Arst v. Max Barken, Inc.

Decision Date02 August 1983
Docket NumberNos. 45851,45911,s. 45851
Citation655 S.W.2d 845
CourtMissouri Court of Appeals
PartiesDavid P. ARST and Maxine E. Arst, his Wife, Plaintiffs-Appellants, v. MAX BARKEN, INC., Defendant-Respondent, Third-Party Plaintiff, v. REITZ & JENS, INC., and The Freeman Contracting Company, Inc., Third-Party Defendants.

Michael J. McKittrick, Clayton, for plaintiffs-appellants.

Bernard A. Barken, Clayton, for respondent.

Ralph Kleinschmidt, St. Louis, for Freeman Contracting.

W.H. Copeland, Clayton, for Reitz & Jens.

Edward S. Meyer, St. Louis, for 3rd Party.

DOWD, Chief Judge.

On March 5, 1981, plaintiff-appellants David and Maxine Arst brought suit against respondent Max Barken, Inc. for breach of express and implied warranties in the construction of their residence, and for breach of a subsequent agreement to repair. Respondent filed a third party petition against Reitz & Jens, Inc. and Freeman Contracting Company. On May 13, 1982, the trial court sustained respondent's motion for summary judgment and this appeal followed. We affirm.

Before this court, respondent filed a motion to dismiss appellants' appeal on the grounds that appellants' statement of the facts is not a fair and concise statement as required by Rule 84.04(c). Although appellants' statement of facts did omit certain facts, the dismissal of an appeal is a drastic remedy and we find that it would be inappropriate here. Motion denied.

Appellants entered into a contract with respondent on June 20, 1969, for the purchase of a residence which was constructed by respondent. Within one month after occupying their residence, appellants discovered cracks and shifting of the foundation and on August 29, 1969, appellants gave respondent notice of this condition. After such notification, respondent's agents made numerous verbal assurances that the cracks would be repaired. On October 28, 1971, and again on January 21, 1974, appellants notified respondent that despite its repair of the cracks, leaks continued and additional cracks appeared.

Respondent's employees inspected the residence in 1974 and again in 1975. In 1976, respondent notified appellants that based upon examinations by Reitz & Jens, respondent's soil engineers, the cracking was a result of underlying soil conditions which caused the vertical settling of the residence. Respondent then contracted with Freeman Contracting Company to underpin the foundation and patch the cracks in appellants' residence. Nevertheless, more cracks appeared after the foundation was underpinned.

Respondent continued to monitor the problem but did nothing further to remedy the condition. In a letter dated August 7, 1979, respondent's president stated to appellants, "I do not feel that Max Barken, Inc. has any further responsibility to you in connection with the construction of your home."

Appellants thereafter retained two soil engineering firms which inspected the premises and concluded that the residence was not settling vertically, but rather was sliding horizontally down the slope because respondent had rechanneled an adjacent creek without stabilizing the slope prior to construction.

In their brief, appellants relied on four points. All four of these points, however, deal with the question of whether the trial court erred in sustaining respondent's motion for summary judgment on the grounds that the action was barred by the statute of limitations.

On review of a grant of a motion for summary judgment, parties against whom summary judgment was entered must be accorded every favorable intendment of the record. Thompson v. Parker, 608 S.W.2d 415, 416 (Mo. banc 1980).

In their petition, appellants alleged that respondent expressly and impliedly warranted that the residence it sold to appellants was constructed in a good and workmanlike manner and that respondent breached these warranties when it constructed the residence on a slope which was unstable. Such actions are governed by a five year statute of limitations. § 516.120 RSMo 1978; Ruhling v. Robert Dawes Construction Company, 610 S.W.2d 403, 405 (Mo.App.1980).

Under § 516.100 RSMo 1978, the five year statute of limitations does not begin to run until the cause of action accrues, which is defined as follows:

... the cause of action shall not be deemed to accrue when the wrong is done or the technical breach of contract or duty occurs, but when the damage resulting therefrom is sustained and is capable of ascertainment, and, if more than one item of damage, then the last item, so that all resulting damage may be recovered, and full and complete relief obtained.

§ 516.100 RSMo 1978.

Appellants contend that their damages were not ascertainable until after April, 1976, when "additional movement occurred," and "only then could appellants have maintained an action for the full extent of their damages to a successful conclusion."

Only when there is more than one item of damage does the cause of action accrue, so as to begin only after the last wrong has been completed. Ruhling v. Robert Dawes Construction Company, 610 S.W.2d 403, 405 (Mo.App.1980). When there is only one wrong which results in continuing damage, as in the case at bar, the cause of action accrues when that wrong is committed and the damage sustained is capable of ascertainment. We find that there was just one wrong committed here, not continuing wrongs. Consequently, appellants cause of action accrued in August of 1969 when their house was delivered in its defective condition and appellants discovered the cracks and shifting of their house's foundation. At this time, the damage was sustained and capable of ascertainment. The fact that the damage was continuing is immaterial since an instruction on future damages is included in the Missouri Approved Instructions and appropriate in such circumstances.

Appellants cite three Missouri cases in which there was a delayed manifestation of injury: Krug v. Sterling Drug, Inc., 416 S.W.2d 143 (Mo.1967); Clohesy v. Century Electric Co., 142 S.W.2d 780 (Mo.App.1940); and Thorne v. Johnson, 483 S.W.2d 658 (Mo.App.1972), in support of their argument that their damages were not ascertainable until after April, 1976. In all three of these cases, the plaintiffs employed experts to ascertain their injuries, and these experts nonetheless failed to ascertain the damages. The reasoning behind these cases was well stated by the Missouri Supreme Court in Krug: "[A] person must have some notice of his cause of action, an awareness either that he has suffered an injury...

To continue reading

Request your trial
23 cases
  • Business Men's Assur. Co. of America v. Graham, WD
    • United States
    • Missouri Court of Appeals
    • November 8, 1994
    ...wrong that continues and becomes more serious over time does not extend the time within which suit may be brought. Arst v. Max Barken, Inc., 655 S.W.2d 845, 847 (Mo.App.1983). In order to prove that it was entitled to a directed verdict as a matter of law, Skidmore had to present undisputed......
  • CitiMortgage, Inc. v. Equity Bank, N.A.
    • United States
    • U.S. District Court — Eastern District of Missouri
    • August 18, 2017
    ...in motion, as soon as the creditor, by his own act and in spite of the debtor, can make demand payable."); Arst v. Barken, Inc. , 655 S.W.2d 845, 848 (Mo. Ct. App. 1983) (rejecting the plaintiffs' arguments that their cause of action did not arise until they gave defendant notice of a breac......
  • Nettles v. American Tel. and Tel. Co.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • June 5, 1995
    ...of a cause of action. Allison, 59 S.W.2d at 773; see also Dixon, 649 S.W.2d at 438-39; Rippe, 292 S.W.2d at 90; Arst v. Max Barken, Inc., 655 S.W.2d 845, 847 (Mo.Ct.App.1983). In Allison, the plaintiff was accidentally struck in the face by a steel bar in 1926. He argued that although he wa......
  • Stolzenburg v. Biewer Lumber, LLC
    • United States
    • U.S. District Court — Eastern District of Missouri
    • June 28, 2016
    ...which means that the damage they suffered was capable of ascertainment within the meaning of § 516.100.1."); Arst v. Max Barken, Inc., 655 S.W.2d 845, 848 (Mo. Ct. App. 1983) (claim barred by statute of limitations where the Arsts "discovered cracks and shifting of their foundation in Augus......