American Sur. Co. of New York v. Noe

Decision Date21 June 1932
Citation245 Ky. 42,53 S.W.2d 178
PartiesAMERICAN SURETY CO. OF NEW YORK v. NOE.
CourtKentucky Court of Appeals

Rehearing Denied Oct. 28, 1932.

Appeal from Circuit Court, Harlan County.

Action by Margie Noe against the American Surety Company of New York and another. Judgment for plaintiff, and named defendant appeals.

Affirmed.

W Pratt Dale, of Louisville, and Forester & Carter, of Harlan for appellant.

J. B Snyder, of Harlan, James M. Gilbert, of Pineville, and H. H. Fuson and E. H. Johnson, both of Harlan, for appellee.

RICHARDSON J.

Mrs. Margie Noe desiring to construct a theater and office building in Harlan, Harlan county, Ky. entered into a written contract for that purpose, on the 2d day of September, 1928, with Crider & Dunavent, a firm engaged in the business of general contractors, to construct it for her. To secure her in their performance of the contract, a bond for $17,850 was executed and delivered by them with the American Surety Company, as their surety. In their contract with her for the agreed consideration of $35,700, they bound themselves to "provide all the materials and perform all the work to erect and complete the building according to its terms and the plan and the specifications prepared by the architects named in the contract." She agreed to pay them 85 per cent. of the contract price, on "only architects' certificates" as the work progressed. By the bond of the American Surety Company, it agreed that the principals named in the bond "shall well and truly perform said contract and specifications in the manner and within the time therein specified according to the letter and spirit thereof, and shall pay for all material and labor used by the obligors in lawful moneys of the United States."

Crider & Dunavent failed to carry out their contract. On September 2, 1928, Mrs. Noe instituted this action in the Harlan circuit court to recover of them and the American Surety Company the amounts which she claimed she was caused to expend to complete the building as per the contract of Crider & Dunavent. The court decreed against Crider & Dunavent a recovery of $19,756.18, and against the American Surety Company, $17,850, the sum specified in its bond, with interest. The American Surety Company appeals.

In its original answer, in addition to a traverse, it affirmatively alleged: "That the plaintiff violated that part of the contract in that she procured for and furnished to the contractors, Crider & Dunavent, the sum of $15,000.00, without any certificate being issued by said architects, R. F. Graf & Sons, and which was used by the said contractors in the payment of their indebtedness of their own and not included in the performance of work under a contract in this case, contrary to the terms of said contract and the bond sued on herein, improperly and without right taken credit as a payment on said contract for said sum of $15,000.00." It further averred: "That she failed to retain the sum of 15% on amount of the contract price and retained only $3,249.09, when in fact she should have retained $5,580.00, making a difference between what she should have retained, and what she retained under the contract the sum of $2,335.91, for no part of which sum this defendant will be liable under this bond and contract."

After the evidence was taken, it filed an amended answer wherein it was charged that: "She signed the $15,000 note as surety for Crider and Dunavent under an understanding and agreement between the plaintiff and said contractors, Crider and Dunavent, that the said note would be paid by plaintiff using for said payments the amount due under the first estimate or certificate obtained from the contractor in charge of said work to the said amount of $15,000.00; that the architects made an estimate on December 11, 1928, and issued the certificate of $15,000.00, and that plaintiff attempted to credit her account with the contractors by the amount of her liability under the note executed for the $15,000.00." It further averred that: "Through the execution of said note by the plaintiff to the First State Bank of Harlan, and the deposit to the credit of Crider and Dunavent in said bank the sum of $15,000.00, was a payment in advance under said contract between plaintiff and Crider and Dunavent, or plaintiff has failed to pay to said contractors the amount of the estimate or certificate issued by the architect in the sum of $15,000.00 on the 11th day of December 1928, and one of said alternatives is true, and this defendant is unable to state which alternative is true other than disclosed by the proof herein."

It is fairly shown by the evidence that Crider & Dunavent, at the time they entered into the contract with Mrs. Noe, were not financially prepared to begin the execution of, much less to carry out, their contract, and that their securement of the proceeds of the $15,000 note was both necessary and required to enable them to begin its performance. After securing the loan of $15,000 and before December 11, 1928, the date of the architect's first certificate, they deposited in the bank, funds derived from other sources, and the proceeds of the $15,000 note, the sum of $32,777.59, with which they paid on other contracts $15,164.89, and for material and labor which actually went into Mrs. Noe's building, the sum of $17,877.59. On the 11th day of December, 1928, the architect made the first estimate and issued the first certificate per the terms of the contract under which Mrs. Noe's building was constructed. At that time Crider & Dunavent claimed to him that they had on the ground for use in her building $25,000 worth of material. But on their and his estimate of the material on hand, he issued the certificate only for $15,000, delivered it to them, and they assigned it to Mrs. Noe; she retained it until the $15,000 note matured in April, 1929, when she applied its proceeds to the payment of the note. After the $15,000 certificate was issued, Crider & Dunavent continued to perform their contract. The building progressed, and the architect's certificates were issued, from time to time, to the contractors and paid by Mrs. Noe, until February 27, 1929, when, on their failure properly to perform their contract, the architect took under advisement with the American Surety Company of New York, the condition and situation of Crider & Dunavent and the status of the building of Mrs. Noe. He explained the situation, and condition of Crider & Dunavent, and imparted to Radford, its assistant manager, the amount that had been expended on her building. He advised Radford that the best thing to do was to take over the building under article 5 of the contract; that Crider & Dunavent did not have a capable foreman and superintendent on the job. Thereupon, Radford and the architect agreed for the architect to find and place in charge of the construction and completion of the building a suitable man as foreman and superintendent, which was accordingly done. Under this arrangement between them, Elmer Henry was selected and placed in charge as foreman and superintendent. "From then on they proceeded that way." At that time Crider & Dunavent were unable to pay their laborers, and the architect would not issue to them certificates. Thereupon, the American Surety Company of New York, through its agent, C. T. Dodson, agreed to, and did, advance Crider & Dunavent $1,000 which they secured by an order on Mrs. Noe's contract for that amount and delivered it to the American Surety Company of New York; the architect agreeing to issue the certificate when the work had thereafter sufficiently progressed to justify him. Crider & Dunavent were unable further to carry out the contract without assistance. The architect sought and obtained on May 6, 1929, the written consent of the American Surety Company of New York to apply the contract price in excess of 85 per cent. to pay for material as it was delivered. Thereafter the architect continuously corresponded with the representatives of the American Surety Company of New York, "and kept them advised as to just what was going on." Crider & Dunavent abandoned the contract. Henry assumed full charge, "and just continued as he had been," except "Mrs. Noe made the payroll and bought sufficient material to complete the building according to the plan and specifications." In doing so, she paid for material and labor in excess of the contract price, $19,766.68. Materialmen's liens were asserted therefor by the holders of the claims which were afterwards paid by Mrs. Noe with funds borrowed from the Louisville Title Company, after the building had been completed under the superintendency of Henry. After it was so completed, the architect wrote to the American Surety Company of New York. It replied as follows:

"Louisville, Ky. June 18, 1929.
"Mr. R. F. Graf, R. F. Graf & Sons, Architects, Knoxville, Tenn.

In Re: Crider & Dunavent Contract bond to Mrs. Margie Noe, #918513B.

This will acknowledge receipt of your letter of the fifteenth. The information you have given me has been passed to our legal department for their advice. As soon as I am in receipt of a reply, I shall communicate with you.

Thanking you for the attention given this matter, I am,

Yours very truly,

Lewis Y. Johnson, Manager.

"By O. L. C. Radford, Asst. Mgr."

It should be noted that at no time did the appellant assert or claim a release of its obligation under its bond, nor intimate the defense now relied on.

A narration of the facts and the excerpts above of the appellant's pleadings show the appellant has shifted positions.

On being advised by the architect of the inability of Crider &amp Dunavent to carry out their contract, it (a) chose to select a foreman and superintendent, and advanced funds to...

To continue reading

Request your trial
20 cases
  • State Bank of Wheatland v. Turpen
    • United States
    • United States State Supreme Court of Wyoming
    • June 26, 1934
    ...... Maryland Casualty Company v. School. District, 188 Wis. 520, 205 N.W. 926; American. Surety Co. v. Noe, 245 Ky. 42, 53 S.W.2d 178;. Pickens County v. National Surety Company, (C. ......
  • Federal Deposit Ins. Corp. v. American Surety Co. of NY, 2325.
    • United States
    • U.S. District Court — Western District of Kentucky
    • June 30, 1941
    ...in balancing the equities. United States Fidelity & Guaranty Co. v. Mayo Arcade Corp., 253 Ky. 763, 70 S.W.2d 531; American Surety Co. v. Noe, 245 Ky. 42, 53 S.W.2d 178; United States Fidelity & Guaranty Co. v. McGinnis' Adm'r, 147 Ky. 781, 145 S.W. 1112; Lewis' Adm'r v. United States Fidel......
  • National Sur. Corp. v. First Nat. Bank
    • United States
    • Court of Appeals of Kentucky
    • May 9, 1939
    ...... the matter and therefore the demurrer to the petition as. amended was properly sustained. They rely upon American. Bonding Company of Baltimore v. First National Bank, 85. S.W. 190, 27 Ky.Law Rep. 393, and Louisville Trust. Company v. Royal Indemnity Company, ...United. States Fidelity & Guaranty Company v. Mayo Arcade. Corporation, 253 Ky. 763, 70 S.W.2d 531; American. Surety Company of New York v. Noe, 245 Ky. 42, 53 S.W.2d. 178; United States Fidelity & Guaranty Company v. McGinnis" Adm'r, 147 Ky. 781, 145 S.W. 1112;. Lewis' Adm'r v. ......
  • Dorman v. Carnes
    • United States
    • Court of Appeals of Kentucky
    • June 23, 1936
    ...... which alters the position of the surety or his liability. American Surety Co. of New York v. Noe, 245 Ky. 42,. 53 S.W.(2d) 178; New York Indemnity Co. v. Hurst, . ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT