Williams v. Chicago, S. F. & C. Ry. Co.

Decision Date12 December 1899
Citation54 S.W. 689,153 Mo. 487
CourtMissouri Supreme Court
PartiesWILLIAMS et al. v. CHICAGO, S. F. & C. RY. CO. et al.

11. A contract for the construction of a railroad provided that the company's engineer should classify the several kinds of material, except hardpan, to be moved and excavated, but left it to him to say whether a specific excavation was hardpan, and provided that hardpan should be classified as loose rock, and that the amounts and kinds of work performed under the contract, and the engineer's estimates of the work, in the absence of fraud, should be conclusive upon the parties. In the classification made by the engineer of the different materials as loose rock, there was no specific classification of hardpan. No objection was made at the time to the omission of hardpan from the classification. The referee and the trial court found that the engineer acted in good faith in making this classification. Held, that the classification was binding upon the parties, though the engineer applied the percentage method in arriving at the amount of loose rock in the material excavated, irrespective of the plow or force test.

12. Where a contract for the construction of a railroad provides that the company's engineer shall classify all material to be moved and excavated, and provides that all material which in the judgment of the engineer could not be removed without blasting should be classified as solid rock, his classification of sand rock as 75 per cent. solid rock and 25 per cent. loose rock was not erroneous.

13. Where the contract for the construction of a railroad leaves to the company's engineer the measurements of all work performed under the contract, his final estimates on the distance material was hauled, made in good faith, and acquiesced in at the close of the work, are conclusive.

14. Where plaintiffs in an action on a contract for the construction of a railroad fail to recover more than defendant's offer of a money judgment, but are adjudged in addition a lien on the roadbed, they are entitled to recover their costs.

Appeal from circuit court, Macon county; Andrew Ellison, Judge.

Action by Benezette Williams and others against the Chicago, Santa Fé & California Railway Company and others. From a judgment of the circuit court rejecting certain findings of the referee, plaintiffs appeal. Reversed.

This is an appeal by plaintiffs from the judgment of the circuit court of Macon county. This is the second appeal in this cause. The first is reported in 112 Mo. 463, 20 S. W. 631. The action grows out of a contract to construct the roadbed, and prepare the same for the superstructure, upon that portion of defendants' road described as sections 75 to 94, inclusive, in division No. 2, and sections 95 to 114, inclusive, in division 3, commencing about three miles west of Grand river, in Carroll county, and terminating at the east end of section 114, in Macon county. The right of lien was settled on the former appeal. After the reversal of the former judgment, the plaintiffs amended their petition at the April term, 1893, of the Macon circuit court. After setting out the contract in full, together with the specifications, plaintiffs allege that between the 7th day of February, 1887, and the 19th day of January, 1888, on which last day the last work was done and materials furnished, plaintiffs did and performed all the work and labor and furnished all the materials required of them by the terms of said contract, and also furnished materials and did extra work under the terms of said contract in section 115, in division 4, of said railway, in the counties of Chariton, Linn, and Macon, amounting in all to the sum of $679,206.68, setting out the various items in detail, and admitted payments and credits to the amount of $490,894.94. There were also allegations as to the rights and liabilities of the other defendants, and the filing and recording of the lien. Plaintiffs then proceeded to assign as breaches of this contract that defendants' engineers fraudulently and willfully misconstrued the contract, and did not classify and measure said work from time to time as required by the contract, but made only approximated or percentage estimates, calculations, and measurements, with intent to defraud plaintiffs out of their just rights and benefit the railroad company. It is then specified, under nine different specifications, wherein the measurements and estimates were fraudulent. Plaintiff's further averred that the engineers of defendants did not at the completion of the work certify, as required by the contract, the completion of the work and labor, and the furnishing of said material, although often requested, and although a reasonable time had elapsed after the completion of the work before the commencement of this suit, but fraudulently neglected to do so in order to defeat plaintiffs' right to the lien conferred by law for the balance due them. The defendants' answer consisted — First, of a general denial. Second. "Defendants, further answering, say that, during the progress of construction by plaintiffs of that part of defendants' railroad covered by their contract, they were furnished from month to month with estimates by the chief engineer of defendants and his assistants, showing the quantities and amounts of the several kinds of work done by the said plaintiffs under their said contract, and that they were fully acquainted with the basis upon which said estimates were made, and the methods by which the results therein contained and set forth were arrived at; that with such knowledge the said plaintiffs acquiesced in said estimates, and submitted to the same, and expressed their satisfaction therewith, as to all that part of the work covered by their contract comprehended in division two (2) thereof, extending from section seventy-five (75) to section nine...

To continue reading

Request your trial
109 cases
  • Johnston v. Star Bucket Pump Co.
    • United States
    • Missouri Supreme Court
    • March 29, 1918
    ...decision. The dissenting opinion so misconceives it that comment is unnecessary. In Williams v. Railway, 153 Mo. loc. cit. 511, 512, 54 S. W. 689, 697, the court considered the scope of appellate review of a finding by the trial court, made after sustaining an exception to the report of a r......
  • St. Joseph Lead Co. v. Fuhrmeister, 38872.
    • United States
    • Missouri Supreme Court
    • September 5, 1944
    ...to the title to the premises in suit. Sanitary Dist. of Chicago v. Chicago Title & Trust Co., 278 Ill. 529; Williams v. Santa Fe Ry. Co., 153 Mo. 487; Barrie v. Smith, 47 Mich. 130, 10 N.W. 168; Tower v. Compton Hill Improvement Co., 192 Mo. 379; Robinson v. Cannon, 346 Mo. 1126. (9) The ri......
  • Equitable Life Assur. Soc. v. Mercantile Com. B. & T. Co.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • July 1, 1944
    ...of a known right. State ex rel. Met. Life Ins. Co. v. Shain, 334 Mo. 385, 66 S.W.2d 871, 874; Williams v. Chicago, Santa Fe, etc., Railway Co., 153 Mo. 487, 54 S.W. 689. The pertinent fact situation is that since 1917 insured had suffered from a condition known as "heart block," from which ......
  • Utah Construction Company v. State Highway Commission
    • United States
    • Wyoming Supreme Court
    • March 13, 1933
    ... ... 135 N.W. 725; Coyle v. Co., (Okla.) 166 P. 394; ... Ferguson Co. v. St., 126 N.Y.S. 108; Myers v ... Wood, (Mo.) 158 S.W. 909; Williams v. Ry. Co., ... (Ark.) 54 S.W. 689; House v. Imp. Dist., (Ark.) ... 251 S.W. 12; Daly v. Ry. Co., 129 F. 513 (8th Cir.); ... Thompson v ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT