Worsley Companies v. Town of Mt. Pleasant, 25070.

Decision Date22 February 2000
Docket NumberNo. 25070.,25070.
Citation339 S.C. 51,528 S.E.2d 657
CourtSouth Carolina Supreme Court
PartiesWORSLEY COMPANIES, INC., Appellant, v. TOWN OF MOUNT PLEASANT, Commissioner of Public Works of the Town of Mt. Pleasant, South Carolina, and Angelo Hassig, Respondents.

W. Andrew Gowder, Jr., of Pratt-Thomas, Pearce, Epting & Walker, P.A., of Charleston, for appellant.

James Elliott, of Barnwell, Whaley, Patterson & Helms; and Thomas J. Wills, of Wills & Massalon, both of Charleston; and R. Allen Young, of Office of Corporate Counsel, of Mt. Pleasant, for respondent Town of Mt. Pleasant.

Michael J. Feri, of Grimball & Cabaniss, of Charleston; and David G. Jennings, of North Charleston, for respondents Commissioner of Public Works of the Town of Mt. Pleasant and Angelo Hassig.

MOORE, Justice:

Appellant brought this action alleging a temporary regulatory taking and denial of substantive due process. The circuit court granted respondents summary judgment. We affirm.

FACTS

In 1986, appellant Worsley Companies (Worsley) built a Scotchman on a tract of land (Tract B) leased from Daniel and Mildred Hall (Halls). Worsley constructed a sewer line across an adjacent tract of land (Tract A), which the Halls also owned, and connected it to Town of Mount Pleasant's (Town's) sewer system. This sewer line was never dedicated or otherwise transferred to Town or Mount Pleasant Waterworks and Sewer Commission (Commission). In 1994, Worsley was also leasing part of Tract A(A-1) owned by the Halls and began construction of a propane facility. The Halls retained the remaining portion of Tract A (Tract A-2).

In June 1994, Worsley was issued a building permit for the propane facility on Tract A-1. On August 30, 1994, Worsley applied for a water and sewer permit from Commission. Commission informed Worsley that an easement was needed for the existing sewer lines prior to the issuance of a permit. Worsley signed the easement documents and sent them to Commission. Commission responded that the easement would have to be granted by the property owners, the Halls, and not Worsley. Town refused to issue a certificate of occupancy until Worsley had water and sewer service. Worsley filed an action seeking an injunction and damages against both Town and Commission.

In January 1995, the Halls and Worsley executed an agreement which allowed Worsley access to the existing water and sewer lines which were located on Tract A-2. This agreement satisfied Commission and it granted service to Worsley. Thereafter, Town issued a certificate of occupancy. Worsley amended its complaint to dismiss the injunction cause of action but still sought damages for a temporary regulatory taking and denial of substantive due process.

ISSUE

Did the circuit court err in granting respondents summary judgment?

DISCUSSION

Worsley contends the circuit court erred in granting summary judgment because there were questions of fact surrounding the issues in this case. We disagree. Summary judgment is appropriate when it is clear there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Summer v. Carpenter, 328 S.C. 36, 492 S.E.2d 55 (1997); Rule 56(c), SCRCP. In determining whether any triable issue of fact exists, the evidence and all inferences which can be reasonably drawn therefrom must be viewed in the light most favorable to the nonmoving party. Koester v. Carolina Rental Ctr., Inc., 313 S.C. 490, 443 S.E.2d 392 (1994). If triable issues exist, those issues must go to the jury. Rothrock v. Copeland, 305 S.C. 402, 409 S.E.2d 366 (1991).

Worsley contends Commission's and Town's refusals to issue the permit and certificate of occupancy constituted a taking of its property. The circuit court held Worsley did not have any protected property interest and, furthermore, the denial of the permit because of the unmet requirement of an easement over the existing sewer lines was not a taking. We agree.

In Board of Regents v. Roth, 408 U.S. 564, 577, 92 S.Ct. 2701, 2709, 33 L.Ed.2d 548 (1972), the United States Supreme Court held that "[t]o have a property interest in a benefit, a person clearly must have more than an abstract need or desire for it.... He must, instead, have a legitimate claim of entitlement to it." A clear entitlement exists in a permit when "the discretion of the issuing agency is so narrowly circumscribed that approval of a proper application is virtually assured." Villager Pond, Inc., v. Town of Darien, 56 F.3d 375, 378 (2d Cir.1995) (citing RRI Realty Corp. v. Incorporated Village of Southampton, 870 F.2d 911, 918 (2d Cir. 1989)).

Worsley was not entitled to a water and sewer permit because it did not comply with the conditions required by Commission. Commission has a policy of requiring an easement or some other agreement when a water and sewer line is to be connected to an existing line owned by a different party. This is to prevent one party from not allowing the other party access to the line for repairs or service and maintenance. See 83 Am.Jur.2d Zoning and Planning § 713 (1992) ("Where the responsible state agency has refused to grant a building permit based on the builder's plans not meeting the required standards, there is no substantive due process "taking" violation."). Thus, the circuit court did not err in granting Town summary judgment.

The circuit court also did not err in granting summary judgment for Town. Worsley had no entitlement to the certificate of occupancy. Town's refusal to issue the certificate of occupancy to Worsley was not a regulatory taking. There was no discretion in Town's actions. Pursuant to S.C.Code Ann. § 6-10-50(h) (Supp.1998), a certificate of occupancy shall be issued only if a building is in accordance with the building permit and other applicable laws. Under Town's building regulations, a building must be connected to water and sewer service prior to the...

To continue reading

Request your trial
22 cases
  • Town of Mount Pleasant v. Chimento
    • United States
    • South Carolina Supreme Court
    • January 10, 2013
  • WILLIAMSBURG RURAL v. WILLIAMSBURG
    • United States
    • South Carolina Court of Appeals
    • December 8, 2003
    ...can be reasonably drawn therefrom must be viewed in the light most favorable to the nonmoving party." Worsley Cos. v. Town of Mount Pleasant, 339 S.C. 51, 55, 528 S.E.2d 657, 659 (2000). I. Exclusive Service Rights The circuit court found that the notices contained in Williamsburg Water's p......
  • Proctor v. Dept. of Health
    • United States
    • South Carolina Court of Appeals
    • March 20, 2006
    ...885, 887 (1994); accord Jinks v. Richland County, 355 S.C. 341, 344, 585 S.E.2d 281, 283 (2003); Worsley Cos., Inc. v. Town of Mount Pleasant, 339 S.C. 51, 57, 528 S.E.2d 657, 661 (2000); Marietta Garage, Inc. v. S.C. Dep't of Public Safety, 337 S.C. 133, 522 S.E.2d 605 (Ct.App. 1999). It i......
  • Sloan v. Sc Bd. of Physical Therapy ex'Mnrs
    • United States
    • South Carolina Supreme Court
    • September 25, 2006
    ...of a cognizable property interest rooted in state law. Sunset Cay, 357 S.C. at 430, 593 S.E.2d at 470; Worsley Companies, Inc. v. Town of Mt. Pleasant, 339 S.C. 51, 528 S.E.2d 657 (2000). A "legislative act will not be declared unconstitutional unless its repugnance to the constitution is c......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT