Aetna Casualty & Surety Company v. United States

Decision Date14 September 1967
Docket NumberNo. 23997.,23997.
CourtU.S. Court of Appeals — Fifth Circuit
PartiesAETNA CASUALTY & SURETY COMPANY, Appellant, v. UNITED STATES of America for the Use and Benefit of GIBSON STEEL COMPANY, Inc., Appellee.

Howard P. Ross, Anthony S. Battaglia, St. Petersburg, Fla., Arnold M. Schwartz, Los Angeles, Cal., Parker & Battaglia, St. Petersburg, Fla., for appellant.

Irving H. Levy, Birmingham, Ala., for appellee.

Before WISDOM and GODBOLD, Circuit Judges, and McRAE, District Judge.

WISDOM, Circuit Judge:

This case presents the narrow question whether one who furnishes custom-built items to a Miller Act1 prime contractor is a subcontractor or a materialman within the meaning of the act. On the facts of this case, we hold that the key party, Rogers Fabricating Co., was a materialman. Accordingly we reverse.

Aetna Casualty and Surety Co. is the surety for the prime contractor, Paul Hardeman, Inc.-Morrison-Knudsen Company, Inc., which built the Manned Space Center Building at Merritt Island, Florida. The prime contractor entered into a purchase order contract with Rogers. This contract called for Rogers to furnish all the miscellaneous steel and iron products for the project, in accordance with the specifications set forth in the prime government contract. Rogers bought a few items already fabricated and delivered them directly to the prime contractor. It performed the remainder of the contract by custom fabricating items purchased from suppliers. This litigation arose when Rogers failed to pay its suppliers, and one of them, Gibson Steel Company, Inc., sued Aetna on the prime contractor's Miller Act payment bond.

The Miller Act payment bond protects not only those persons who deal directly with the prime contractor, but also certain classes of persons who have an indirect relationship with him. The statute provides, in pertinent part:

Any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond * * *. 40 U.S.C. § 270b(a). (Emphasis added.)

The Supreme Court has interpreted this language to mean that a supplier may recover against the prime contractor's surety only when the supplier's customer was a subcontractor in a technical sense and not simply a materialman. MacEvoy v. United States, 1944, 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163. The supplier's right to recover in this case, then, turns on whether Rogers was a subcontractor or a materialman. The parties have so stipulated.

The Court in MacEvoy cast some light on the meaning of "subcontractor" for purposes of the Miller Act. The Court said:

In a broad, generic sense a subcontractor includes anyone who has a contract to furnish labor or material to the prime contractor. * * * But under the more technical meaning, as established by usage in the building trades, a subcontractor is one who performs for and takes from the prime contractor a specific part of the labor or material requirements of the original contract, thus excluding ordinary laborers and materialmen. 322 U.S. at 108-109, 64 S.Ct. at 894.

The Court turned to the "practical considerations underlying the Act" to distinguish between "subcontractors" and "ordinary laborers and materialmen". The controlling consideration, it found, was the relatively small number of "subcontractors" and the relative ease with which the prime contractor could police their financial responsibility. The Court said:

The relatively few subcontractors who perform part of the original contract represent in a sense the prime contractor and are well known to him. It is easy for the prime contractor to secure himself against loss by requiring the subcontractors to give security by bond, or otherwise, for the payment of those who contract directly with the subcontractors. * * * But this method of protection is generally inadequate to cope with remote and undeterminable liabilities incurred by an ordinary materialman, who may be a manufacturer, a wholesaler or a retailer. 322 U.S. at 110, 64 S.Ct. at 895.

As we read MacEvoy, in a borderline case2 the distinction between a "subcontractor" and a "materialman" turns on the substantiality and importance of the relationship between the middle party and the prime contractor. If a middle party has taken responsibility for a large and definable part of the construction project, he is a "subcontractor"; otherwise he is a "materialman".

Most of the pertinent decisions of the lower federal courts support our reading of MacEvoy. Thus in United States v. Lembke Constr. Co., 10 Cir. 1966, 370 F.2d 293, the court refused to classify a middle party as a subcontractor even though he had undertaken to provide all the concrete for the project and to meet the specifications of the prime contract. The court disregarded the middle party's undertaking to furnish the total concrete requirements for the job, and held that nonetheless the prime contractor had not sufficiently "delegated * * * a specific part of the labor or material requirements of the prime contract". Id. at 295. See also Brown & Root, Inc. v. Gifford-Hill & Co., 5 Cir. 1963, 319 F.2d 65; United States v. Wright Contracting Co., D.Md.1961, 194 F.Supp. 444.

Courts have found, however, that a delegation of responsibility may be sufficient to render a middle party a "sub-contractor" when the middle party fabricated a complex installation, of relatively great importance in relation to the entire project. This classification held true even though the middle party did not install his product or do any on-site work. In United States v. MSI Corp., 2 Cir. 1965, 350 F.2d 285, for example, the middle party's contract was to furnish "a...

To continue reading

Request your trial
29 cases
  • U.S.A For The Use And Benefit Of Wfi Ga. Inc v. The Gray Ins. Co.
    • United States
    • U.S. District Court — Northern District of Georgia
    • March 24, 2010
    ...if it “undertakes to do all the plumbing, or heating, or electrical work” on a project. Aetna Cas. & Sur. Co. v. United States ex rel. Gibson Steel Co., 382 F.2d 615, 617 n. 2 (5th Cir.1967). The Miller Act also does not define what it means to “furnish” labor or materials. The Supreme Cour......
  • Unadilla Silo Co., Inc. v. Hess Bros., Inc.
    • United States
    • New Jersey Supreme Court
    • February 28, 1991
    ...work as one factor in determining whether a supplier of materials is a subcontractor. See Aetna Casualty & Surety Co. v. United States ex rel. Gibson Steel Co., 382 F.2d 615, 618 (5th Cir.1967); Farwest Steel Corp. v. Mainline Metal Works, 48 Wash.App. 719, 726, 741 P.2d 58, 62 (1987). Amon......
  • Liberty Mut. Ins. Co. v. Friedman
    • United States
    • U.S. District Court — District of Maryland
    • December 28, 1979
    ...relationship" between them, including other contracts and the interrelation of management. In Aetna Casualty & Surety Co. v. United States ex rel. Gibson Steel Co., 382 F.2d 615 (5th Cir. 1967), the Fifth Circuit held that a company which furnished custom-built items to a prime government c......
  • Rich Co Inc v. United States Industrial Lumber Company, Inc 8212 1382
    • United States
    • U.S. Supreme Court
    • May 28, 1974
    ...1156, 10 L.Ed.2d 278 (1963); Rule 23.1(c) of the Rules of this Court. 7 See, e.g., Aetna Casualty & Surety Co. v. United States for Use and Benefit of Gibson Steel Co., 382 F.2d 615, 617 (CA5 1967); Basich Bros. Construction Co. v. United States for Use of Turner, 159 F.2d 182 (CA9 1946); c......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT