))). Section 7103(b)(1) states......
  • Newport News Shipbuilding and Dry Dock Co. v. Garrett, 91-1432
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 5 Octubre 1993
    ...officer, there can be no appeal to this court under the CDA. It is a jurisdictional requirement. "); W.H. Moseley Co. v. United States, 677 F.2d 850, 852, 230 Ct.Cl. 405 ("Since failed to certify its claim as required by section 6(c)(1) of the Contract Disputes Act of 1978, we are without j......
  • U.S. v. W.H. Moseley Co.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 26 Marzo 1984
    ...Moseley's claim as one arising under the CDA, as an earlier decision by the United States Court of Claims in this case, W.H. Moseley Co. v. United States, 677 F.2d 850, cert. denied, --- U.S. ----, 103 S.Ct. 81, 74 L.Ed.2d 77 (1982), allegedly held that Moseley could not proceed under the C......
  • U.S. v. Turner Const. Co.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 3 Septiembre 1987
    ...Venture, ASBCA No. 31072-150, 85-3 BCA p 18,507; Sierra Blanca, Inc., ASBCA No. 30910, 85-3 BCA p 18,440. In W.H. Moseley Co. v. United States, 677 F.2d 850, 852, 230 Ct.Cl. 405, cert. denied, 459 U.S. 836, 103 S.Ct. 81, 74 L.Ed.2d 77 (1982), this court held that proper certification of a c......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT