Carson v. Roediger

Decision Date23 March 1994
Docket NumberNo. 93-271,93-271
Citation513 N.W.2d 713
PartiesJudy CARSON d/b/a Savage Lumber Co., Appellant, v. Wesley G. ROEDIGER and Karen M. Roediger, Appellees, and Carpetland U.S.A., Inc., Defendant.
CourtIowa Supreme Court

Jon M. McCright of Fisher, Ehrhart, McCright & Turner, Cedar Rapids, for appellant.

Gregory J. Epping of Terpstra, Terpstra & Epping, Cedar Rapids, for appellees Roedigers.

William J. Wimmer and David A. Bolte of Wasker, Dorr, Wimmer & Marcouiller, P.C., Des Moines, for amicus curiae Iowa Lumber Ass'n.

No appearance by Carpetland U.S.A.

Considered by McGIVERIN, C.J., and HARRIS, LARSON, LAVORATO, and NEUMAN, JJ.

HARRIS, Justice.

In 1981 the legislature extensively amended Iowa statutes on mechanic's liens in order to ensure, according to the bill's preamble, "that the lien of a subcontractor is not enforceable ... except to the extent of the amount owed to the principal contractor at the time" of notice of the lien. 1981 Iowa Acts ch. 186. This dispute is within the familiar pattern in which the principal contractor fails in his obligations and the courts must decide who, as between the homeowner and a subcontractor, must suffer the loss. The trial court, under the special facts and in light of the 1981 legislation, assigned the loss to the subcontractor and we affirm.

In January of 1990 Wesley and Karen Roediger, the defendants, contracted with Larry Pinckney for the construction of a home for the set sum of $126,000. Plaintiff Judy Carson became a subcontractor by delivering construction materials to the site.

By reason of faulty construction by Pinckney, the Roedigers stopped payment under the contract in April of 1990. Pinckney also defaulted in payments to Carson. Carson then filed a mechanic's lien on the Roedigers' property in May, with notice served in June pursuant to Iowa Code section 572.14 (1989). Carson brought an action against the Roedigers to foreclose the lien. This action was consolidated for trial with another such claim by Carpetland USA. The Roedigers then cross-claimed against Pinckney for breach of contract. Pinckney failed to appear, resulting in a default judgment for the Roedigers.

The district court found that the contract price, with the extras ordered by the Roedigers, was $129,557. $108,731 of that total had been paid, so that $20,826 was due. The court found that the Roedigers had established that the cost for repairing defects in the construction and completing the home amounted to $25,235. This sum exceeded any remaining amount due under the contract with Pinckney. The court found that Carson's lien totaled $13,673. Because it found no amount due, the court held all mechanic's liens were canceled pursuant to its interpretation of Iowa Code section 572.14(2). 1 The primary issue on the appeal is whether the district court correctly applied this statute. Carson appeals and Roedigers cross-appeal.

An action to enforce a mechanic's lien is in equity. Iowa Code § 572.26 (1993). The scope of review is therefore de novo. Iowa R.App.P. 4. We give weight to the district court's fact findings, but are not bound by them. Iowa R.App.P. 14(f)(7).

A mechanic's lien is purely statutory in nature. Gollehon, Schemmer & Assoc. v. Fairway-Bettendorf Assoc., 268 N.W.2d 200, 201 (Iowa 1978). All persons who furnish any material or labor for improvements to building or land will generally be entitled to a lien to secure payment for the labor and materials furnished. Iowa Code § 572.2. Mechanic's liens stem from principles of equity which require paying for work done or materials delivered. 53 Am.Jur.2d Mechanic's Liens § 2, at 516 (1970). The doctrines of restitution and prevention of unjust enrichment drive the mechanic's lien entitlement. Id. The mechanic's lien statute is liberally construed to promote these objects and assist parties in obtaining justice. Gollehon, 286 N.W.2d at 201.

Under our statutory scheme, if a mechanic's lien is filed within ninety days of the date on which the last material or labor was furnished, a lien arises for the full amount regardless of the balance due on the general contract. Iowa Code § 572.11. There is an exception in the case of an owner-occupied dwelling; the most a subcontractor can recover in that situation is the balance due, regardless of whether notice is filed within ninety days. Iowa Code § 572.14(2). 2

We analyzed the purposes of Iowa Code section 572.14 in Louie's Floor Covering v. DePhillips Interests, 378 N.W.2d 923 (Iowa 1985). There we noted that chapter 572 was extensively revised in 1981. Id. at 925; 1981 Iowa Acts ch. 186. This revision was intended to alleviate the "hardship when the principal contractor goes bankrupt or becomes defunct" after the owner has already paid some or all of the contract price. See Louie's, 378 N.W.2d at 927. We also approved language stating that "[i]f an innocent party must be hurt, the materialman is less favored than a homeowner because the materialman is far more sophisticated and familiar with the construction industry and better able to protect" his or her interests than is the homeowner. Id.

This case involved an owner-occupied dwelling. While we have never construed the "balance due" language in section 572.14(2), we did consider identical language found in section 572.11. 3 See Diecke v. Lumber Supply, 260 Iowa 470, 149 N.W.2d 822 (1967). In Diecke, we answered the identical question with reference to the ninety-day exception. We held "that in determining the 'balance due' at time of service of such notice, any amounts needed to finish the work would be deducted from the balance due [on the contract]." Diecke, 260 Iowa at 477, 149 N.W.2d at 826. The district court relied on this analogous ruling in its interpretation of the balance due language in section 572.14(2) and its resulting denial of Carson's lien.

Carson vigorously contends the district court's reliance on Diecke was in error. She notes that liens filed by the subcontractors in Diecke were untimely whereas Carson filed within the required period. But we think it is appropriate to analyze the "balance due" language of the two sections together. The fact that a subcontractor does or does not file a timely lien on an owner-occupied dwelling should not control the meaning of the term "balance due." A rubric of statutory construction dictates that, when identical language is used in several places in a statute, the phrase is usually given the same meaning throughout. B.A.A. v. University of Iowa Hosp., 421 N.W.2d 118, 125 (Iowa 1988); Iowa Code § 4.6(4) (court may consider "former statutory provisions, including laws upon the same or similar subjects").

Another section of chapter 572 reinforces this conclusion. Subsection 16, "rule of construction," provides that "in the case of an owner-occupied dwelling, nothing in this chapter shall be construed to require the owner to pay a greater amount ... than is provided in the owner's contract with the principal contractor...." Iowa Code § 572.16 (emphasis added).

Performance by the principal contractor, then, is crucial to the lien rights of a subcontractor. Before a subcontractor can recover on a mechanic's lien, the subcontractor must prove the homeowner is indebted to the principal contractor for the work in which the subcontractor's materials were used. See Kawneer Mfg. Co. v. Renfro & Lewis, 186 Iowa 1344, 1347-48, 173 N.W. 899, 900 (1919); see also Central Iowa Grading v. UDE Corp., 392 N.W.2d 857, 859 (Iowa App.1986) (citing Kawneer, 186 Iowa at 1347-48, 173 N.W. at 900).

We have long recognized that, where a contractor abandons a project and the owner must pay to complete it, the owner is entitled to pay the costs of completion out of the balance remaining on the contract. L.A. Page & Son v. Grant, 127 Iowa 249, 257, 103 N.W. 124, 127 (1905). Subcontractors' liens are only valid to the extent of the contract price not paid after deduction of the owner's completion costs. Id. Computation of the balance due to subcontractors requires (1) deducting payments made by the owner from the contract price, (2) adding extras provided by the contractor, (3) then deducting the owner's damages from omissions and deficiencies in the contractor's work. See Wickham v. Monroe, 89 Iowa 666, 669-70, 57 N.W. 434, 435 (1894).

A final reason for applying the Diecke holding to section 572.14(2) is its wording. When the legislature enacted the "balance due" limitation for 572.14(2), it chose to adopt the exact language construed in our Diecke holding.

We conclude...

To continue reading

Request your trial
30 cases
  • Haskenhoff v. Homeland Energy Solutions, LLC
    • United States
    • Iowa Supreme Court
    • 23 Junio 2017
    ...times in the same statute, it should have the same meaning. State v. Paye , 866 N.W.2d 1, 7 (Iowa 2015) ; accord ≠ Carson v. Roediger , 513 N.W.2d 713, 716 (Iowa 1994) ; State v. Johnson , 604 N.W.2d 669, 672 (Iowa Ct. App. 1999). This familiar rule has been applied repeatedly in the contex......
  • Service Employees International Union, Local 199 v. Iowa Board of Regents
    • United States
    • Iowa Supreme Court
    • 17 Mayo 2019
    ...the same statute, it should have the same meaning."See, e.g. , State v. Paye , 865 N.W.2d 1, 7 (Iowa 2015) ; see also Carson v. Roediger , 513 N.W.2d 713, 716 (Iowa 1994) (same).The use of the term "negotiations" elsewhere in Iowa Code chapter 20 demonstrates a legislative intent to allow a......
  • In re Interest of C.F.-H.
    • United States
    • Iowa Supreme Court
    • 16 Diciembre 2016
    ...to construe a term consistently throughout a statute. See, e.g. , State v. Paye , 865 N.W.2d 1, 7 (Iowa 2015) ; Carson v. Roediger , 513 N.W.2d 713, 716 (Iowa 1994) ; B.A.A. v. Chief Med. Officer , 421 N.W.2d 118, 125 (Iowa 1988) ; see also In re Lucinda R ., 85 A.D.3d 78, 924 N.Y.S.2d 403,......
  • Flynn Builders, L.C. v. Lande
    • United States
    • Iowa Supreme Court
    • 1 Junio 2012
    ...for further review, which we granted.II. Standard of Review. Actions to enforce mechanic's liens are in equity. Carson v. Roediger, 513 N.W.2d 713, 715 (Iowa 1994). Our review is therefore de novo. Id. In our de novo review, the district court's fact findings are given weight, but we are no......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT