Wolfe Masonry, Inc. v. Stewart, 13-82-111-

Decision Date09 June 1983
Docket NumberNo. 13-82-111-,13-82-111-
Citation664 S.W.2d 102
PartiesWOLFE MASONRY, INC., d/b/a Tropical Pools, Appellant, v. James STEWART, Appellee. cv.
CourtTexas Court of Appeals

Curtis Bonner, Harlingen, for appellant.

Randall P. Crane, San Benito, for appellee.

Before NYE, C.J., and YOUNG and KENNEDY, JJ.

OPINION

KENNEDY, Justice.

This is a breach of contract/Deceptive Trade Practices Act TEX.BUS. & COMM CODE ANN. (Vernon Supp.1982-1983), (hereinafter referred to as "the Act") case. Appellant brought suit against appellee under the terms of a swimming pool construction contract for recovery of sums allegedly due and owing under said contract and unpaid, and for attorney's fees. Appellee answered and filed a counterclaim under Sec. 17.50 of the Act.

Trial was to the court which awarded judgment to appellee in the amount of $10,250 less an offset of appellant's contractual claims of $1,033.56 for a total of $9,216.44. Specifically, the trial court found that appellant had violated its express warranty against defects in material and workmanship and that appellee was damaged in the amount of $2,500. In addition to this sum, the trial court then doubled the first $1,000 and trebled the remaining $1,500, added attorneys fees of $1,250 for the total of appellee's award. The trial court also made the legal conclusion that the notice provision of Sec. 17.50A(b) of the Act, effective August 27, 1979, was applicable to the case.

On May 22, 1979, the parties entered into a contract whereby appellant was to construct a swimming pool on appellee's property for the sum of $8,050. Thereafter, several changes were made in the contract bringing the total price of the pool to $9,002.56. The contract provided for payment to be made by appellee based upon the completion of certain phases of the construction. It is undisputed that appellee paid the appellant $7,969, and that the remaining $1,033.56 was not paid.

Although there was some dispute as to exactly when appellant completed construction of the pool, it is undisputed that the appellant completed construction of the pool by July 4, 1979. Appellee disputes that the pool was ever completed and these complaints form the basis of his counterclaim. However, the evidence clearly shows that the pool was essentially complete by July 4, 1979.

The appellee testified at trial that the pool was very poorly constructed and that:

There was an insufficient number of expansion joints in the decking.

The "cool deck" was improperly applied to the decking.

The plaster was not properly finished.

The deck was improperly anchored to the pool shell.

The plumbing was improperly installed and continually leaked.

These claims were corroborated by the expert testimony of Headly Raybourn, appellee's expert witness and the only non-party witness, who testified by deposition. Mr. Raybourn also testified that the cost of repairing the aforementioned defects was at least $2,500.

In his first point of error, appellant complains that the trial court's award of treble damages was improper because the notice provisions of Sec. 17.50A(2) of the Act were not complied with by the appellee. Specifically, appellant is complaining that the Act, in July of 1979, required that one seeking to enforce the treble damage provisions of the Act had to provide the potential defendant with 30 days written notice of his claims. It is undisputed that appellant did not receive written notice of appellee's claims. Appellee argues that the 1979 amendments to the Act effective August 27, 1979 are applicable. The 1979 amendments to Sec. 17.50A provides that written notice is not required where a countersuit is filed as in this case. The threshold question, then, is which version of the Act applies to this case. If the pre-August 1979 version of the Act applies, then the trial court's award of treble damages was error. If the post-August 1979 Act applies, the Action of the trial court in assessing treble damages was proper.

Appellee's counterclaim is for breach of the express warranty contained in the contract which states that "[t]ropical pools guarantee the work performed by it against defects in material and workmanship for a period of one year from the date of the contract."

Sec. 2.725(b) TEX.BUS. & COMM.CODE ANN. (Vernon 1968) is applicable to this fact situation. This section of the Uniform Commercial Code as adopted by Texas provides that a cause of action for breach of warranty accrues when the breach is discovered. The question of whether or not the warranty in question is covered by the uniform commercial code is answered in Sec. 2.313 TEX.BUS. & COMM.CODE ANN. (Vernon 1968) wherein any express warranty which relates to goods and becomes part of the bargain is covered by the code. See W.R. Weaver Co. v. Burrough Corp., 580 S.W.2d 76 (Tex.Civ.App. El Paso 1979, writ ref'd n.r.e.). See generally 3 R. ANDERSON, ANDERSON ON THE U.C.C. SEC. 2.313 (1983); 4 R. ANDERSON, ANDERSON ON THE U.C.C. SEC. 2.725 (1971); T. QUINN, U.C.C., COMMENTARY & LAW DIGEST SEC. 2.75 & 2.313 (1978); J. WHITE & R. SUMMERS, HANDBOOK ON THE LAW UNDER THE UNIFORM COMMERCIAL CODE 11-8, 9-2 (1972) which discuss in detail the application of these code sections.

Applying these code sections to the facts of this case, it is undisputed that the last possible date on which the defective pool was installed was July 4, 1979...

To continue reading

Request your trial
4 cases
  • McAllen State Bank v. Linbeck Const. Corp.
    • United States
    • Texas Court of Appeals
    • 28 d4 Março d4 1985
    ...writ); Jim Walter Homes, Inc. v. Chapa, 614 S.W.2d 838 (Tex.Civ.App.--Corpus Christi 1981, writ ref'd. n.r.e.); See also Wolfe Masonry, Inc. v. Stewart, 664 S.W.2d 102 (Tex.App.--Corpus Christi 1983, no Under the 1975 and 1977 versions of the DTPA, § 17.50(b)(1) provided that each consumer ......
  • Hines v. Hash
    • United States
    • Texas Supreme Court
    • 9 d3 Dezembro d3 1992
    ...expressly provided that plaintiff could recover only actual damages and not additional statutory damages. See Wolfe Masonry, Inc. v. Stewart, 664 S.W.2d 102, 103-104 (Tex.App.--Corpus Christi 1983, no writ); Lubbock Mort. & Inv. Co. v. Thomas, 626 S.W.2d 611, 614 (Tex.App.--El Paso 1981, no......
  • Winkle Chevy-Olds-Pontiac, Inc. v. Condon
    • United States
    • Texas Court of Appeals
    • 30 d4 Abril d4 1992
    ...of notice. Schenck v. Ebby Halliday Real Estate, Inc., 803 S.W.2d 361, 373 (Tex.App.--Fort Worth 1990, no writ); Wolfe Masonry, Inc. v. Stewart, 664 S.W.2d 102, 103 (Tex.App.--Corpus Christi 1983, no writ).5 Texas law holds the price the injured party paid for the chattel is not determinate......
  • Schenck v. Ebby Halliday Real Estate, Inc.
    • United States
    • Texas Court of Appeals
    • 12 d3 Dezembro d3 1990
    ...which was in effect at the time the cause of action accrued is the provision which governs the sufficiency of notice. Wolfe Masonry, Inc. v. Stewart, 664 S.W.2d 102, 103 (Tex.App.--Corpus Christi 1983, no The portion of § 17.50A in effect when this cause of action accrued provided as follow......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT