Ayer & Lord Tie Company v. Young

Decision Date29 March 1909
Citation117 S.W. 1080,90 Ark. 104
PartiesAYER & LORD TIE COMPANY v. YOUNG
CourtArkansas Supreme Court

Appeal from Monroe Circuit Court, Eugene Lankford, Judge; reversed.

STATEMENT BY THE COURT.

This action was brought by Herbert Young against the Ayer & Lord Tie Company for an amount alleged to be due him by defendant for building a skidway at a lumber mill.

In October or November, 1906, one U.S. Pitney, who had charge of the defendant company's business in the State of Arkansas, made an agreement with the plaintiff to build a skidway at a sawmill on White River, and agreed to pay him therefor $ 15. The defendant had a contract with the owners of the mill to furnish them saw logs, and the skidway was to be used in delivering the logs. The plaintiff started the erection of the skidway, but soon afterwards stopped work on account of the high water.

The plaintiff testified that he did nothing more toward the erection of the skidway until the following summer, when one Harbin, an employee of the defendant, came down to look after the work, and to see about cutting the timber and logs. That Harbin said the mill owners objected to the kind of skids that were being put in, and made a new contract with him to build a different kind of skidway. That he then erected it according to the terms of the new contract, and that there is a balance due him of $ 85.

C. M Harbin testified that he was sent by the company to get some one to log the mill and to put it in condition to receive the logs for sawing; that a skidway was necessary for this purpose; that he instructed Herbert Young to fix the skidway and that if there was any additional work outside of what Pitney had told him to do that he would see that he got his money.

Pitney testified that Harbin was sent to the mill by him to start it up, but that he had no authority to make an additional or new contract with Young.

The suit was originally brought in the justice of the peace court. On appeal in the circuit court, there was a verdict for the plaintiff for $ 50. The defendant has duly prosecuted an appeal to this court.

Judgment reversed and cause remanded.

Thomas & Lee, for appellant.

1. There is no affirmative proof that Harbin was the agent of appellant, and his acts, admissions and declarations are not competent until his agency is shown by affirmative proof. 223 Ill. 41; 79 N.E. 38; 53 S.E. 908; 5 How. 29; 43 Ill. 43; I Conn. 255; 193 Mass. 458; 87 P. 469; 107 N.W. 227; 10 Ark 213; 58 Id. 21; 76 Id. 472; 64 Id 217; 96 Iowa 737; 111 F. 337; 28 Nev. 235; 85 P. 657; 33 S.W. 604; 22 N.W. 276; 129 F. 583-5.

2. Proof of the making of similar contracts by an agent which were carried out by the principal is inadmissible to show the agent's authority or to raise an inference that he had authority to make the contract. 97 Mich. 72; 92 S.W. 273-4; 82 Tex. 516; 44 Ill. 437; 53 S.E. 908; 41 Me. 382.

3. To submit the question of agency or ratification to a jury where there is no competent evidence is reversible error. 28 P. 505; 96 Iowa 737; 85 N.W. 403.

3. There is no proof that Harbin was ever an agent, or that his acts were made known to appellant. There must be full knowledge by the principal of all the material facts and of the terms of a contract, as these are essential elements of an effective ratification by the principal of an unauthorized contract of his agent. 107 N.W. 227; 69 Id. 308; 85 P. 657-661; 115 Ill. 138; 41 Me. 382; 9 Pet. 607-629; 105 U.S. 355-360; 121 Id. 135; 115 F. 678-681; 128 Id. 243-255; 41 U.S. 213-18; Clark & Skyles on Ag. § 106-7, pp. 266, 271; 64 Ark. 217; 76 Id. 472; 58 Id. 21; 31 Id. 212; 76 Id. 563. In view of these authorities, the court erred in its instructions.

Manning & Emerson, for appellee.

1. Appellant's objection to the instructions are general. The court's attention should have been called to defects, and a specific instruction correcting the alleged defects asked. 89 Ark. 24.

2. No exceptions were saved to the testimony of Young and Simmons.

3. The proof shows ratification by appellant. Acquiescence and silence when the agent's acts are brought home to the knowledge of the principal is a ratification. 32 F. 270; 87 Id. 61; 73 Id. 110; 21 Ark. 554; 29 Id. 131; 42 Id. 97; 66 Id. 209. Third parties are entitled to notice of the restrictions of the agent's authority where he is attending generally to the business of a principal. 27 F. 894 and cases supra.

OPINION

HART, J., (after stating the facts).

It is earnestly insisted by counsel for appellant that there is no evidence in the record tending to show that Harbin was ever an agent of the Ayer & Lord Tie Company, and that the acts, admissions or declarations of Harbin are not competent to prove his agency. While it is true that in an action against the principal the declarations or admissions of the agent are not competent to prove the agency, the rule has no application here. No attempt was made to prove Harbin's authority by his declarations or admissions. Harbin was a witness in the case, and his testimony was of matters of which he stated he had knowledge. If he knew the facts concerning the extent of his authority, his testimony was as competent on that point as that of any other witness having knowledge of the same facts. The point was expressly so ruled in the case of Beekman Lumber Co. v. Kittrell, 80 Ark. 228, 96 S.W. 988.

The testimony of Harbin to the effect that he was sent down there to start the mill up and have it logged, in connection with his further testimony that the skidway was necessary for this purpose, was sufficient testimony from which the jury might infer that he had the authority to make the contract sued on.

Counsel for appellant also assigns as error the action of the court in giving the following instructions:

"No. 3. Although you believe from the evidence that Pitney agreed to pay plaintiff $ 15 for building a skidway still if you find from the evidence that a new and different contract was made by the plaintiff and Harbin, who was in the employ of the defendant, whereby a different sum was to be paid for different work, the defendant would be liable, if you find that the work was done by the plaintiff for defendant under the last contract, and defendant ratified same by receiving the benefit of the labor.

"No. 4. It was agreed by the plaintiff and the defendant company, or its agent, Mr. Pitney, that he was to...

To continue reading

Request your trial
18 cases
  • Pekin Cooperage Co. v. Gibbs
    • United States
    • Arkansas Supreme Court
    • October 26, 1914
    ...that of approval of the milling company's acts. Ratification is a question of fact for the jury, under the circumstances. 99 Ark. 358; 90 Ark. 104-7. SMITH, J., (after stating the facts). As has been stated, the proof was sufficient to support the jury's finding that the staves had not been......
  • American Railway Express Co. v. Davis
    • United States
    • Arkansas Supreme Court
    • April 30, 1923
    ...Green & McInnis, and June R. Morrell, in reply. Burden was on plaintiff to show that Garrison was acting within scope of his employment. 90 Ark. 104; 105 Ark. 130; 124 1073; 105 Ark. 326. Court erred in refusing to give appellant's instruction numbered 1 to 5, to the effect that the court w......
  • Graysonia-Nashville Lumber Co. v. Carroll
    • United States
    • Arkansas Supreme Court
    • February 19, 1912
    ...144 S.W. 519 102 Ark. 460 GRAYSONIA-NASHVILLE LUMBER COMPANY v. CARROLL Supreme Court of ArkansasFebruary 19, 1912 [144 S.W. 520] ... ...
  • Wales-Riggs Plantations v. Banks
    • United States
    • Arkansas Supreme Court
    • January 1, 1912
    ...of the principal and the agent can not be proved by the declaration of the agent, it may be established by the testimony of the agent." 90 Ark. 104; 80 Ark. 288. also 93 Ark. 521; 11 Ark. 189; Id. 378; 55 Ark. 112; 54 Ark. 216; 49 Ark. 320. 3. The answer having set up defenses cognizable on......