SJ Groves & Sons Co. v. Warren

Decision Date19 April 1943
Docket NumberNo. 8405.,8405.
Citation135 F.2d 264
PartiesS. J. GROVES & SONS CO. v. WARREN, Comptroller General.
CourtU.S. Court of Appeals — District of Columbia Circuit

Mr. O. R. McGuire, of Washington, D. C., with whom Mr. O. R. McGuire, Jr., of Washington, D. C., was on the brief, for appellant.

Mr. Bernard J. Long, Assistant United States Attorney, of Washington, D.C., with whom Messrs. Edward M. Curran, United States Attorney, and Charles B. Murray and John P. Burke, Assistant United States Attorneys, all of Washington, D. C., were on the brief, for appellee.

Before GRONER, Chief Justice, and MILLER and VINSON, Associate Justices.

Writ of Certiorari Denied June 7, 1943. See ___ U.S. ___, 63 S.Ct. 1327, 87 L.Ed. ___.

GRONER, C. J.

On October 5, 1936, appellant contracted with the United States to construct the Grassy Lake Dam on the Upper Snake River, in the State of Idaho. The contract was on a standard Government form. The work was completed October 14, 1939. In good time thereafter appellant made claim for a modification of the contract to allow for increased compensation on the ground that in the course of the work it had encountered unknown conditions which substantially increased its costs. The claim was allowed by the Secretary of the Interior to the extent of $23,615.70, and an approved voucher, together with a copy of his decision, was sent to the Comptroller General for certification for payment. The latter, after prolonged correspondence with the Secretary, refused to certify the voucher for payment and issued a settlement certificate to the effect that there was no balance due from the United States. This suit was then commenced in the District Court for a mandatory injunction restraining the Comptroller General from interfering with the payment of the claim, and for an order requiring him to set aside his settlement and to certify for payment the amount ascertained by the Secretary to be due. The District Court refused the relief asked and entered summary judgment for appellee. The case then came here on appeal.

The claim arose under these circumstances. In the construction of the dam large quantities of earthfill were necessary. The Government geologists had made a geological survey of the area, had dug test pits to ascertain whether the land in the vicinity of the dam would yield the necessary quantities, had concluded that it would, and had located borrow pits accordingly. Relying upon these explorations and the conclusion therefrom, which was approved by the Government engineer, appellant made its bid. However, in the progress of the work appellant encountered rhyolite at a depth of approximately twelve feet in the territory from which the fill was expected to be obtained. This substance was examined by the Government and rejected as unsuitable. Consequently, it became necessary for appellant to locate new pits further removed from the site of the dam, thereby incurring greater expense.

The decision of the Secretary to modify the contract to allow for this expense was based on Article 41 of the contract, which in substance provides that where "unknown conditions of an unusual nature differing materially from those ordinarily encountered" are found to exist, the contracting officer, with the approval of the Secretary, shall increase or decrease the contract payment accordingly.

The Secretary made the appropriate findings, deciding specifically that as a result of additional work created by "unknown conditions of an unusual nature" not contemplated by the contract, appellant was entitled to compensation as follows:

                  (1) Clearing and grubbing of
                        areas not originally designated
                        as borrow pits,                   $ 5,881.00
                  (2) Providing drainage for borrow
                        pits,                               2,731.05
                  (3) Constructing haul roads to
                        additional borrow pits,             3,435.65
                  (4) Extra costs due to general
                        borrow pit conditions,             11,568.00
                                                          __________
                                                          $23,615.70
                

The Comptroller General, in refusing to authorize payment of these additional amounts, pointed out that paragraph 47 of the specifications expressly authorized the location of additional borrow pits by the contracting officer whenever necessary to obtain material for the embankment, and did not provide for additional payment for the work performed in such operations. He took the view that this paragraph took precedence over Article 4 of the contract, relating to changed conditions generally. With respect to the allowance for clearing and grubbing and for constructing haul roads to additional pits, he took the position that paragraphs 37 and 33 of the specifications, respectively, specifically forbid additional compensation for this work. He objected to the items representing the cost of providing drainage and the cost alleged to have been due to general moisture conditions in the borrow pits on the ground that there was nothing in the Secretary's findings to show that these expenses were due to changed conditions within the meaning of Article 4 of the contract. In short, he concluded that Article 4 had no application and that the decision of the Secretary was a misconstruction of the contract and therefore an erroneous conclusion of law. These considerations led him to decline to authorize payment.

In this Court and in the Court below appellant relies upon Article 15 of the contract, which provides as follows: "Art. 15. Disputes. — * * * Except as otherwise specifically provided in this contract, all other disputes concerning questions arising under this contract shall be decided by the contracting officer, subject to written appeal by the contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto." Appellant contends that by virtue of this Article appellee has no discretion to exercise with respect to its claim, but must authorize its payment.

We think the following two principles are readily deducible from the authorities:

1. While courts as a general rule have no power of review of the action of the Comptroller General, Doehler Metal Furn. Co. v. Warren, 76 U.S.App.D.C. 60, 129 F.2d 43, they may, by means of mandamus or mandatory injunction, compel the performance of a ministerial duty to pay money. McCarl v. Cox, 56 App.D.C. 27, 8 F.2d 669; Dane v. United States, 57 App. D.C. 161, 18 F.2d 811; Baker v. McCarl, 58 App.D.C. 69, 24 F.2d 897; McCarl v. United States, 58 App.D.C. 319, 30 F.2d 561; McCarl v. Wylly, 1 Cir., 5 F.2d 964.

2. Where parties to a building and construction contract, including the United States, designate a person to determine disputes arising under the contract and stipulate that the determination shall be final and conclusive, they are bound by such determination in the absence of fraud or such gross mistake as to imply bad faith. Kihlberg v. United States, 97 U.S. 398, 24 L.Ed. 1106; United States v. Gleason, 175 U.S. 588, 20 S.Ct. 228, 44...

To continue reading

Request your trial
7 cases
  • Ward v. Cardillo
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • April 19, 1943
  • Levy v. Arsenault
    • United States
    • D.C. Court of Appeals
    • January 31, 1949
    ...of action until final hearing on the merits. Cf. Brunswick v. Elliott, 70 App.D.C. 45, 103 F.2d 746; S. J. Groves & Sons Co. v. Warren, 77 U.S.App.D.C. 347, 135 F.2d 264, certiorari denied, 319 U.S. 766, 63 S.Ct. 1327, 87 L.Ed. 1716; Leonardo v. Leonardo, 79 U.S.App.D.C. 258, 145 F.2d 849. ......
  • Stiers Bros. Const. Co. v. Broderick
    • United States
    • U.S. District Court — District of Kansas
    • April 7, 1945
    ...arbiter's determinations as to questions of fact, they are not competent in this respect as to questions of law, S. J. Groves Sons' v. Warren, 77 U.S.App.D.C. 347, 135 F.2d 264; certiorari denied 319 U.S. 766, 63 S.Ct. 1327, 87 L.Ed. 1716, and the Court, therefore, may examine into question......
  • Universal-Cyclops Steel Corp., B-142344
    • United States
    • Comptroller General of the United States
    • April 19, 1960
    ... ... but are questions of Law. See S. J. Groves and sons company ... v. Warren, 135 F.2d 264, certiorari denied, 319 U.S. 766; ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT