WILDNER CONTRACTING CO. v. Ohio Turnpike Com'n
Decision Date | 26 January 1996 |
Docket Number | No. 1:95CV0696.,1:95CV0696. |
Citation | 913 F. Supp. 1031 |
Parties | R.J. WILDNER CONTRACTING CO., INC., Plaintiff, v. OHIO TURNPIKE COMMISSION, Defendant. |
Court | U.S. District Court — Northern District of Ohio |
COPYRIGHT MATERIAL OMITTED
COPYRIGHT MATERIAL OMITTED
Robert L. Tucker, Karen K. Grasso, Buckingham, Doolittle & Burroughs, Akron, OH, for R.J. Wildner Contracting Co. Inc.
Alan Neil Hirth, Thomas M. Wilson, Mark E. Leskovec, Climaco, Climaco, Seminatore, Lefkowitz & Garofoli, Cleveland, OH, for Ohio Turnpike Commission.
Hugh M. Stanley, Jr., Arter & Hadden, Cleveland, OH, for Hugh M. Stanley.
R.J. Wildner Contracting Company brought this diversity action against the Ohio Turnpike Commission (OTC) for breach of contract, misrepresentation, recision of a contract, superior knowledge, unjust enrichment, and conversion. After the OTC answered the original complaint, Wildner asked for and received leave to file an amended complaint. The OTC has now moved pursuant to Fed.R.Civ.P. 12(b)(6) to dismiss each count of the amended complaint for failure to state a claim upon which relief can be granted. The OTC has also moved pursuant to Fed.R.Civ.P. 12(b)(1) to dismiss count V of the amended complaint for lack of subject matter jurisdiction. For the reasons which are stated below, the OTC's motion to dismiss is granted in part and denied in part.
Contract, § SP 101.
The contract estimated that the bridge covered 205,300 square feet and that approximately 35 tons of hazardous and non-hazardous waste would be generated during the removal process. As it turned out, the bridge actually covered 213,149 square feet. More importantly, the existing paint was much thicker than Wildner anticipated ("abnormally thick" in the language of Wildner's complaint) and far more waste was generated. In addition, removing the thicker coating required a greater expenditure of labor, materials and time than Wildner had anticipated. Wildner alleges that the OTC had information in its files which indicated that the coating was abnormally thick, but did not share this information with Wildner.
Wildner sought compensation from the OTC for this work, which it characterized as "extra work," in accordance with §§ G-4.02 and G-4.03 of the contract. Section G-4.02 ("Increased or Decreased Quantities") provides:
Section G-4.02 is explicitly amended by § SP 105 ("Increased or Decreased Quantities"), which adds the following language:
The Contractor's attention is directed to Item SP 525 — Hazardous Waste Classification, Handling, and Disposal and Item SP 525 — Non-Hazardous Waste Classification, Handling, and Disposal. The quantities shown for these items were determined from the best available information that existed during the preparation of the Plans and the estimates of quantities. In addition, at this time it is not known if the waste material will be hazardous or nonhazardous. Therefore, the Contractor is cautioned that the estimates of the quantities of these items (which estimate, as in other cases, is for bidding and bonding purposes only) are necessarily more speculative than estimates of some other types of work. Payment will be made in accordance with the unit price bid or when applicable, in accordance with the procedures set forth in G-4.02.
The next section, § G-4.03 ("Extra Work"), defines extra work and provides:
"Extra Work" is unforeseen work, including changes in any work which is made necessary by alteration of Plans, or necessary to complete the work or for other reasons, and which is ordered pursuant to Section G-4.02 or G-5.01. Extra work shall be performed by the Contractor as directed by the Engineer. In any situation deemed by the Engineer to be an emergency in which he shall consider such action necessary in order to save or protect life or property, he may require the performance of extra work by oral direction to the Contractor, which oral direction shall, however, be as promptly as possible confirmed in writing. In all other cases extra work shall be performed only after delivery to the Contractor of the Engineer's written order or direction therefor.
Section G-5.01 ("Authority of Engineer"), which § G-4.03 references, provides, in pertinent part:
The Engineer shall have authority to require the Contractor to perform extra work, including changes in work, whether or not the work to be changed shall already have been partly or completely performed; provided, however, that the exercise of such authority shall be limited to cases in which in the opinion of the Engineer it is necessary in order to provide for some unforeseen contingency arising in the course of the performance of the Contract, or shall otherwise be in furtherance of and subordinate to the carrying out of the objective of the Contract, and shall not be for the purpose of requiring the performance of new work, unrelated thereto.
When Wildner sought compensation under these provisions for the additional work performed, the OTC paid extra for the additional square footage, but not for removal of the "abnormally thick" existing paint. The OTC claimed that Wildner was responsible for determining how much work would be required to remove the paint before it bid on the contract under § G-2.04 (). Section G-2.04 provides:
The OTC did give Wildner an extension of time in which to complete performance, however.
As a condition of being awarded the contract, Wildner was required to deposit $75,760 in escrow with Society National Bank. On September 27, 1994, upon the completion of the project, Wildner requested the release of those funds. The OTC did not release the funds. When Wildner brought the original complaint in this case, the OTC filed a counterclaim for $30,000. Wildner then requested the release of the funds in excess of the $30,000 counterclaim, but the OTC again refused. After an exchange of correspondence,...
To continue reading
Request your trial-
City of Cincinnati v. Beretta U.S.A. Corp., Bryco Arms, Inc., Colt's Manufacturing Co., Inc., Fabrica D'armi Pietro Beretta, S.P.A., H. & R. 1871, Inc., Hi-Point Firearms, B.L. Jennings, Inc., Lorcin Engineering Co., Inc., North American Arms, Inc., Phoenix Arms, Smith & Wesson Corp., Sturm & Ruger Co., Inc., Taurus International Manufacturing, Inc., American Shooting Sports Coalition, Inc., National Shooting Sports Foundation, Inc., and Sporting Arms and Ammunition Manufacturers' Institute, Inc.
... ... -990814, C-990815 00-LW-3505 (1st) Court of Appeals of Ohio, First District, ... Hamilton August 11, 2000 ... F.Supp. 960, 972, citing R.J. Wildner Constructing Co., ... Inc. v. Ohio Turnpike Commn ... ...
-
Maltz v. Union Carbide Chemicals & Plastics Co.
...of policy coverage unreasonable as a matter of law where purchaser failed to read the policy); R.J. Wildner Contracting Co. v. Ohio Turnpike Comm'n, 913 F.Supp. 1031, 1040 (N.D.Ohio 1996) (motion to dismiss granted where reliance on oral representation was unreasonable as a matter of law be......
-
Eva v. Midwest National Mortgage Banc, Inc.
...over property belonging to another inconsistent with or in denial of the rights of the owner." R.J. Wildner Contracting Co., Inc. v. Ohio Turnpike Comm'n, 913 F.Supp. 1031, 1043 (N.D.Ohio 1996). Under Ohio law, the elements of a conversion of property claim are: (1) the plaintiff's ownershi......
-
Caroline County v. Dashiell
...quasi-contract) based on that transaction."), rev'd on other grounds, 156 F.3d 535 (4th Cir.1998); R.J. Wildner Contracting Co. v. Ohio Turnpike Comm'n, 913 F.Supp. 1031, 1043 (N.D.Ohio 1996) ("[I]n the absence of fraud or bad faith, Ohio law prohibits recovery under a theory of unjust enri......