Dickson County v. Bomar Const. Co., Inc.

Citation935 S.W.2d 413
PartiesDICKSON COUNTY, Tennessee, Plaintiff/Appellee, v. BOMAR CONSTRUCTION COMPANY, INC., and United States Fidelity and Guaranty Company, Defendants/Appellants.
Decision Date11 July 1996
CourtTennessee Court of Appeals

Don Smith, Nashville, for Defendants/Appellants.

Allan Kerns, Dickson, for Plaintiff/Appellee.

OPINION

TODD, Presiding Judge (M.S.).

The Defendant, Bomar Construction Company, Inc., (hereafter Bomar) has presented this appeal under TRAP Rule 9 from an interlocutory order of the Trial Court overruling Bomar's motion to dismiss its claim to arbitration as required by the contract of the parties.

The sole issue on appeal is whether Bomar is entitled to dismissal.

The complaint asserts that, on May 24, 1993, the Plaintiff County executed a contract requiring Bomar to construct a jail for the County, that Bomar failed to perform said contract as agreed, and that the County has suffered $500,000 damage thereby.

Bomar filed a "Motion to Dismiss" supported by an affidavit and memorandum of law. The affidavit identifies and exhibits a copy of the contract between the parties, and a "Demand for Arbitration."

The Trial Judge filed an "Opinion and Order" stating:

OPINION AND ORDER

This matter is before the court on a Motion to Dismiss the Complaint in this cause, because the parties entered into a contract on May 24, 1993, which provides for arbitration of disputes.

By statute and an abundance of case law in this state, arbitration clauses of such contracts have been upheld and enforced, and such arbitration clauses are not against public policy.

However, under this particular contract, the court must give interpretation to the following paragraph:

7.6 RIGHTS AND REMEDIES

7.6.1 The duties and obligations imposed by the Contract documents and the rights and remedies available thereunder Shall be in addition to and not a limitation of any duties, Obligations, rights and remedies otherwise imposed or available by law.

The court is of the opinion that this paragraph says the parties have the rights and remedies imposed by available law and in addition thereto, but not a limitation of, the rights and remedies imposed by law, they have the rights and remedies available under this contract.

Therefore, this paragraph actually gives the parties an option to proceed under the contract or by remedies available under the law.

Therefore, for reasons hereinabove set forth, the Order to Dismiss is overruled.

The arbitration clause of the contract reads as follows:

4.5.1 Controversies and Claims Subject to Arbitration.

Any controversy or Claim arising out of or related to the Contract, or the breach thereof, shall be settled by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association, and judgment upon the reward rendered by the arbitrator or arbitrators may be entered in any court having jurisdiction thereof, except controversies or Claims relating to aesthetic effect and except those waived as provided for in Subparagraph 4.3.5. Such controversies or Claims upon which the Architect has given notice and rendered a decision as provided in Subparagraph 4.4.4 shall be subject to arbitration upon written demand of either party. Arbitration may be commenced when 45 days have passed after a Claim has been referred to the Architect as provided in Paragraph 4.3 and no decision has been rendered.

As indicated above, the Trial Judge held that Paragraph 7.6.1, quoted in his order conflicted with and rendered ineffective the compulsory nature of Paragraph 7.9.1, quoted above, thereby changing the word, "shall" to the words "may, if agreeable to the parties."

Defendants cite Coble Systems, Inc. v. Gifford Co., Tenn.App.1981, 627 S.W.2d 359 wherein a truck lessor sued the lessee for damage to the leased truck while in lessee's possession. On the face of the lease, the renter's signature appeared beside a paragraph stating:

Renter to pay total cost of loss or damages to vehicle (See Par. 9). Renter sign here ____________.

Following the above provision of the lease was a paragraph stating:

Customer's limits of liability are: $1,000.00 straight trucks, $2,000.00 each tractor, trailer or refrig. Unit (see Par. 9). Renter sign here N.A. .

The renter signed again at the conclusion of the agreement.

On the reverse side of the agreement were paragraph 8, repeating the...

To continue reading

Request your trial
2 cases
  • Dunn Indus. Group v. City of Sugar Creek
    • United States
    • Missouri Supreme Court
    • August 26, 2003
    ...or remedies that do not nullify or are not inconsistent with their obligation to arbitrate. See, e.g., Dickson County v. Bomar Constr. Co., 935 S.W.2d 413, 415 (Tenn.Ct. App.1996). Examples of such unspecified rights or remedies include the right to confirm an arbitration award under 9 U.S.......
  • Meier v. Huntington Ridge Townhouse Homeowners Association, Inc., No. M2007-02511-COA-R3-CV (Tenn. App. 10/23/2008), M2007-02511-COA-R3-CV.
    • United States
    • Tennessee Court of Appeals
    • October 23, 2008
    ...terms of the Declaration of Covenants in context and to construe them such as to avoid a conflict. See Dickson County v. BomarConstr. Co., Inc., 935 S.W.2d 413 (Tenn. Ct. App. 1996). Mr. Warren explained at length that the floor trusses are a part of the bearing wall system and that, while ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT