Bfgc Architects Planners v. Forcum/Mackey

Decision Date21 June 2004
Docket NumberNo. G032543.,G032543.
Citation14 Cal.Rptr.3d 721,119 Cal.App.4th 848
PartiesBFGC ARCHITECTS PLANNERS, INC., Cross-complainant and Appellant, v. FORCUM/MACKEY CONSTRUCTION, INC. et al., Cross-defendants and Respondents.
CourtCalifornia Court of Appeals Court of Appeals

Collins, Collins, Muir & Stewart, Christine E. Drage, Jacqueline C. Pons-Bunney and Douglas Fee for Cross-complainant and Appellant.

Lang, Richert & Patch, Val W. Saldana and Tracy E. Sagle Benneyan for Cross-defendant and Respondent Forcum/Mackey Construction, Inc.

Case, Ibrahim & Clauss, Brian S. Case, Costa Mesa, F. Albert Ibrahim, Mark R. Guevara and Andrew C. Carlton for Cross-defendant and Respondent S.C. Anderson, Inc.

OPINION

RYLAARSDAM, J.

Cross-complainant BFGC Architects Planners, Inc. (plaintiff) appeals from a judgment entered in favor of cross-defendants,Forcum/Mackey Construction Inc. (Forcum) and S.C. Anderson, Inc. (Anderson) (collectively defendants) after their demurrers were sustained without leave to amend. Plaintiff contends the court erred by holding that its claims for implied indemnity required a predicate tort. We find the demurrers were correctly sustained without leave to amend and affirm.

FACTS

Porterville Unified School District (district) and plaintiff entered into a contract whereby plaintiff agreed to prepare architectural drawings for and supervise construction of a high school. District also entered into contracts with Forcum and Anderson to act as general contractors for the site phase and construction phase, respectively. In its complaint against plaintiff for breach of contract and professional negligence, district alleged that after construction was completed, Anderson submitted a claim to district for more than $11 million, alleging "delays and disruptions stemming from [plaintiff's] defective design. . . ." District paid Anderson just over $4 million to settle the action; it also spent approximately $717,500 in defense costs and more than $2.1 million in change orders, "many of which were caused by [plaintiff's] failure to perform its work expeditiously . . . [or] with professional skill and care. . . ."

Plaintiff filed a cross-complaint against several parties, including defendants. It alleged defendants were negligent in failing to comply with the terms of their contracts with district and that they "breached their duties as to the standard of care" by failing "to administer, coordinate, construct, install, supervise, build, inspect and assemble [the] structures with reasonable skill and care" and by failing "to perform work and services in a timely manner." It further alleged these deficiencies caused "delays and disruption," led to the underlying dispute between district and Anderson, and caused plaintiff's damages. Plaintiff also sought implied equitable indemnity, apportionment of fault/contribution, and declaratory relief for indemnity.

Defendants each filed a demurrer and motion to strike the causes of action against them. Anderson argued the negligence claim failed to state a cause of action because it owed no duty to plaintiff in connection with plaintiff's performance obligations to district and because plaintiff claimed only purely economic damages. Anderson asserted the equitable causes of action were based on the invalid negligence claim and could not stand alone.

Similarly, Forcum challenged the negligence cause of action, arguing it could not be negligent as a matter of law because it had no agreement with plaintiff but had contracted only with district, and because the purely economic damages plaintiff sought were not recoverable. Forcum attacked the indemnity claim on the ground district had no cause of action against it, and the contribution and declaratory relief claims on the ground they could not stand without a valid underlying cause of action for negligence.

At the hearing, plaintiff agreed with the court's tentative ruling that the negligence cause of action failed based on the economic loss doctrine and limited its argument to the equitable claims. The court sustained the demurrers without leave to amend, ruling that the negligence claim failed to state a cause of action because it sought purely economic damages. The equitable claims failed for that same reason and also because they were purely derivative of the negligence cause of action.

DISCUSSION

Plaintiff contends the court erroneously sustained the demurrers because it "misunderstood the term `joint tortfeasor' . . . ." It asserts that no "`predicate' common law tort" is required to support its claim for equitable indemnity against defendants. Rather, it argues, instead of looking at the allocation of fault, the focus should be on apportionment of the loss based on equity and good conscience. While these arguments have a surface appeal, on closer examination, they lack any factual underpinnings to sustain them in this case.

Although the body of law defining and applying principles of equitable indemnity has not fully gelled but is still evolving, one thing is clear: The doctrine applies only among defendants who are jointly and severally liable to the plaintiff. (GEM Developers v. Hallcraft Homes of San Diego, Inc. (1989) 213 Cal.App.3d 419, 430, 261 Cal.Rptr. 626.) As plaintiff maintains, joint and several liability in the context of equitable indemnity is fairly expansive. We agree it is not limited to "the old common term `joint tortfeasor'. . . ." It can apply to acts that are concurrent or successive, joint or several, as long as they create a detriment caused by several actors. (Yamaha Motor Corp. v. Paseman (1990) 219 Cal.App.3d 958, 964, 268 Cal.Rptr. 514.)

One factor is necessary, however. With limited exception, there must be some basis for tort liability against the proposed indemnitor. (Munoz v. Davis (1983) 141 Cal.App.3d 420, 425, 190 Cal.Rptr. 400.) Generally, it is based on a duty owed to the underlying plaintiff (e.g., Yamaha Motor Corp. v. Paseman, supra, 219 Cal.App.3d at pp. 964-966, 268 Cal.Rptr. 514; Munoz v. Davis, supra, 141 Cal.App.3d at p. 425, 190 Cal.Rptr. 400), although vicarious liability (Fireman's Fund Ins. Co. v. Haslam (1994) 29 Cal.App.4th 1347, 1356, 35 Cal.Rptr.2d 135) and strict liability (Daly v. General Motors Corp. (1978) 20 Cal.3d 725, 737, 144 Cal.Rptr. 380, 575 P.2d 1162) also may sustain application of equitable indemnity. In addition, implied contractual indemnity between the indemnitor and the indemnitee can provide a basis for equitable indemnity. (Bay Development, Ltd. v. Superior Court (1990) 50 Cal.3d 1012, 1028-1035, 269 Cal.Rptr. 720, 791 P.2d 290.) But neither vicarious or strict liability nor implied contractual indemnity are alleged or exist here. Thus, we are left with the requirement that defendants owed a duty to district.

And there are no facts to support this. Plaintiff argues that neither district's pleadings nor those of defendants can dictate the outcome. We agree, with the caveat that plaintiff's pleadings control in ruling on a demurrer. Here, plaintiff's own complaint torpedoes its claim. It alleges defendants breached their duties to district by failing to comply with the terms of their contracts. This is not a cognizable claim on which to base equitable indemnity.

"A person may not ordinarily recover in tort for the breach of duties that merely restate contractual obligations. Instead, "`[c]ourts will generally enforce the breach of a contractual promise through contract law, except when the actions that constitute the breach violate a...

To continue reading

Request your trial
75 cases
  • Archdale v. American Intern. Spec. Lines
    • United States
    • California Court of Appeals Court of Appeals
    • August 22, 2007
    ...do not raise or discuss and which is asserted for the first time in oral argument. (BFGC Architects Planners, Inc. v. Forcum/Mackey Construction, Inc. (2004) 119 Cal.App.4th 848, 854, 14 Cal.Rptr.3d 721; Ace American Ins. Co. v. Walker (2004) 121 Cal.App.4th 1017, 1027, fn. 2, 18 Cal.Rptr.3......
  • Bostick v. Flex Equip. Co., Inc.
    • United States
    • California Court of Appeals Court of Appeals
    • January 29, 2007
    ...com. c, p. 345.) 15. Opinions stating the purported rule include, among others, BFGC Architects Planners, Inc. v. Forcum/Mackey Construction, Inc. (2004) 119 Cal.App.4th 848, 852, 14 Cal. Rptr.3d 721 ("The doctrine applies only among defendants who are jointly and severally liable to the pl......
  • Henry v. Superior Court
    • United States
    • California Court of Appeals Court of Appeals
    • February 25, 2008
    ...distinct and divisible injury." (Id at pp. 1200, fn. 2, 1203, 213 Cal.Rptr. 781;7 see BFGC Architects Planners, Inc. v. Forcum/Mackey Construction, Inc. (2004) 119 Cal.App.4th 848, 852, 14 Cal.Rptr.3d 721["[J]oint and several liability in the context of equitable indemnity is fairly expansi......
  • Fremont Reorganizing Corp. v. Faigin
    • United States
    • California Court of Appeals Court of Appeals
    • August 30, 2011
    ...and indemnitee are mutually liable to another person for the same injury. ( BFGC Architects Planners, Inc. v. Forcum/Mackey Construction, Inc. (2004) 119 Cal.App.4th 848, 852, 14 Cal.Rptr.3d 721( BFGC ).) FRC alleges in its equitable indemnity count that Faigin breached his fiduciary duties......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT