Campanella & Cardi Const. Co. v. Com.

Decision Date15 May 1959
Citation158 N.E.2d 304,339 Mass. 231
PartiesCAMPANELLA & CARDI CONSTRUCTION CO. v. COMMONWEALTH.
CourtUnited States State Supreme Judicial Court of Massachusetts Supreme Court

Francis V. Matera, Boston (John H. F. Calver, Boston, with him), for plaintiff.

Joseph H. Elcock, Jr., Boston (Eugene G. Panarese, Chelsea, with him), for the Commonwealth.

Before WILKINS, C. J., and WILLIAMS, COUNIHAN, WHITTEMORE and CUTTER, JJ.

WHITTEMORE, Justice.

This is a petition under G.L. c. 258 for compensation alleged to be due from the Commonwealth for extra work done by the petitioner under a contract of August 11, 1953, for the construction of a section of highway at the intersection of Routes 3 and 128 in Burlington.

The judge found for the respondent and filed a 'report of material facts,' expressly stated to be a report of all the material facts upon which the judge's conclusion was based. It contained rulings of law and the decision of the judge. The petitioner claimed an exception to the report, without specification of particular rulings.

The petitioner filed and was heard on a motion for a new trial on the grounds that the finding was against the weight of the evidence and constituted a mistake of law, and claimed an exception to the denial of the motion. Three days after this motion had been denied the judge allowed the petitioner to file, and the judge denied, the request for a ruling that a 'finding for the respondent is not warranted on the law and evidence of this case.' Two evidential questions are also presented by the bill of exceptions.

Where the basis for a general finding or decision is not in dispute an exception thereto suffices to raise the question of law whether it was warranted. Leshefsky v. American Employers' Ins. Co., 293 Mass. 164, 166-167, 199 N.E. 395, 103 A.L.R. 1388. Barton v. City of Cambridge, 318 Mass. 420, 424, 61 N.E.2d 830. Employers Mut. Liab. Ins. Co. of Wisconsin v. Merrimac Mills Co., 325 Mass. 676, 678, note 2, 92 N.E.2d 256. Contrast Graustein v. Boston & Maine R. R., 317 Mass. 164, 166-168, 57 N.E.2d 570.

We assume that the belated request for a ruling was received in connection with the motion for a new trial. So received, it could have been denied on the ground that it presented a question of law which was or could have been raised at the trial. Haines Corp. v. Winthrop Square Cafe, Inc., 335 Mass. 152, 154, 138 N.E.2d 759. We think, however, that the action of the judge in allowing it to be filed, and denying it without specification of ground, shows an intent that the petitioner have the right of review of the issue stated.

We rule that the exception to the voluntary report was an exception to the general finding and decision for the respondent and that it brings here the question of the correctness of the decision on the facts which the judge found, and stated were the basis for his conclusion, and on the subsidiary rulings; and that the denial of the request for a ruling raises the issue of the sufficiency of the evidence to support the finding for the respondent. We do not intimate that, had the request been filed at the time of argument on the motion and denied without indication of basis for the denial, any question would have been presented for review. See Haines Corp. v. Winthrop Square Cafe, Inc., supra.

The statute, G.L. c. 231, § 129, gives but two grounds for filing a motion for a new trial as of right; mistake of law and newly discovered evidence. Therefore, no question is presented by the exception to the denial of the motion on the ground that the finding was aginst the weight of the evidence. Petition of Scano, 338 Mass. ----, 153 N.E.2d 642.

2. To judge the correctness of the finding for the respondent on stated facts we must accept those facts as the judge has found them. We do not for this purpose refer to the evidence summarized in the bill of exceptions.

The report finds as follows: This petitioner had a contract with the Commonwealth for the construction of about a mile of new Route 3, and the issue relates to an area in the southwest quadrant of the clover leaf where Route 3 crosses Route 128. The cross section plan applicable to the quadrant called for the removal of all material therein. The resident engineer 'having such authority as is granted by the chief engineer under the * * * specifications' staked out the quadrant in such a way as not to require the removal of the ledge, and to leave an 'island' of rock between access ramps. 1 After the excavation of the ramps the assistant chief engineer and the chief engineer ordered the rock island removed and the petitioner removed it and complied with the provisions of the contract necessary to preserve its rights. Article 58 of the contract specifications provides that '[a]ll claims of the contractor for compensation other than as provided for in the contract on account of any act of omission or commission by the * * * [Commonwealth] or its agents must be made in writing * * *.' Article 28 provides that the engineer shall decide all questions which may arise and his determination and decision shall be final and conclusive. '[T]he decision of the resident engineer to interpret the cross section as not requiring the removal of all material in the island is not an act of omission or commission as set forth in article 58. If it were, the contractor suffered some financial damages' in having to bring back its equipment and because the first blasting in the area affected the ledge so that in the final blasting 'larger lumps of material would result with some additional expense for the removal thereof.' If the petitioner is entitled to recover under article 58, 'the sum of $5,000 would be more than adequate compensation for any damages * * * suffered.' Articles 3 and 22 provide that the engineer may make alterations in the form and character of the work and that the contractor shall be paid therefor at prices based upon prices allowed on the same character of work under the specifications. The contract proposal estimated that excavation of 140,000 cubic yards of rock would be required; the bid price for rock excavation was 78 cents per cubic yard; a total of 137,000 cubic yards was actually excavated including the island; the contractor has been paid therefor at the contract price. '[T]his situation is covered by article 3 and 22 of the specifications * * *. [T]he engineer, at any time, could have ordered the removal of the island, and at a cost of 78 cents per cubic yard.' The report notes the contention of the petitioner that there was a 'change' in the contract in that because of the first blasting the material became 'unconsolidated' with an additional expense for removal. The report then concludes that the 'only additional expense I find not to exceed $5,000 as above set forth, and that should be the limit of its recovery, if the petitioner can recover at all. I find and rule that the petitioner, having already been paid for the removal of this island * * * is not entitled to any further compensation.'

We think that, on these facts, it was error to rule that the staking out of the area to leave the island unexcavated was not 'an act of omission or commission' by an agent of the Commonwealth. The report implies a finding that the resident engineer was exercising the powers of the engineer in thus interpreting the contract. It was a misconstruction of the contract which the contractor, on the facts found, was bound to accept. See Benjamin Foster Co. v. Commonwealth, 318 Mass. 190, 205-208, 61 N.E.2d 147, 166 A.L.R. 925. The right in the engineer to alter the work does not mean that an interpretation binding on the contractor can be changed with impunity after the...

To continue reading

Request your trial
2 cases
  • State Line Contractors, Inc. v. Com.
    • United States
    • United States State Supreme Judicial Court of Massachusetts Supreme Court
    • July 1, 1969
    ...authority, as they doubtless have under art. 28, for example, to order work to stop or to resume. See Campanella & Cardi Constr. Co. v. Commonwealth, 339 Mass. 231, 237, 158 N.E.2d 304. It is quite another matter, however, to say that they have authority to make an oral agreement under whic......
  • Fox v. Bottomly
    • United States
    • United States State Supreme Judicial Court of Massachusetts Supreme Court
    • February 3, 1961
    ...Leshefsky v. American Employers' Ins. Co., 293 Mass. 164, 166-167, 199 N.E. 395, 103 A.L.R. 1388; Campanella & Cardi Constr. Co. v. Commonwealth, 339 Mass. 231, 233, 158 N.E.2d 304. The bill of exceptions attempts to extend the formal action of the judge by engrafting upon it what might be ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT