Cosmopolitan Engineering v. Ondeo Degremont

Decision Date09 August 2005
Docket NumberNo. 31771-1-II.,31771-1-II.
Citation117 P.3d 1147,128 Wn. App. 885
CourtWashington Supreme Court
PartiesCOSMOPOLITAN ENGINEERING GROUP, INC., Appellants, v. ONDEO DEGREMONT, INC., a Virginia corporation; and National Fire Insurance Company/Hartford, a foreign corporation, Respondents.

Alan R. Merkle, Margarita V. Latsinova, Christina L. Haring, Stoel Rives LLP, Seattle, WA, for Respondents.

Sandra Jean Rovai, Attorney at Law, Tacoma, WA, for Appellant.

PART PUBLISHED OPINION

VAN DEREN, J.

¶ 1 Cosmopolitan Engineering Group, Inc., (Cosmopolitan) appeals the trial court's (1) refusal to award attorney fees against both Ondeo Degremont, Inc. (Ondeo) and its surety bond under RCW 18.27.040(6); (2) denial of prejudgment interest on the jury's damages award to Cosmopolitan for its unpaid fees by Ondeo; and (3) summary dismissal of its materialmen's lien claim. We affirm the trial court's denial of prejudgment interest and its summary dismissal of Cosmopolitan's lien claim, but we reverse and remand for entry of judgment for attorney fees against Ondeo under RCW 18.27.040(6).

FACTS
A. Wastewater Development Plans

¶ 2 Miller Brewing Company (Miller)1 sought to develop its brewery plant in Tumwater, Washington, into a wastewater treatment plant and also investigated the possibility of a remote facility to reuse wastewater in Olympia, Washington. Miller eventually cancelled both development plans.

¶ 3 Ondeo was Miller's engineering contractor for the wastewater treatment plant. It is undisputed that in 2001, Cosmopolitan was Ondeo's subcontractor for the wastewater treatment plant and that Cosmopolitan was responsible for engineering design and local permitting. In September 2001, Cosmopolitan contracted directly with Miller to investigate the possibility of a remote reuse wastewater facility in Olympia (also called the Briggs location).

¶ 4 Then in July 2002, Ondeo and Cosmopolitan together developed a proposal at Miller's request to explore the feasibility of a remote facility to reuse wastewater in Olympia. Although it is undisputed that Ondeo and Cosmopolitan jointly submitted this proposal, the parties dispute the proposal's contents and whether Ondeo terminated its relationship with Cosmopolitan after this proposal.

¶ 5 In December 2002 and January 2003, Cosmopolitan attended two meetings with officials from the City of Tumwater regarding the development of the wastewater treatment plant. Cosmopolitan later invoiced Ondeo for its professional services related to these meetings. Ondeo disputes that Cosmopolitan had a contractual relationship with them at this time, arguing that Cosmopolitan acted solely at Miller's request.

¶ 6 On January 8, 2003, Miller publicly announced its plans to sell its brewery plant in Tumwater and cancelled all its prior development plans. On March 28, 2003, Cosmopolitan filed a materialmen's lien under chapter 60.04 RCW against Miller's property for its unpaid services, including its 2001 work with Ondeo and its December 2002 and January 2003 meetings with the City of Tumwater. Cosmopolitan later amended its lien claim to $100,420 for unpaid services. Cosmopolitan's lien claim identified Ondeo as an indebted party and Miller as the property owner.

¶ 7 In July 2003, Cosmopolitan filed a complaint to foreclose on its lien. Cosmopolitan's complaint named both Ondeo and its contractor's bond under the Contractor Registration Act (CRA), chapter 18.27 RCW.

B. Summary Judgment and Jury Trial on Contract and Equitable Theories

¶ 8 Miller and Ondeo moved for summary dismissal of Cosmopolitan's lien claim. The trial court granted Miller's motion and dismissed the lien claim because it found that Miller had paid Cosmopolitan for the direct contract they had. After a request for clarification, the court stated that it was dismissing the lien claim against Ondeo because Cosmopolitan untimely filed the claim on the alleged work it performed for Ondeo.

¶ 9 But the court allowed Cosmopolitan's breach of contract and its equitable claims against Ondeo to go forward, finding that the complex facts relating to their professional relationship made summary judgment inappropriate.

¶ 10 Neither party objected to the court's jury instructions directing the jury to consider Cosmopolitan's breach of contract theory and its equitable theories of promissory estoppel and unjust enrichment/quantum meruit. The jury instructions informed the jury that Cosmopolitan's contract and equitable theories of recovery were mutually exclusive. Although the court expressly asked the parties at the jury instruction conference if a special verdict form or interrogatory were required, Cosmopolitan proposed, and the court accepted, a general verdict form that specified only the jury's damages award but did not identify the underlying legal or equitable theory supporting a verdict for damages.

¶ 11 A jury found for Cosmopolitan and awarded the company all its claimed unpaid fees for a total of $100,420.

C. Post-trial Motions

¶ 12 Miller and Ondeo moved for attorney fees, based in part on their assertion that they defended a frivolous lien claim. Cosmopolitan also moved for attorney fees and costs under the prevailing party fee shifting provision of RCW 18.27.040(6). Cosmopolitan also requested prejudgment interest based on the jury's award.

¶ 13 The court awarded Miller and Ondeo attorney fees for dismissal of the lien claim, although for an amount less than the parties' requested. The court awarded Cosmopolitan attorney fees against Ondeo's bond under RCW 18.27.040(6) for $3,000. Although the court found Cosmopolitan's interpretation of RCW 18.27.040(6)'s fee shifting provision persuasive, it ultimately sided with Ondeo's argument that RCW 18.27.040(6) was designed to limit awards to the contractor's bond without imposing an obligation on the contractor. The court also denied Cosmopolitan's request for prejudgment interest, ruling that given the general verdict form, it could not precisely determine how the jury determined its award.

ANALYSIS

I. RCW 18.27.040(6)

¶ 14 Cosmopolitan argues that the trial court misinterpreted RCW 18.27.040(6) by awarding attorney fees solely against Ondeo's bond, but not against Ondeo. Cosmopolitan emphasizes that the trial court erroneously based its ruling on Subcontractors & Suppliers Collection Servs. v. McConnachie, 106 Wash.App. 738, 741, 24 P.3d 1112 (2001). Ondeo argues on appeal that Cosmopolitan has waived this argument because of its failure to propose a special verdict form specifying a breach of contract claim. Ondeo also asserts that Cosmopolitan's interpretation of RCW 18.27.040(6), to require an attorney fees award against both a contractor and its bond, is overbroad.

¶ 15 We review the trial court's ruling de novo because statutory interpretation is a matter of law. State v. Beaver, 148 Wash.2d 338, 344, 60 P.3d 586 (2002). "The court's fundamental objective is to ascertain and carry out the legislature's intent, and if the statute's meaning is plain on its face, then the court must give effect to that plain meaning as an expression of legislative intent." State ex rel. Citizens Against Tolls v. Murphy, 151 Wash.2d 226, 242, 88 P.3d 375 (2004). We also examine the statutory scheme. Murphy, 151 Wash.2d at 242, 88 P.3d 375.

¶ 16 The CRA "is a comprehensive scheme governing contractors" that "defines a contractor, creates categories of exemptions, regulates business practices and requires that contractors be registered." Int'l Commercial Collectors, Inc. v. Carver, 99 Wash.2d 302, 304, 661 P.2d 976 (1983). RCW 18.27.140 expressly states the CRA's purpose is to "afford protection to the public including all persons, firms, and corporations furnishing labor, materials, or equipment to a contractor from unreliable, fraudulent, financially irresponsible, or incompetent contractors." (Emphasis added).

¶ 17 "A contractor in substantial compliance with the CRA may sue in contract or under alternative theories such as quantum meruit." Bort v. Parker, 110 Wash.App. 561, 571, 42 P.3d 980 (2002) (relying on Murphy v. Campbell Inv. Co., 79 Wash.2d 417, 422-23, 486 P.2d 1080 (1971)) (emphasis added); see also Williamson, Inc. v. Calibre Homes, Inc., 147 Wash.2d 394, 400, 54 P.3d 1186 (2002) (reaffirming Murphy and the application of the substantial compliance doctrine to the CRA).

¶ 18 The CRA requires all contractors to file a surety bond and obtain public liability and property damage insurance. RCW 18.27 .040, .050. A party may sue a contractor and its bond for breach of contract or equitable relief. RCW 18.27.040,.080.

¶ 19 In 2001, the legislature added a fee shifting provision for prevailing parties that stated:

The prevailing party in an action filed under this section against the contractor and contractor's bond or deposit, for breach of contract by a party to a construction contract, is entitled to costs, interest, and reasonable attorneys' fees. The surety upon the bond is not liable in an aggregate amount in excess of the amount named in the bond nor for any monetary penalty assessed pursuant to this chapter for an infraction.

RCW 18.27.040(6)2 (emphasis added).

¶ 20 Given the foregoing case law, the CRA's purpose, and RCW 18.27.040(6)'s plain language, we hold that as a matter of law a prevailing party under this provision is entitled to attorney fees against both the opposing contractor and its bond. Thus, the trial court erred in ruling that RCW 18.27.040(6) limits a prevailing party's attorney fees, interest, and costs to the other contractor's bond only.

¶ 21 Cosmopolitan contends that interpreting RCW 18.27.040(6) to apply to both a contractor and its bond is consistent with the CRA's purpose to protect plaintiffs from negligent contractors. We agree. As aptly stated in Cosmopolitan's appellate brief, "The circumstances in which the bond would be sufficient to pay both the contractor's liability and the costs, interest, and attorneys' fees...

To continue reading

Request your trial
3 cases
  • Cosmopolitan Eng. Group v. Ondeo Degremont
    • United States
    • Washington Supreme Court
    • December 28, 2006
    ...surety bond. The Court of Appeals decided the case in a partially published opinion. Cosmopolitan Eng'g Group, Inc. v. Ondeo Degremont, Inc., 128 Wash.App. 885, 117 P.3d 1147 (2005). In the published portion, the Court of Appeals held, "as a matter of law a prevailing party under this provi......
  • Brotherton v. Kralman Steel Structures, Inc.
    • United States
    • Washington Court of Appeals
    • December 29, 2011
    ...contractor and its bond,” based on, among other reasons, the plain language of the provision. Cosmopolitan Eng'g Group, Inc. v. Ondeo Degremont, Inc., 128 Wash.App. 885, 892, 117 P.3d 1147 (2005), rev'd, 159 Wash.2d 292, 149 P.3d 666. ¶ 19 The Supreme Court accepted review and reversed. The......
  • Cosmopolitan Engineering Group, Inc. v. Ondeo Degremont, Inc.
    • United States
    • Washington Supreme Court
    • April 4, 2006

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT