Agnew v. Lacey Co-Ply

Decision Date29 November 1982
Docket NumberCO-PLY,No. 9277-4-I,9277-4-I
Citation654 P.2d 712,33 Wn.App. 283
PartiesS.J. AGNEW, d/b/a Agnew Environmental Products, Appellant, v. LACEY, a cooperative association, Respondent.
CourtWashington Court of Appeals

John M. Woodley, Bellevue, for appellant.

Dale R. Martin, Seattle, for respondent.

DURHAM, Acting Chief Judge.

S.J. Agnew, d/b/a Agnew Environmental Products, appeals from an order of the superior court confirming an arbitration award and denying Agnew's motions to partially vacate or to modify the award with regard to attorney's fees. The underlying contract in the dispute provided that the prevailing party in arbitration "shall be entitled" to reasonable attorney's fees. Although Agnew was successful in the arbitration, the arbitrators did not award attorney's fees.

The dispute arose over an industrial wood waste fired furnace which Agnew agreed to sell to respondent Lacey Co-Ply, a cooperative association which manufactures plywood veneer. The parties entered into a sales contract and purchase agreement which detailed the sale terms, including delivery, installation and payment for the $560,000 furnace. The sales contract, which was signed on March 31, 1976, included an arbitration clause which provided, in part, that

[a]ll claims, disputes and other matters in question arising out of or relating to this agreement or breach thereof shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association...

The agreement also contained this provision for attorney's fees:

In the event that either party institutes legal action against the other party on account of any breach of this agreement ... then the prevailing party in such action shall be entitled to reasonable attorney's fees from the non-prevailing party.

Lacey began operating the Agnew furnace in 1977. In April 1978, the furnace broke down and required substantial repairs. Differences arose between the parties as to the performance of each under the contract and responsibilities for repairs. In a letter to Agnew dated June 15, 1978, Lacey's attorney Richard A. Clark discussed Lacey's claims and divided them into the "First Group of Claims" and the "Second Group of Claims." Thereafter, the parties amended the original sales contract. In the amendment they agreed on certain disputed issues, such as payment by Lacey of the remaining balance, and repair of the furnace by Agnew. Lacey agreed to limit its claims against Agnew to the "First Group of Claims" and waived the "Second Group of Claims." Lacey's claims were to be submitted to arbitration pursuant to the original contract. The parties also amended the attorney's fees clause to read as follows:

In the event either party institutes legal action or undertakes arbitration proceedings against the other party on account of any br[e]ach of this agreement ... then the prevailing party in the litigation or arbitration proceedings shall be entitled to reasonable attorney's fees from the non-prevailing party.

(Italics ours.) The original contract was ratified except as specifically modified in the amendment. The amendment to the sales contract and purchase agreement was signed by the parties on July 14, 1978.

Dissatisfaction with the furnace continued. On February 21, 1979, Lacey filed a demand for arbitration. In addition to submission of the "First Group of Claims," Lacey sought rejection of the furnace, repayment of the purchase price and additional damages. On October 5, 1979, Agnew filed a complaint for declaratory judgment in King County Superior Court, asking that the court limit the scope of the arbitration to the "First Group of Claims." The court issued its order on November 5, 1979. Judge Horton Smith stayed the court action pending arbitration and declined to limit the scope of the issues submitted to the arbitrators. The court also ordered the arbitrators to award attorney's fees as provided for in the contract. Agnew appealed the order to this court. Viewing Judge Smith's order as not a final appealable order, the court denied review. The Supreme Court also denied review.

The case went to arbitration and Lacey sought approximately $1.6 million in damages. On May 14, 1980, the arbitrators denied all of Lacey's claims. They also ordered, in paragraph 4 of the award, that "[e]ach party shall bear their own attorneys fees and costs." Agnew moved the court to confirm the award except for attorney's fees. Judge William Goodloe continued the hearing on the motion to confirm and remanded the case to the arbitrators for reconsideration of their paragraph 4. The arbitrators declined to reconsider. Agnew filed a motion to modify or correct the award to include attorney's fees, or to partially vacate the award and set attorney's fees. On August 14, 1980, Judge Scholfield denied Agnew's motions and confirmed the arbitration award in its entirety. Agnew appeals from that order.

We will first examine the court's power to vacate or modify an arbitration award. In Washington, arbitration is a creature of statute, governed by what has been termed a "code of arbitration", RCW 7.04. Northern State Constr. Co. v. Banchero, 63 Wash.2d 245, 249, 386 P.2d 625 (1963). The code sets forth grounds for vacation or modification of an arbitration award. RCW 7.04.160, .170. Specifically, RCW 7.04.160 provides in part:

In any of the following cases the court shall after notice and hearing make an order vacating the award, upon the application of any party to the arbitration:

* * *

(4) Where the arbitrators exceeded their powers, or so imperfectly executed them that a final and definite award upon the subject matter submitted was not made.

Lacey contends that the arbitrators are the judges of both the law and the facts, and the court cannot vacate or modify the award unless the award shows on its face the adoption of an erroneous rule or mistake in applying the law. Northern State Constr. Co. v. Banchero, supra; Moen v. State, 13 Wash.App. 142, 533 P.2d 862 (1975). According to Lacey, the arbitrators heard argument on the issue and decided not to grant attorney's fees. The court, therefore, is without authority to disturb the award. 1 Agnew argues that the court had the power to vacate or modify the award by virtue of the attorney's fees clause in the contract and by the court's authority to vacate the award because the arbitrators "exceeded their powers". RCW 7.04.160(4). A consideration of the contract leads us to the conclusion that Agnew is correct.

The authority of the arbitration tribunal derives from the contract of the parties. Balfour, Guthrie & Co. v. Commercial Metals Co., 93 Wash.2d 199, 607 P.2d 856 (1980); Tombs v. Northwest Airlines, Inc., 83 Wash.2d 157, 516 P.2d 1028 (1973); RCW 7.04.010. Lacey admits that the arbitrators could do no more than that authorized by the contract. However, it is Lacey's position that the agreement empowered the tribunal to award attorney's fees, but did not compel it to do so.

The language of the sales agreement and its amendment does not support Lacey's argument. The attorney's fees clause stated that if either party undertook arbitration, "then the prevailing party ... shall be entitled to reasonable attorney's fees." We do not believe that this language, agreed to by both parties prior to arbitration, gave the arbitrators discretion with regard to an award of attorney's fees, except for the amount of the award. Indeed, because the parties agreed on the matter prior to arbitration, there was nothing left for the arbitrators to decide except the amount. The question of whether or not attorney's fees should be awarded to the prevailing party was not an issue submitted to the tribunal for arbitration with the other claims and disputes; having already been decided by the parties by agreement, it was not arbitrable. To hold otherwise would require us to ignore the express language of a contract, something that courts may not do. Wagner v. Wagner, 95 Wash.2d 94, 621 P.2d 1279 (1980). A court may not create a contract for the parties which they did not make themselves. It may neither impose obligations which never before existed, nor expunge lawful provisions agreed to and negotiated by the parties. Wagner v. Wagner, supra; Farmers Ins. Co. v. Miller, 87 Wash.2d 70, 549 P.2d 9 (1976).

If a dispute is not arbitrable, the arbitrators have no power to resolve it. Teufel Constr. Co. v. American Arbitration Ass'n, 3 Wash.App. 24, 472 P.2d 572 (1970). The arbitrators awarded neither party attorney's fees in paragraph 4 of the award. Thus they considered and decided a non-arbitrable issue, and thereby exceeded their powers.

Support for our conclusion is found in the language of the attorney's fees clause itself: "In the event either party ... undertakes arbitration proceedings ... then the prevailing party ... shall be entitled to reasonable attorney's fees." The phrase "shall be entitled" has been given mandatory meaning when used in attorney's fees clauses contained in contracts. Artz v. O'Bannon, 17 Wash.App. 421, 562 P.2d 674 (1977); Dalton v. McLaughlin, 130 Ariz. 270, 635 P.2d 863 (Ct.A...

To continue reading

Request your trial
31 cases
  • Comprehensive Orthopaedics v. Axtmayer
    • United States
    • Connecticut Supreme Court
    • 20 Octubre 2009
    ...of Appeals. See footnote 6 of the dissent. The rationale underpinning those cases was premised on the decision of Agnew v. Lacey Co-Ply, 33 Wash.App. 283, 654 P.2d 712 (1982), cert. denied, 99 Wash.2d 1006 (1983), which the Washington Court of Appeals recently rejected outright in Morrell v......
  • Turner v. Vulcan, Inc.
    • United States
    • Washington Court of Appeals
    • 2 Noviembre 2015
    ...refuse to confirm award): see also ACF Prop. Mgmt.. Inc. v. Chaussee, 69 Wn.App. 913, 921, 850 P.2d 1387 (1993); Aanew v. Lacey Co-Play, 33 Wn.App. 283, 288, 654 P.2d 712 (1982) ("If a dispute is not arbitrable, the arbitrators have no power to resolve it."). Failure to seek discretionary r......
  • Turner v. Vulcan, Inc.
    • United States
    • Washington Court of Appeals
    • 2 Noviembre 2015
    ...to confirm award): see also ACF Prop. Mqmt., Inc. v. Chaussee, 69 Wn. App. 913, 921, 850 P.2d 1387 (1993); Agnew v. Lacey Co-Play, 33 Wn. App. 283, 288, 654 P.2d 712 (1982) ("If a dispute is not arbitrable, the arbitrators have no power toresolve it."). Failure to seek discretionary review ......
  • Mainline Rock & Ballast, Inc. v. Barnes, Inc.
    • United States
    • Washington Court of Appeals
    • 16 Abril 2019
    ...amount deceeded the amount claimed.¶ 52 The court in Phillips Building Co. v. An distinguished Agnew v. Lacey Co-Ply , 33 Wash. App. 283, 654 P.2d 712 (1982), on which Barnes relies. In the latter decision, this court modified an arbitration award because the arbitrators failed to award the......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT