Winston Bros. Company v. United States

Decision Date14 April 1972
Docket NumberNo. 288-69.,288-69.
Citation198 Ct. Cl. 37,458 F.2d 49
PartiesWINSTON BROS. COMPANY and Green Construction Company d/b/a Winston-Green v. The UNITED STATES.
CourtU.S. Claims Court

Charles E. Carlsen, Minneapolis, Minn., attorney of record for plaintiffs; Mordaunt, Walstad, Cousineau & Mc-Guire, Minneapolis, Minn., of counsel.

Michael J. Rubin, Washington, D. C., with whom was Asst. Atty. Gen. William D. Ruckelshaus for defendant.

Before COWEN, Chief Judge, LARAMORE, Senior Judge, and DAVIS, COLLINS, SKELTON, NICHOLS and KASHIWA, Judges.

ON PLAINTIFF'S MOTION AND DEFENDANT'S CROSS-MOTION FOR SUMMARY JUDGMENT

NICHOLS, Judge.

This case is before us on cross-motions for summary judgment. The plaintiff was engaged in constructing a tunnel in Arkansas for the Army Corps of Engineers. On August 20, 1964, the tunnel caved in, causing substantial delay and extra cost in the project, and destroying some of plaintiff's equipment. Following the disputes procedure of the contract, plaintiff sought a time extension and an equitable adjustment for equipment lost, and certain other expenses. The Corps of Engineers Board of Contract Appeals, (Eng. BCA Nos. 2732 and 2768, 68-2 BCA ¶ 7240) found the cave-in to be the result of the Government's non-negligent but deficient design of rock bolts intended to shore up the walls of the tunnel. The Board determined that plaintiff should have an extension of time and an equitable adjustment for a constructive change. It denied, in BCA No. 2732, plaintiff's claim for reimbursement for loss of its equipment, two drill jumbos, on the ground that the loss was covered by insurance, the cost of which was presumably covered in the bid. Plaintiff seeks review under the Wunderlich Act, 41 U.S.C. § 322 (1970), saying that, as a matter of law, such a loss of equipment is compensable under the Changes clause. In the alternative, plaintiff says that the equipment loss was a result of a breach of the Government's warranty of its specifications and thus is compensable as a breach claim brought in this court.

Defenses raised by defendant include among others the admitted fact that the loss was insured and thus that plaintiff has been fully paid for the loss. Our ruling on the so-called insurance issue makes it unnecessary to address the others. Whether the claim is based on breach of warranty or on a theory of constructive change the result is still governed by the disposition of the threshold issue of the effect of insurance coverage carried on the lost equipment. As we read the contract, plaintiff cannot recover by either route.

The policy of granting equitable adjustments under contract clauses is limited by the sense of what is or may be equitable. Thus, within the contract the parties have provided for compensation to contractors for some work not previously contemplated in the contract, made necessary by Government action or, as in this case, error. But the duty of the Government to the contractor does not extend beyond the contract and the general procurement process, for plaintiff of course does not prosecute a tort claim in this court, nor did it before the Board. In the primary portion of its claim before the Board, Eng. BCA No. 2768, plaintiff recovered for all the extra work made necessary by the cave-in. The Government's duty has been performed through the administrative relief provided. The contractor is whole, in no worse position that if the contract had been performed without a hitch. In Bruce Constr. Corp. v. United States, 324 F.2d 516, 518-519, 163 Ct.Cl. 97, 101 (1963) this court said:

But the standard of reasonable cost `must be viewed in the light of a particular contractor\'s cost * * *\' (footnote omitted), and not the universal, objective determination of what the cost would have been to other contractors at large. (Emphasis in original.)

While that case was concerned with quantum of the adjustment, the language can be applied equally as a test as to who is entitled to recover. If the contractor has incurred no cost, there is neither necessity nor rationale for an adjustment. In Bruce, supra, at 100, 324 F.2d 518, we said:

Equitable adjustments in this context are simply corrective measures utilized to keep a contractor whole when the Government modifies a contract. Since the purpose underlying such adjustments is to safeguard the contractor against increased costs engendered by the modification, it appears patent that the measure of damages cannot be the value received by the Government, but must be more closely related to and contingent upon the altered position in which the contractor finds himself by reason of the modification. * * * (Emphasis supplied.)

Plaintiff takes the position that it has not been paid by the insurance company for its loss, but merely loaned an amount equal to its loss "repayable only in the event and to the extent of any net recovery" in any legal action brought in furtherance of claims for liability for the damage covered by the loan agreement. The courts have generally found this type of insurance loan arrangement to be an acceptable business practice and have given them effect as intended. See, e. g., Luckenbach v. W. J. McCahan Sugar Refining Co., 248 U.S. 139, 39 S.Ct. 53, 63 L.Ed. 170 (1918); Dixey v. Federal Compress & Warehouse Co., 132 F.2d 275 (8th Cir., 1942).

Accepting that the proceeds accompanying this agreement were a loan and not insurance proceeds of the underlying insurance contract, plaintiff is the only party entitled to press this action in this court, but it is still an insured contractor and had a valid claim against its insurer when the disaster happened. Therefore, we must necessarily focus on the costs suffered by plaintiff, and only its necessary costs, with regard to the claim it is now pressing. Under the circumstances presented in this case, plaintiff is now financially whole and suffers no loss regardless of this court's decision. The insurance loan agreement clearly provides that plaintiff will be required to repay to its insurer only the amounts, if any, recovered in this action. If plaintiff does not recover, it need not repay the loan. Thus plaintiff is not in the position of most plaintiffs in this court who have suffered an actual loss and are seeking to be made whole.

The construction contract included a clause entitled General Condition 8 which states:

GC-8. Protection of Material and Work. The contractor shall at all times protect and preserve all materials, supplies and equipment of every description * * *

Defendant argues that the word "protect" places the risk of loss or damage upon plaintiff. Plaintiff suggests that this is a strained reading of the clause and beyond the "usual and ordinary meaning" admonition of Hotpoint Co. v. United States, 117 F.Supp. 572, 127 Ct. Cl. 402, cert. denied, 348 U.S. 820, 75 S.Ct. 32, 99 L.Ed. 647 (1954). We agree with plaintiff that this clause, in and of itself, does not place the risk of loss caused by defective Government specifications on the contractor. The clause goes on to recite that if the contractor failed to protect equipment, the Government would do so and transfer the cost of protection to the contractor. Plaintiff suggests that the loss anticipated by the clause was damage by the elements. While plaintiff's contract of insurance covering the drill jumbos is not in evidence, it is fair to assume a fairly broad coverage, including damage due to weather. Therefore, plaintiff at least partially would have been motivated to insure its equipment in part because General Condition 8 wherever encountered in Government contracts made clear that the Government did not intend to act as caretaker of the equipment.

It is possible that the insurance coverage involved here was a general policy, the cost of which was carried by plaintiff as a general cost of doing business, and was not specifically intended to apply only to this particular project or even all Government work, and was not made necessary by plaintiff's reading of this particular contractual provision. The General Condition 8 clause is therefore not, by itself, dispositive of the insurance issue, but clarifies the intention of the parties as to who was to bear the risk of loss.

It is by now a basic canon of Government contract interpretation, in which a whole body of distinct and special contract law has developed, that the Armed Services Procurement Regulations (hereinafter, ASPR) are "law which governs the award and interpretation of contracts as fully as if they were made a part thereof. * * *" Chris Berg, Inc. v. United States, 426 F.2d 314, 317, 192 Ct.Cl. 176, 182 (1970); Newport News Shipbuilding & Dry Dock Co. v. United States, 374 F.2d 516, 179 Ct.Cl. 97 (1967); 32 C.F.R. § 1.102. Even where not directly binding they provide "useful and valuable guidelines for the resolution of all Government contracts cases, * * *." Firestone Tire & Rubber Co. v. United States, 444 F.2d 547, 554, 195 Ct.Cl. 21, 35 (1971). Insofar as the regulations cited by defendant are applicable, they constitute constructive notice to contractors to the extent they are published in the Federal Register. See, 5 U.S.C. § 552; 44 U.S.C. §§ 1505, 1507 (1970); Lynsky v. United States, 126 F.Supp. 453, 456, 130 Ct.Cl. 149, 153 (1954); Coat Corp. of America v. United States, 105 F.Supp. 832, 834, 123 Ct.Cl. 176, 196 (1952).

Defendant relies heavily on the ASPR to support its proposition that insurance taken out by the contractor inures to the benefit of the Government, to reduce its contract liability. While we do not hold that this is universally so, the ASPR, taken together with the contract provisions...

To continue reading

Request your trial
19 cases
  • Winston Bros. Company v. United States
    • United States
    • U.S. District Court — District of Minnesota
    • August 28, 1973
    ...the contention of a Government "warranty" to pay for damages to equipment due to defective specifications. Winston Brothers Co. v. United States, 458 F.2d 49, 198 Ct.Cl. 37 (1972). The instant action was commenced January 15, 1973. Winston-Green's breach of contract claim must be dismissed ......
  • OMEN CONST. CO. v. Tennessee Valley Authority
    • United States
    • U.S. District Court — Middle District of Tennessee
    • December 13, 1979
    ...944 (Ct.Cl. 1977); accord, Dale Ingram, Inc. v. United States, 475 F.2d 1177, 1185, 201 Ct.Cl. 56 (1973); Winston Bros. Co. v. United States, 458 F.2d 49, 54, 198 Ct.Cl. 37 (1972). TVA's motion here, as in the proceeding before the Hearing Officer, presents for determination the single issu......
  • Victory Construction Co., Inc. v. United States, 8-73.
    • United States
    • U.S. Claims Court
    • February 19, 1975
    ...United States, 312 F.2d 418, 160 Ct.Cl. 1, cert. denied, 375 U.S. 954, 84 S.Ct. 444, 11 L.Ed.2d 314 (1963); Winston Bros. Co. v. United States, 458 F.2d 49, 198 Ct.Cl. 37 (1972). It is consequently appropriate, in the absence of exceptional circumstances not present here, to accord the lang......
  • Granite-Groves v. Washington Metropolitan Area Transit Authority, GRANITE-GROVES
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • April 22, 1988
    ... ... No. 87-7148 ... United States Court of Appeals, ... District of Columbia Circuit ... 56 (1973); Foster Constr. C.A. & William Bros. Co. v. United States, 435 F.2d 873, 878, 193 Ct.Cl. 587 ... 564 F.2d at 944; Dale Ingram, 475 F.2d at 1177; Winston Bros. Co. v. United States, 458 F.2d 49, 54, 198 Ct.Cl. 37 ... is a joint venture composed of Granite Construction Company and S.J. Groves & Sons Company. See Appellant's Brief at ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT