Wood v. Milionis Constr.
Court | Court of Appeals of Washington |
Parties | JEFFREY WOOD and ANNA WOOD, husband and wife, Respondents, v. MILIONIS CONSTRUCTION, INC., a Washington corporation; STEPHEN MILIONIS, an individual, Respondents, CINCINNATI SPECIALTY UNDERWRITERS INSURANCE COMPANY, an insurance corporation, Appellant. |
Docket Number | No. 36286-8-III,36286-8-III |
Decision Date | 28 April 2020 |
LAWRENCE-BERREY, J. — Cincinnati Specialty Underwriters Insurance Company (Cincinnati) appeals the trial court's finding that a covenant agreement entered into between its insured and the claimants was reasonable. The basis for the trial court's determination was its belief that the insured, itself, had valued the claimants' contract damages at $1.2 million, which was near the $1.7 million settlement amount. The record does not support this. Instead, the insured valued the claimants' contract damages at less than $350,000, which includes $200,000 for what the claimants asserted they previously paid for repairs. Because of the significant discrepancy between $350,000 and $1.2 million, substantial evidence does not support the trial court's finding of reasonableness. We therefore reverse and remand for a second reasonableness hearing.
In July 2015, Jeffrey and Anna Wood hired Milionis Construction, Inc. (MCI) as their general contractor to build a new home in Newman Lake, Washington. As the general contractor, MCI had the responsibility to oversee, manage, supervise, and administer the building of the custom, single-family residence. The parties originally agreed to $1,356,000 as the contract price to complete the house.
MCI and its subcontractors started work in the summer of 2015. On November 1, 2016, work ceased, at which time the Woods claimed to have paid MCI more than $550,000.
Substandard work performed by various subcontractors left the house with multiple defects. Brian Hanson, the engineer who provided structural design plans for the house, provided the Woods with a list of defects and deviations caused by the subcontractors' work.
The Woods sued MCI and its president, Steve Milionis on November 18, 2016. They asserted claims for breach of contract, unjust enrichment, promissory estoppel,breach of contractual duties of good faith and fair dealing, negligence, negligent misrepresentation, and violation of the Consumer Protection Act, chapter 19.86 RCW. The Woods also asserted a claim against MCI's bond.1 MCI counterclaimed, seeking damages still owed under the contract.
Cincinnati had issued MCI a commercial liability insurance policy in the amount of $1 million. The broad claims asserted by the Woods invoked Cincinnati's duty to defend its insured. Cincinnati retained attorney Shane McFetridge to defend MCI.2 Cincinnati also reserved its right to deny or limit coverage.
On December 12, 2016, the trial court entered an agreed stay of proceedings in accordance with the parties' contract for building the house. The contract required the dispute to be mediated and, if mediation failed, the dispute had to be arbitrated.
The parties mediated in May 2017 and again in September 2017, but both mediations were unsuccessful. They then scheduled the third and final mediation for October 19, 2017.
MCI experts' October 17, 2017 opinion of value
On October 17, just before the October mediation, McFetridge sent a letter to Cincinnati, requesting settlement authority:
Clerk's Papers (CP) at 414-15 (underlining added). Thus, excluding attorney fees and costs, MCI's experts believed the Woods' breach of contract claims totaled $146,102.18.
Contingent settlement agreement
The parties chose a general contractor, Paul Shelton, to assist in the third mediation. Rather than acting as a passive go-between, Shelton actively worked with the parties.
McFetridge wrote a postmediation letter to Cincinnati, describing the mediation and how the parties achieved a conditional settlement:
CP 419-20 (underlining and emphasis added).
The following day, Brook Cunningham, the corporate attorney for MCI, sent a letter to Cincinnati. In it, he demanded Cincinnati to fund the settlement amount and also accused Cincinnati of repeatedly placing its interest above that of its insured. Cunningham's letter concluded:
If Cincinnati fails to fund [the] settlement amount, this insured will have no choice but to offer to stipulate to a judgment in favor of the plaintiffs in this matter in exchange for a release from individual liability and assign the bad faith insurance claim against Cincinnati to the plaintiffs.
On October 25, Cincinnati responded to Cunningham and explained its reasons for not funding the full settlement amount. Cincinnati explained that its general commercial insurance policy with MCI did not cover the Woods' claims, but instead covered only "property damage" caused by an "occurrence." CP at 300. Cincinnati elaborated:3
Cincinnati explained an additional reason that precluded coverage. As a condition to coverage, the policy required MCI to obtain written contracts from each subcontractor...
To continue reading
Request your trial