Associated v. Northwest

Decision Date31 March 2009
Docket NumberNo. 36834-0-II.,36834-0-II.
Citation203 P.3d 1077,149 Wn. App. 429
CourtWashington Court of Appeals
PartiesASSOCIATED PETROLEUM PRODUCTS, INC., a Washington corporation, Respondent, v. NORTHWEST CASCADE, INC., Appellant.

Lucy R. Clifthorne, Attorney at Law, Tacoma, WA, for Appellant.

Ken Fielding, James Victor Handmacher, Morton McGoldrick PS, Tacoma, WA, for Respondent.

ARMSTRONG, J.

¶ 1 Associated Petroleum Products, Inc. (Associated), a diesel fuel provider for Northwest Cascade, Inc. (Northwest), sued Northwest for money due under several invoices. Northwest had deducted the claimed amounts from its payments to Associated to compensate for fees Northwest had paid after Associated added them to its invoices without telling Northwest. Northwest now appeals the trial court's summary judgment in favor of Associated, arguing that (1) Associated had a duty to give "reasonable notice" before unilaterally modifying the contract and (2) Northwest's repeated payments of the disputed charges do not constitute an "account stated" as a matter of law because they were based on an excusable mistake. Northwest also appeals the trial court's award of attorney fees to Associated. Because issues of material fact exist as to whether Associated gave reasonable notice to Northwest of its new charges, we reverse the summary judgment, vacate the attorney fees award, and remand for further proceedings.

FACTS1

¶ 2 Associated is a petroleum products wholesaler. Northwest uses diesel-powered equipment at its construction sites. In 2005, Northwest hired Associated to provide "fleet fueling" services wherein Associated employees fueled Northwest's equipment at its job sites in the evenings. The companies agreed that as a service charge, Northwest would pay 20 cents per gallon over the market "rack rate" for the fuel it purchased. The agreement was terminable at will by either party.

¶ 3 Associated began providing the service in August 2005. In December 2005, Associated's sales manager, Chris Bertram, arranged a meeting with Northwest's fleet manager, Jeff Warren, to "discuss housekeeping issues" regarding the fleet fueling arrangement. Clerk's Papers (CP) at 286. According to Warren, Bertram "wanted to talk about ways our construction crews could make their job easier, such as lining up the equipment that needed to be fueled by the roadside." CP at 286. Warren also recalled that Bertram had suggested adding "demurrage" fees to the contract, but Warren had responded, "No, no way." CP at 201. Overall, the meeting "did not stand out in [Warren's] mind" as involving any renegotiation of contract terms. CP at 286.

¶ 4 After the meeting, Associated's lengthy invoices began to include charges referred to as "time on site" charges. Over four months, those charges totaled $13,404.16. Associated added the charges because Northwest was often sending Associated out to refuel equipment that needed very little fuel. Warren did not notice the "time on site" charges, however, and consequently authorized payment on seven bi-monthly invoices that included them.

¶ 5 In March 2006, Associated terminated the fleet fueling arrangement for other reasons. Warren began going through Associated invoices to prepare for negotiating an agreement with a new fuel provider. He discovered the "time on site" charges and called Bertram to ask what they were for. Bertram initially said that he "could not explain" the charges; later, he told Warren that he had told him about the charges in the "housekeeping" meeting several months earlier. CP at 287. Bertram produced an undated document entitled "APP Fleet Fueling —Wet-Hosing—Small Tank Delivery Policies & Procedures," claiming that he gave it to Warren at the meeting. CP at 281. The document included a section labeled "Gallonage Requirements" that described an hourly "demurrage fee" for deliveries where fewer than 200 gallons were needed. CP at 281. Warren did not remember discussing any such charges, and he testified in a declaration that he would not have agreed to them even if they had come up because he knew that he did not have authority to do so.

¶ 6 Northwest still had two pending Associated invoices at the time, so in paying them it deducted the amounts already paid for the "time on site" charges. Associated sued Northwest for the balance due under the invoices, $13,871.39, plus interest. Associated then moved for summary judgment, arguing that it was entitled to the invoiced amounts as a matter of law under the doctrine of "account stated" and because the agreement was terminable at will. The trial court granted Associated's motion for summary judgment and awarded it attorney fees pursuant to the parties' contract.

ANALYSIS

¶ 7 Northwest argues that the trial court erred in granting summary judgment to Associated because questions of material fact exist as to whether Associated gave adequate notice of the new charges and whether Northwest agreed to them. A trial court may grant a motion for summary judgment where there is no genuine issue as to any material fact and the moving party is entitled to a judgment as a matter of law. CR 56(c). We review an order on summary judgment de novo, viewing the facts in the light most favorable to the nonmoving party. Vallandigham v. Clover Park Sch. Dist. No. 400, 154 Wash.2d 16, 26, 109 P.3d 805 (2005).

A. Terminable At Will Contracts

¶ 8 Associated argues that it was entitled to unilaterally modify the contract because it was terminable at will. Northwest responds that it should not be bound by Associated's unilateral modification because Associated did not provide Northwest with reasonable notice of it.2

¶ 9 A party to a terminable at will contract can unilaterally modify the contract because, in doing so, the party is simply terminating the old contract and offering a new one. Cascade Auto Glass, Inc. v. Progressive Casualty Ins. Co., 135 Wash.App. 760, 768-69, 145 P.3d 1253 (2006) (citing Gaglidari v. Denny's Rests., Inc., 117 Wash.2d 426, 433-34, 815 P.2d 1362 (1991)), review denied, 161 Wash.2d 1012, 166 P.3d 1217 (2007). But before terminating such a contract, the party must give reasonable notice to the other party. Cascade Auto Glass, 135 Wash.App. at 766, 145 P.3d 1253 (citing Mayflower Air-Conditioners, Inc. v. W. Coast Heating Supply, Inc., 54 Wash.2d 211, 213, 339 P.2d 89 (1959)). Reasonable notice is notice "`fairly to be expected or required under the particular circumstances.'" Cascade Auto Glass, 135 Wash.App. at 767, 145 P.3d 1253 (quoting Black's Law Dictionary 1091 (8th ed.1999)). Whether notice is reasonable depends on the circumstances of each case and is ordinarily a question of fact for the jury. Cascade Auto Glass, 135 Wash. App. at 766-67, 145 P.3d 1253 (citing Lano v. Osberg Constr. Co., 67 Wash.2d 659, 663, 409 P.2d 466 (1965)).

¶ 10 We hold that a genuine issue of material fact exists as to whether Associated provided reasonable notice of the new charges to Northwest before imposing them. Associated claims that Bertram discussed the new charges with Warren at the December meeting. Warren says that Associated wanted the meeting to discuss "housekeeping" issues. Associated claims that it provided Warren with a sheet explaining the new charges. Warren says that he does not recall seeing the new sheet and further explains that he would not have agreed to the new charges because he had no authority to do so. Associated then began billing for the new charges in its lengthy itemized billings. But Associated did not separately confirm or highlight the "new" agreement either in its billings or in a separate document. Although Northwest may have been lax in reviewing its billings, we cannot conclude as a matter of law that the new billings alone gave Northwest reasonable notice of a new contract, particularly where the parties had operated under the old agreement for only four or five months, and Warren had specifically rejected any increase in the fees at the December meeting. Under these circumstances, the trier of fact could find that Associated had to provide something more than simply changing its billings to create a new agreement.

B. Account Stated

¶ 11 Associated also argues that the doctrine of "account stated" entitles it to relief as a matter of law. Northwest responds that even if that doctrine applies, genuine issues of material fact remain regarding whether its failure to notice the charges on the invoices was an excusable mistake.3

¶ 12 An account stated is "`a manifestation of assent by debtor and creditor to a stated sum as an accurate computation of an amount due the creditor.'" Sunnyside Valley Irrigation Dist. v. Roza Irrigation Dist., 124 Wash.2d 312, 315, 877 P.2d 1283 (1994) (quoting 2 Restatement (Second) of Contracts § 282(1), at 386 (1981)). There must be some form of assent to the account, although that assent may be implied from the circumstances and acts of the parties. Sunnyside Valley Irrigation, 124 Wash.2d at 316, 877 P.2d 1283 (quoting Shaw v. Lobe, 58 Wash. 219, 221, 108 P. 450 (1910)). An account stated is an admission of the facts asserted and a promise by the debtor to pay the sums indicated.4 Sunnyside Valley Irrigation, 124 Wash.2d at 315, 877 P.2d 1283.

¶ 13 Associated relies on Sunnyside Valley Irrigation, 124 Wash.2d 312, 877 P.2d 1283. In that case, a debtor paid invoices to the creditor over about eight years. Sunnyside Valley Irrigation, 124 Wash.2d at 317, 877 P.2d 1283. During that period, the debtor "had some concerns about the billing" and "made inquiries about the sums indicated," but it ultimately paid the bills without protest. Sunnyside Valley Irrigation, 124 Wash.2d at 317, 877 P.2d 1283. The trial court granted summary judgment to the creditor, finding that the debtor had each year "expressly or impliedly consented and agreed" to the bills and was thus precluded from contesting the amount of those bills by the doctrine of account stated. Sunnyside Valley Irrigation, 124...

To continue reading

Request your trial
33 cases
  • Nielson v. Robbins, No. 63479-8-I (Wash. App. 6/1/2010)
    • United States
    • Washington Court of Appeals
    • June 1, 2010
    ...could not be reformed where the evidence "merely demonstrates a unilateral mistake"); Associated Petroleum Prods., Inc. v. Nw. Cascade, Inc., 149 Wn. App. 429, 437, 203 P.3d 1077, 1082 (2009) ("Unilateral mistake entitles a party to reform a contract only if the other party engaged in fraud......
  • Spradlin Rock Prods., Inc. v. Pub. Util. Dist. No. 1 of Grays Harbor Cnty.
    • United States
    • Washington Court of Appeals
    • November 1, 2011
    ...the account, although that assent may be implied from the circumstances and acts of the parties.” Assoc. Petroleum Prods., Inc. v. Nw. Cascade, Inc., 149 Wash.App. 429, 436, 203 P.3d 1077, rev. denied, 166 Wash.2d 1034, 217 P.3d 782 (2009). An account stated is “an admission by each party o......
  • Traverso v. Snyder
    • United States
    • Washington Court of Appeals
    • August 15, 2022
    ... ... party to reform a contract only if the other party engaged in ... fraud or inequitable conduct." Associated Petrol ... Prods., Inc. v. Nw. Cascade, Inc. , 149 Wn.App. 429, 437, ... 203 P.3d 1077 (2009) (citing Gammel v. Diethelm , 59 ... ...
  • Johnson v. Associated Milk Producers, Inc.
    • United States
    • Iowa Supreme Court
    • October 14, 2016
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT