S&W Enterprises v. Southtrust Bank of Alabama

Decision Date06 January 2003
Docket NumberNo. 02-10090.,02-10090.
Citation315 F.3d 533
PartiesS&W ENTERPRISES, L.L.C., a Nevada Limited Liability Company, Plaintiff-Appellant, v. SOUTHTRUST BANK OF ALABAMA, NA, an Alabama Banking Corporation, Defendant-Appellee.
CourtU.S. Court of Appeals — Fifth Circuit

Lawrence S. Fischman (argued), Glast, Phillips & Murray, Dallas, TX, for Plaintiff-Appellant.

Christopher H. Rentzel (argued), Timothy J. Van Meir, Bracewell & Patterson, Dallas, TX, for Defendant-Appellee.

Appeal from the United States District Court for the Northern District of Texas.

Before HIGGINBOTHAM, DUHÉ and DeMOSS, Circuit Judges.

DUHÉ, Circuit Judge:

Appellant S&W Enterprises, L.L.C. appeals from the district court's order granting summary judgment in favor of Appellee SouthTrust Bank of Alabama, N.A., arguing that the court abused its discretion in denying Appellant leave to amend its complaint. Appellant argues also that fact issues preclude summary judgment. We affirm.

BACKGROUND

SouthTrust Bank of Alabama ("SouthTrust") sold to Daiwa Bank Limited ("Daiwa") a $10 million participation in a $24 million loan SouthTrust had issued to Medical Technology Systems, Inc. The agreement between SouthTrust and Daiwa ("Participation Agreement") prohibited Daiwa from assigning its interest without SouthTrust's consent, which consent SouthTrust agreed not to withhold unreasonably. Thereafter, Daiwa and S&W Enterprises, L.L.C. ("S&W") entered into an agreement ("Purchase Agreement") whereby S&W would acquire Daiwa's participation interest. S&W's obligation to purchase and Daiwa's obligation to sell the participation interest were contingent on SouthTrust's consent to the assignment agreement ("Assignment") that would consummate the purchase. When the parties sought SouthTrust's consent to the Assignment, S&W alleges that SouthTrust imposed unreasonable conditions before it would consent. S&W refused to meet the conditions, and SouthTrust refused to consent to the Assignment. S&W sued SouthTrust for breach of contract, alleging that it was a third party beneficiary to the Participation Agreement, and tortious interference with prospective advantage, naming the Assignment.

The district court, on SouthTrust's 12(b)(6) motion, dismissed S&W's breach of contract claims, leaving S&W to pursue only its interference with prospective advantage claim. The court's Third Amended Scheduling Order, issued March 7, 2001, set the deadline for amendment of pleadings at June 11, 2001 and the deadline for completion of discovery at October 5, 2001. Trial was scheduled for the court's February 4, 2002 docket.

On March 8, 2001, the Texas Supreme Court decided Wal-Mart Stores, Inc., v. Sturges, 52 S.W.3d 711 (Tex.2001). Sturges clarified that tortious interference with prospective advantage requires a plaintiff to show that the defendant's conduct rather than being a lawful means to obtain the advantage, was "independently tortious or wrongful." Id. at 717.

On September 25, 2001, more than three months after the deadline for amendment of pleadings and more than six months after Sturges was decided, S&W moved for leave to amend, ostensibly to conform its pleadings to the requirements of Sturges. S&W acknowledged that it was aware of the Sturges decision before the deadline for amendment of pleadings, but explained that its counsel failed to understand the impact of the case on S&W's interference with prospective advantage claim until after the deadline expired. In fact, S&W's proposed amended complaint added a new cause of action, interference with contract, involving a contract not before named in the pleadings, the Purchase Agreement between S&W and Daiwa.

Before the district court ruled on S&W's motion to amend, SouthTrust filed its motion for summary judgment on the tortious interference with prospective advantage claim asserted in the original complaint. In the same opinion and order, the district court denied S&W leave to amend and granted summary judgment to SouthTrust. Emphasizing that S&W offered no adequate explanation for its delay in seeking leave to amend, the court denied leave because S&W's motion was untimely and amendment would unduly prejudice SouthTrust, who would require more discovery, or alternatively, unnecessarily delay the trial. The court then granted summary judgment, finding that S&W failed to demonstrate a fact issue suggesting SouthTrust's unreasonableness in refusing to consent to the Assignment. S&W timely appeals.

DISCUSSION
I. DENIAL OF S&W'S MOTION FOR LEAVE TO AMEND

We review for abuse of discretion the district court's denial of leave to amend. Herrmann Holdings Ltd. v. Lucent Technologies Inc., 302 F.3d 552, 558 (5th Cir.2002).

The district court denied S&W leave to amend based on the lenient standard of Federal Rule of Civil Procedure 15(a), which provides that leave to amend "shall be freely given when justice so requires." SouthTrust argues, and S&W now concedes, that Federal Rule of Civil Procedure 16(b) governs amendment of pleadings once a scheduling order has been issued by the district court. Rule 16(b) provides that a scheduling order "shall not be modified except upon a showing of good cause and by leave of the district judge." The good cause standard requires the "party seeking relief to show that the deadlines cannot reasonably be met despite the diligence of the party needing the extension." 6A Charles Alan Wright et al., Federal Practice and Procedure § 1522.1 (2d ed. 1990).

This Court has not ruled on the applicability of Rule 16(b) to amendment of pleadings after the deadline set by a scheduling order. We owe the trial court "`broad discretion to preserve the integrity and purpose of the pretrial order,'" Geiserman v. MacDonald, 893 F.2d 787, 790 (5th Cir. 1990) (quoting Hodges v. United States, 597 F.2d 1014, 1018 (5th Cir.1979)), which, toward the end of court efficiency, is to expedite pretrial procedure. Hodges, 597 F.2d at 1018. Several circuits,1 as well as district courts within our circuit,2 have applied Rule 16(b) when leave to amend would require modification of the scheduling order. We take this opportunity to make clear that Rule 16(b) governs amendment of pleadings after a scheduling order deadline has expired. Only upon the movant's demonstration of good cause to modify the scheduling order will the more liberal standard of Rule 15(a) apply to the district court's decision to grant or deny leave.

The district court denied S&W leave to amend because its motion was untimely and because of potential prejudice to SouthTrust or, alternatively, unnecessary delay of the trial. The court premised its denial also on its conclusion that S&W offered no adequate explanation for its failure to comply with the scheduling order.3 As the district court noted, the same facts were known to S&W from the time of its original complaint to the time it moved for leave to amend. S&W could have asserted interference with contract from the beginning, but fails to explain why it did not. S&W's explanation for its delayed analysis of Sturges — inadvertence — is tantamount to no explanation at all.

In the context of allowing untimely submission of expert reports, this Court has applied a four-part test to determine whether the district court's refusal to modify its scheduling order was an abuse of discretion. We find this test appropriate as well in the context of untimely motions to amend pleadings. We consider "`(1) the explanation for the failure to [timely move for leave to amend]; (2) the importance of the [amendment]; (3) potential prejudice in allowing the [amendment]; and (4) the availability of a continuance to cure such prejudice.'" Reliance Ins. Co. v. La. Land & Exploration Co., 110 F.3d 253, 257 (5th Cir.1997) (quoting Geiserman v. MacDonald, 893 F.2d 787, 791 (5th Cir. 1990)).4

Three of the four factors weigh against S&W — the first because S&W offers effectively no explanation, and the third because, as S&W would assert a different cause of action, SouthTrust would be required to conduct additional discovery. The fourth factor weighs against S&W because, while a continuance could be granted for additional discovery, the district court found that a continuance would unnecessarily delay the trial. In view of district judges' "power to control their dockets by refusing to give ineffective litigants a second chance to develop their case," Reliance Insurance, 110 F.3d at 258, we conclude that it was within the judge's sound discretion not to grant a continuance. Taking the court's conclusions as a determination that good cause to modify the scheduling order is absent, we find no abuse of discretion in the district court's refusal to grant leave to amend.

II. SUMMARY JUDGMENT
A. Standard of review

We review a district court's grant of summary judgment de novo, applying the same standards as would the district court. Pratt v. Houston, 247 F.3d 601, 605-06 (5th Cir.2001). Summary judgment shall be rendered when the pleadings, depositions, answers to interrogatories, and admissions on file, together with affidavits, if any, show that there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Fed. R.Civ.P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). Once a movant makes a properly supported motion, the burden shifts to the nonmovant to show that summary judgment should not be granted. Id. at 321-25, 106 S.Ct. at 2551-54. The nonmovant may not rest upon allegations in the pleadings, but must set forth and support with summary judgment evidence facts showing the existence of a genuine issue for trial. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255-57, 106 S.Ct. 2505, 2513-14, 91 L.Ed.2d 202 (1986). All evidence and the reasonable inferences to be drawn therefrom must be viewed in the light most favorable to the non-movant. United States v. Diebold, Inc., 369 U.S. 654, 655, 82 S.Ct. 993, 8 L.Ed.2d 176 (...

To continue reading

Request your trial
1102 cases
  • Chao v. Westside Drywall Inc
    • United States
    • U.S. District Court — District of Oregon
    • May 13, 2010
    ...(9th Cir.2000); Johnson v. Mammoth Recreations Inc., 975 F.2d 604, 609 (9th Cir.1992); see also, S & W Enters., L.L.C. v. SouthTrust Bank of Ala., N.A., 315 F.3d 533, 535-36 (5th Cir.2003) (agreeing with the First, Second, Eighth, Ninth, and Eleventh Circuits that Rule 16(b) trumps Rule 15(......
  • George v. Duke Energy Retirement Cash Balance Plan
    • United States
    • U.S. District Court — District of South Carolina
    • June 2, 2008
    ...Rico, 357 F.3d 152, 154-55 (1st Cir.2004); Leary v. Daeschner, 349 F.3d 888, 906 (6th Cir.2003); S & W Enters., L.L.C. v. SouthTrust Bank of Ala., 315 F.3d 533, 536 (5th Cir. 2003); Parker v. Columbia Pictures Indus., 204 F.3d 326, 340 (2d Cir.2000); In re Milk Prods. Antitrust Litig., 195 ......
  • Le v. Exeter Fin. Corp.
    • United States
    • U.S. District Court — Northern District of Texas
    • March 31, 2019
    ...must first show "good cause" for failure to meet the scheduling order deadline under Rule 16(b). S & W Enters., L.L.C. v. Southwest Bank of Alabama, 315 F.3d 533, 536 (5th Cir. 2003). A scheduling order "may be modified only for good cause and with the judge's consent." Fed. R. Civ. P. 16(b......
  • Dewan ex rel. Situated v. M-I
    • United States
    • U.S. District Court — Southern District of Texas
    • February 22, 2016
    ...judge's consent." Southwestern Bell Tel. Co. v. City of El Paso, 346 F.3d 54, 546 (5th Cir. 2003); S&W Enterprises, LLC v. SouthTrust Bank of Alabama, NA, 315 F.3d 533, 536 (5th Cir. 2002). To determine whether good cause for modification exists, the Court must weigh four factors: the party......
  • Request a trial to view additional results
1 firm's commentaries
1 books & journal articles
  • A Tale of Two Waivers: Waiver of the Jury Waiver Defense Under the Federal Rules of Civil Procedure
    • United States
    • University of Nebraska - Lincoln Nebraska Law Review No. 87, 2021
    • Invalid date
    ...("A schedule may be modified only for good cause and with the judge's consent."); SandW Enter., L.L.C. v. Southtrust Bank of Ala., NA, 315 F.3d 533, 535-536 (5th Cir. 2003) ("We take this opportunity to make clear that Rule 16(b) governs amendment of pleadings after a scheduling order deadl......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT