Corbin-Dykes Elec. Co. v. Burr

Decision Date31 August 1972
Docket NumberCORBIN-DYKES,CA-CIV,No. 1,1
Citation500 P.2d 632,18 Ariz.App. 101
PartiesELECTRIC COMPANY, an Arizona corporation, Appellant, v. Walter BURR and Jane Doe Burr, his wife, dba Burr & Sons Construction Co., Appellees. 1677.
CourtArizona Court of Appeals

Trew & Woodford by R. R. Woodford, Phoenix, for appellant.

Ash & Reeb by Gary B. Larson, Mesa, for appellees.

EUBANK, Judge.

This appeal from a summary judgment questions whether a contractual relationship results from a situation where a subcontractor submits a bid for the electrical subcontract to the general contractor, who in turn includes it within his bid for the general construction contract which is subsequently awarded the general contractor.

The facts are as follows:

General Motors Corporation requested bids from general contractors to construct the central air-conditioning plant at its proving grounds located east of the city of Mesa. The defendant-appellee Walter Burr, et al., a general contractor, hereafter 'Burr', was interested in obtaining the contract and as a result received bids for the electrical subcontract solicited by Lowry & Sorensen, the consulting engineers on the project. One of the bids received by Burr was from the plaintiff-appellant Corbin-Dykes Electric Company, hereafter 'Corbin-Dykes'. Burr incorporated Corbin-Dykes' subcontract bid, which was the low bid, into his general contract bid and submitted it to General Motors Corporation. All bids were rejected by General Motors because they exceeded the cost estimate; and the project was rebid on October 14, 1969. The second bid submitted by Burr also included the Corbin-Dykes subcontract bid; however, prior to submitting the second bid, Burr had received another bid from Sands Electric Company which matched the Corbin-Dykes bid but also provided that, in the event Sands could work the proposed project in conjunction with its current project at the proving grounds, they would reduce their subcontract bid by $4000. When the second round of bids was opened, Burr was awarded the general contract, and since Sands Electric's other project at the proving grounds was not yet completed, Burr accepted Sands' bid for the electric subcontract as the low bid.

Corbin-Dykes objected to this selection of Sands as the subcontractor and sued Burr for breach of their alleged subcontract. The subcontract was denied by Burr in his answer; and following several depositions, Burr moved for summary judgment, which was granted. Corbin-Dykes appeals from that summary judgment.

Two questions are raised by Corbin-Dykes for review. First, whether taking all inferences in a light most favorable to Corbin-Dykes the trial court was justified in granting the summary judgment to Burr; Second, whether there remains a genuine issue as to a material fact which would preclude granting the summary judgment.

Both of these questions are based upon Corbin-Dykes' contention that a custom and usage exists in the trade to the effect that a subcontractor who is listed in the general contractor's bid will receive the subcontract, if the general contractor is successful and is awarded the general contract. This custom and usage would be introduced at the trial, according to Corbin-Dykes, in order to prove the contract existed between it and Burr, or in other words to prove the acceptance by Burr of Corbin-Dykes' bid offer. The record shows that there was no other evidence of acceptance by Burr of the subcontract offer.

In Arizona the law is clear that Corbin-Dykes' bid to Burr was nothing more than an offer to perform the subcontract under specified terms, and that it did not ripen into a contract until it was voluntarily accepted by Burr. Universal Construction Co. v. Arizona Consolidated Masonry & Plastering Contractors Ass'n., 93 Ariz. 4, 377 P.2d 1017 (1963). The law and its related problems are well stated in the 53 Virginia L.Rev. 1720 (1967), Law note: Another Look at Construction Bidding and Contracts at Formation, which states:

'From the time a general contractor (general) receives bids from subcontractors (subs) until he formally accepts one of those bids, the parties are not adequately protected by the common law. Although they are forced by the commercial context to rely upon each other during this period, at common law their relationship cannot be contractual until the general responds with the requisite promise of acceptance. To some extent the promissory estoppel doctrine has alleviated the general's problems by binding the sub to perform according to the terms of his bid. But this protection is one-sided, and despite the view of some courts that promissory estoppel is a panacea, it appears that in confining the scope of protection to the general, the doctrine in fact raises serious problems.' (53 Virginia L.Rev. at 1720).

The...

To continue reading

Request your trial
12 cases
  • Mitchell v. Siqueiros
    • United States
    • Idaho Supreme Court
    • July 5, 1978
    ...Const. Co. v. Arizona Consolidated Masonry & Plastering Contractors Ass'n, 93 Ariz. 4, 377 P.2d 1017 (1963); Corbin-Dykes Electric Co. v. Burr, 18 Ariz.App. 101, 500 P.2d 632 (1972); Southern Cal. Acoustics Co., Inc. v. C. V. Holder, Inc., 71 Cal.2d 719, 79 Cal.Rptr. 319, 456 P.2d 975 (1969......
  • Johnson v. Earnhardt's Gilbert Dodge, Inc.
    • United States
    • Arizona Supreme Court
    • April 25, 2006
    ...165 Ariz. at 474, 799 P.2d at 815. Objective evidence includes written and spoken words as well as acts. Corbin-Dykes Elec. Co. v. Burr, 18 Ariz.App. 101, 103, 500 P.2d 632, 634 (1972) (holding that the manifestation of mutual assent "is determined by the words used and the other manifestat......
  • ELECTRO LAB OF AIKEN v. SHARP CONST.
    • United States
    • South Carolina Court of Appeals
    • February 2, 2004
    ...Inc., 330 N.W.2d 693, 696 (Minn.1983); Mitchell v. Siqueiros, 99 Idaho 396, 582 P.2d 1074, 1077 (1978); Corbin Dykes Elec. Co. v. Burr, 18 Ariz.App. 101, 500 P.2d 632, 634 (1972); K.L. House Constr. Co. v. Watson, 84 N.M. 783, 508 P.2d 592, 593 (N.M. 1973); Neptune Gunite Co. v. Monroe Ente......
  • Finney Co., Inc. v. Monarch Const. Co., Inc.
    • United States
    • United States State Supreme Court — District of Kentucky
    • June 14, 1984
    ...582 P.2d 1074 (1978); K.L. House Construction Company, Inc. v. Watson, 84 N.M. 783, 508 P.2d 592 (1973); Corbin-Dykes Electric Company v. Burr, 18 Ariz.App. 101, 500 P.2d 632 (1972); Southern California Acoustics Company, Inc. v. C.V. Holder, Inc., 71 Cal.2d 719, 79 Cal.Rptr. 319, 456 P.2d ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT