D.A. Davis Const. Co., Inc. v. Palmetto Properties, Inc.

Decision Date20 March 1984
Docket NumberNo. 22084,22084
Citation315 S.E.2d 370,281 S.C. 415
CourtSouth Carolina Supreme Court
PartiesD.A. DAVIS CONSTRUCTION COMPANY, INC., Appellant, v. PALMETTO PROPERTIES, INC., and Schafer Distributing Company, Inc., Respondents. . Heard

Allen L. Ray, Conway, for appellant.

George M. Hearn, Jr., of Stevens, Stevens, Thomas, Hearn & Hearn, Loris, for respondents.

GREGORY, Justice:

This is an action to foreclose a mechanic's lien. Appellant D.A. Davis Construction Company, Inc. (Davis) appeals the order of the circuit court denying its request for payment for cost overruns; granting offsets for deficient wall panels and lost rentals requested by respondent Palmetto Properties, Inc.; and granting Davis an award of attorney's fees in the amount of fifteen percent of the recovery. We affirm.

This is an action at law, Wallace Concrete Pipe Co. v. Downs, 272 S.C. 335, 251 S.E.2d 759 (1979), tried without a jury; therefore, the findings of fact of the judge will not be disturbed upon appeal unless found to be without evidence which reasonably supports the judge's findings. Townes Associates, Ltd. v. City of Greenville, 266 S.C. 81, 221 S.E.2d 773 (1976). This is so even if the judge's findings are made with a reference. Id. This matter was referred to the Master-in-Equity for Horry County. While the Master and the circuit judge disagreed on all but one issue, our review of the findings of the judge is limited to whether there is any evidence which may reasonably support the factual conclusions of the circuit judge.

In December 1977, Davis submitted a bid to Palmetto Properties for the construction of a warehouse and office facility in Myrtle Beach. The Bid Form stated Davis would substantially complete 1 the warehouse no later than May 15, 1978, and the office facility no later than June 15, 1978. The bid without the bonus and liquidated damages provisions was for the guaranteed maximum cost of $293,850.00.

Davis submitted requests for payment during the course of construction and received payments totalling $261,049.50. After completion of the project, Davis submitted a final request for payment in the amount of $53,960.04, bringing the total cost of the project to $315,009.54. Palmetto Properties did not honor the request. Davis then commenced this action.

On the issue of cost overruns, the Master found Davis was entitled to payment in the amount of $21,159.50. The circuit judge disagreed, finding the Bid Form provided for a guaranteed maximum cost, and absent any agreement between the parties, with respect to extras, Davis was obligated to construct the facility for the sum of $293,850.00. We agree with the circuit judge.

The Bid Form was executed in anticipation that a later contract containing a stipulated sum would be negotiated. A later contract was not executed; therefore, the Bid Form is the only agreement between the parties. The Bid Form provided:

Bid to negotiate a Stipulated Sum Agreement upon the completion of all project design revisions by the Architect; such Stipulated Sum, Contract Sum, shall not exceed the Guaranteed Maximum Cost hereinbefore indicated ($293,850.00). (Emphasis added.)

In construing a contract, it is axiomatic that the main concern of the court is to ascertain and give effect to the intention of the parties. It is the court's duty to enforce the contract regardless of its wisdom or folly or apparent unreasonableness. Blakeley v. Rabon, 266 S.C. 68, 221 S.E.2d 767 (1976).

Davis clearly contracted with Palmetto Properties to construct a warehouse and office facility in Myrtle Beach for a guaranteed maximum amount of $293,850.00. Absent an agreement with Palmetto Properties with respect to extras, Davis can only recover the cost of construction up to $293,850.00.

Next, Davis contends Palmetto Properties is not entitled to offsets for deficient concrete wall panels or lost rental. We disagree.

The evidence established that unacceptable concrete wall panels were put up; they were recoated rather than replaced; they would have to be recoated every five years at a cost of $2,250.00 per coating; the average life of the buildings is twenty years; the total cost of maintaining the concrete wall panels in acceptable form would cost $6,750.00. Both the Master and the circuit judge allowed an offset for that amount. We find the evidence amply supports their finding.

Palmetto Properties...

To continue reading

Request your trial
32 cases
  • Ecclesiastes Prod. Ministries v. Outparcel
    • United States
    • South Carolina Court of Appeals
    • June 14, 2007
    ...Servs., Inc. v. Middleton, 349 S.C. 77, 80-81, 562 S.E.2d 482, 484-85 (Ct. App.2002); accord D.A. Davis Constr. Co., Inc. v. Palmetto Props., Inc., 281 S.C. 415, 418, 315 S.E.2d 370, 372 (1984); Williams v. Teran, Inc., 266 S.C. 55, 59, 221 S.E.2d 526, 528 (1976); RentCo., a Div. of Fruehau......
  • Perini Corp. v. Greate Bay Hotel & Casino, Inc.
    • United States
    • New Jersey Supreme Court
    • August 6, 1992
    ...damages, lost profits can be assessed up to the date of substantial completion. For example, in D.A. Davis Construction v. Palmetto Properties, Inc., 281 S.C. 415, 315 S.E.2d 370 (1984), the court awarded three months' lost rental income to the owner for the builder's failure to substantial......
  • Ward v. West Oil Co., Inc.
    • United States
    • South Carolina Court of Appeals
    • May 12, 2008
    ...497, 649 S.E.2d at 501; S. Atl. Fin. Servs., 349 S.C. at 80-81, 562 S.E.2d at 484-85; accord D.A. Davis Constr. Co., Inc. v. Palmetto Props., Inc., 281 S.C. 415, 418, 315 S.E.2d 370, 372 (1984); Williams v. Teran, Inc., 266 S.C. 55, 59, 221 S.E.2d 526, 528 (1976); RentCo., a Div. of Fruehau......
  • Vill. W. Horizontal Prop. Regime v. Arata
    • United States
    • South Carolina Court of Appeals
    • January 11, 2007
    ... ... Investors Title ... Ins. Co., 370 S.C. 578, ___, 635 S.E.2d 649, 654-55 (Ct ... at 434, 629 S.E.2d at 648; BPS, Inc. v ... Worthy, 362 S.C. 319, 325, 608 ... D.A ... Davis Constr. Co., Inc. v. Palmetto Props., Inc., 281 ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT