Technica LLC v. Carolina Cas. Ins. Co.

Decision Date29 April 2014
Docket NumberNo. 12–56539.,12–56539.
Citation749 F.3d 1149
PartiesTECHNICA LLC, for the use and benefit of UNITED STATES of America, Plaintiff–Appellant, v. CAROLINA CASUALTY INSURANCE COMPANY; Candelaria Corporation; Otay Group, Inc.; Does 1 Through 10, Inclusive, Defendants–Appellees.
CourtU.S. Court of Appeals — Ninth Circuit

OPINION TEXT STARTS HERE

Limited on Preemption Grounds

West's Ann.Cal.Bus. & Prof.Code § 7031(a)J. Scott Scheper (argued), Jack R. Leer; Seltzer Caplan McMahon Vitek, San Diego, CA, for PlaintiffAppellant Technica, LLC.

Robert J. Berens (argued), Adam D. Melton; Lewis Brisbois Bisgaard & Smith, LLP, Phoenix, AR, for Defendants-Appellees Carolina Casualty Insurance Company, Candelaria Corporation and Otay Group, Inc.

Appeal from the United States District Court for the Southern District of California, Marilyn L. Huff, District Judge, Presiding. D.C. No. 3:08–cv–01673–H–KSC.

Before: RICHARD A. PAEZ and ANDREW D. HURWITZ, Circuit Judges, and RALPH R. ERICKSON, Chief District Judge.*

OPINION

PAEZ, Circuit Judge:

In this Miller Act case, Technica, Inc. (Technica), a subcontractor on a federal construction project in California, appeals the grant of summary judgment to Candelaria Corporation (Candelaria), the prime contractor, and its surety Carolina Casualty Insurance Company (CCIC). See40 U.S.C. §§ 3131–3134. At issue is whether the district court erred in concluding that because Technica was not a licensed California contractor as required by California law, it is precluded from pursuing its Miller Act claim for payments due under the subcontract. Reviewing the grant of summary judgment de novo, we conclude that the absence of California licensure does not bar this suit, and therefore reverse. See McDonald v. Sun Oil Co., 548 F.3d 774, 778 (9th Cir.2008).

I.

This dispute stems from work performed in California on the ICE El Centro SPC—Perimeter Fence Replacement/Internal Devising Fence Replacement federal project (“Project”). Candelaria, the prime government contractor on the Project, provided a payment bond as required by the terms of the government contract and the Miller Act, and enlisted CCIC as its surety. In December 2007, Candelaria entered into a subcontract with Otay Group, Inc. (Otay) to perform a portion of the work required under the prime contract. Shortly thereafter, Otay contracted with Technica to act as a sub-subcontractor on the Project.

Between late 2007 and June 2008, Technica provided $893,697.77 worth of labor, material and services to the Project. Technica submitted invoices to Otay and Candelaria for this work, but received only partial payments totaling $287,861.81. In June 2008, Candelaria terminated Otay's subcontract. In September 2008, Technica filed a complaint in district court invoking its rights under the Miller Act to recover outstanding amounts owed on the subcontract against the payment bond.

Candelaria and CCIC filed a motion for summary judgment, arguing that California's contractor licensing statute, California Business and Professions Code § 7031(a),1 provided a complete defense to Technica's Miller Act claim. Section 7031(a) precludes any contractor from maintaining an action for collection of compensation for services if the contractor was not a licensed contractor during the performance of the contract. Candelaria and CCIC asserted that because Technica did not hold a California contractor's license and did not fit within the “labor provider” exception to the licensing requirement it could not maintain its Miller Act claim.2See Cal. Labor Pool, Inc. v. Westway Contractors, Inc., 53 Cal.App.4th 152, 61 Cal.Rptr.2d 715 (1997). The district court, finding there was no dispute that Technica lacked a California contractor's license, concluded that California's contractor licensing law applied and that, because the labor provider exception did not apply, Technica could not pursue its Miller Act claim.

This appeal timely followed.3

II.

The Miller Act is the modern-day remedy to the historical dilemma faced by contractors and materialmen denied compensation in federal construction projects. The common law doctrine of sovereign immunity prevented liens against property of the federal government, and federal statutes only allowed those in privity of contract with the government to sue to enforce contractual rights. See28 U.S.C. § 1491; United States v. Munsey Trust Co., 332 U.S. 234, 241, 108 Ct.Cl. 765, 67 S.Ct. 1599, 91 L.Ed. 2022 (1947). Recognizing that other parties who contribute to the performance of a federal construction contract, including subcontractors, should in some way be assured payment of their claims, Congress enacted the Heard Act in 1894. See Act of August 13, 1894, ch. 280, 28 Stat. 278, amended by Pub.L. No. 58–100, ch. 778, 33 Stat. 811, and Pub.L. No. 61–476, ch. 238, 36 Stat. 1167. In 1935, the Heard Act was repealed and the Miller Act enacted in its place. See Pub.L. No. 74–321, ch. 642, 49 Stat. 793 (codified as amended at 40 U.S.C. §§ 3131–3134).

The Miller Act requires a general contractor on a federal construction project to furnish a payment bond “for the protection of all persons supplying labor and material in carrying out the work provided for in the contract.” 40 U.S.C. § 3133(b)(2). It “represents a congressional effort to protect persons supplying labor and material for the construction of federal public buildings in lieu of the protections they might receive under state statutes with respect to the construction of nonfederal buildings.” Mai Steel Serv. Inc. v. Blake Constr. Co., 981 F.2d 414, 416–17 (9th Cir.1992) (quoting United States ex rel. Sherman v. Carter, 353 U.S. 210, 216, 77 S.Ct. 793, 1 L.Ed.2d 776 (1957)) (internal quotation marks omitted). Under the Miller Act, any person who has furnished labor or material in carrying out work on a federal construction project and

[who] has not been paid in full within 90 days after the day on which the person did perform the last of labor ... may bring a civil action on the payment bond for the amount unpaid at the time the civil action is brought and may prosecute the action to final execution and judgment for the amount due.

40 U.S.C. § 3133(b)(1). The Miller Act explicitly extends to sub-subcontractors, like Technica, the right to file and prosecute an action against a prime contractor's payment bond. See§ 3133(b)(2) (“A person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond may bring a civil action on the payment bond....”). Because, the Miller Act provides Technica a federal cause of action, “the scope of the remedy as well as the substance of the rights created thereby is a matter of federal not state law.” F.D. Rich Co., Inc., v. United States ex rel. Indus. Lumber Co., 417 U.S. 116, 127, 94 S.Ct. 2157, 40 L.Ed.2d 703 (1974). The Miller Act is highly remedial in nature, and “is entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects.” Sherman, 353 U.S. at 216, 77 S.Ct. 793 (quoting Clifford F. MacEvoy Co. v. Calvin Tomkins Co., 322 U.S. 102, 107, 64 S.Ct. 890, 88 L.Ed. 1163 (1944)) (internal quotation marks omitted).

III.

The question before us is whether California's contractor's licensing law restricts “the substance of the rights” afforded to Technica under the Miller Act. Although this is a matter of first impression for our circuit, the Supreme Court, and the Eighth and Tenth Circuits, have held that rights and remedies under the Miller Act may not be conditioned by state law. We conclude that their reasoning applies with equal force to this case.4

In F.D. Rich, the Supreme Court relied upon the federal interest in the uniform application of law in determining that state laws cannot be used to provide an award of attorneys' fees to a Miller Act claimant where such a right is not provided by federal law. 417 U.S. at 127–28, 94 S.Ct. 2157. Reversing a ruling of this circuit, the Supreme Court held that, where there was no evidence of congressional intent to incorporate state law, the application of uniform federal law better served [t]he reasonable expectations of [ ] potential litigants” under the Miller Act. Id. at 127, 94 S.Ct. 2157. In particular, the Court noted [m]any federal contracts involve construction in more than one State, and often, as here, the parties to Miller Act litigation have little or no contact, other than the contract itself, with the State in which the federal project is located.” Id.

Following F.D. Rich, the Tenth Circuit concluded that state statutes cannot condition the rights available to a subcontractor under the Miller Act because state laws “do not condition or otherwise proscribe in any manner the right of the United States to institute and maintain in the United States Court for the use and benefit of a subcontractor an action against the prime contractor....” Hoeppner Constr. Co. v. United States ex rel. E.L. Mangum, 287 F.2d 108, 110 (10th Cir.1960). In Hoeppner, the Tenth Circuit considered a proffered defense to a Miller Act claim based on Colorado's requirement that a partnership record an affidavit with a county recorder's office identifying the names of the individual partners. Id. State law further provided that where the partnership failed to file such an affidavit, it could not maintain an action to collect debts. Id. Invoking this procedural requirement, the surety argued that the United States could not maintain an action under the Miller Act on behalf of a subcontractor who had failed to file the affidavit. Id. The court rejected this defense, holding that the right to maintain an action under the Miller Act “does not have its source in the law of Colorado.” Id. Accordingly, the state law filing requirements could not be used to limit subcontractor rights under...

To continue reading

Request your trial
10 cases
  • United States ex rel. Chasney & Co. v. Hartford Accident & Indem. Co.
    • United States
    • U.S. District Court — District of Maryland
    • March 3, 2016
    ...faced by contractors and materialmen denied compensation in federal construction projects.” Technica LLC ex rel. United States v. Carolina Cas. Ins. Co. , 749 F.3d 1149, 1151 (9th Cir.2014). Because the subcontractor's ordinary fail-safe—the mechanic's lien—is inapposite when the subject pr......
  • Paige Int'l, Inc. v. XL Specialty Ins. Co.
    • United States
    • U.S. District Court — District of Columbia
    • July 28, 2017
    ...laborersand suppliers. Sherman, 353 U.S. at 216, 77 S.Ct. 793 ; see 40 U.S.C. § 3131(b)(1) ; Technica LLC ex rel. United States v. Carolina Cas. Ins. Co., 749 F.3d 1149, 1153 (9th Cir. 2014) (distinguishing "rights established by the Miller Act" from "application of the substantive law of c......
  • U.S. for the United Statese & Benefit of Galvin Bros., Inc. v. Fid. & Deposit Co. of Md.
    • United States
    • U.S. District Court — Eastern District of New York
    • September 30, 2015
    ...as the substance of the rights created thereby is a matter of federal not state law."); See also Technica LLC ex rel. U.S. v. Carolina Cas. Ins. Co., 749 F.3d 1149, 1152 (9th Cir. 2014). Galvin's public policy argument therefore must be rejected.IV. Dismissal or Transfer Since this Court ha......
  • Frontier Contracting Inc. v. Allen Eng'g Contractor, Inc.
    • United States
    • U.S. District Court — Eastern District of California
    • September 25, 2014
    ...they might receive under state statutes with respect to the construction of nonfederal buildings." Technica LLC ex rel. U.S. v. Carolina Cas. Ins. Co. 749 F.3d 1149, 1152 (9th Cir. 2014) (citations omitted). A cause of action under the Miller Act accrues "90 days after the day on which the ......
  • Request a trial to view additional results
1 firm's commentaries

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT