Doane v. Pine State Volkswagen, Inc.

Decision Date13 September 1977
Citation377 A.2d 481
PartiesRoger DOANE v. PINE STATE VOLKSWAGEN, INC.
CourtMaine Supreme Court

Zendzian & Anderson by Peter Avery Anderson, Bangor, for plaintiff.

Rudman, Rudman & Carter, Richard J. Relyea, Paul L. Rudman, Bangor, for defendant.

Before DUFRESNE, C. J., and POMEROY, WERNICK, ARCHIBALD, DELAHANTY and GODFREY, JJ.

POMEROY, Justice.

A Penobscot County Superior Court jury reached a verdict for the plaintiff in this breach of contract action. A judgment for the plaintiff was entered. The defendant seasonably appealed to the Law Court.

We deny the appeal.

The appellee was employed by the appellant as a car salesman from May 1972 until February 1974. In early 1973 the appellee and the appellant, through its general manager Mr. Doyle, entered into an oral agreement for the construction of a drag racing car. The terms of the agreement, according to the appellee, were as follows. The appellant would purchase all needed parts for construction of the car. The appellee would do all of the assembly work and would drive the car upon completion. The appellant would use the car to advertise its business and would receive all winnings from racing the car until its cost had been recovered. The appellee would receive all winnings after the appellant's cost had been recovered, and title to the car would be conveyed to the appellee on January 1, 1974.

During 1973 it became apparent that the car would cost about twice the original estimate and there would be a delay in completing the car. After being informed of this Mr. Doyle told the appellee to continue with the project. Sometime in the fall of 1973, the appellant refused to give the appellee any more money to purchase parts. For the remainder of 1973 and until he was discharged in February 1974, the appellee tried to persuade the appellant to purchase the needed parts. The appellant answered by telling the appellee that he could have the car but only after reimbursing the appellant for its costs. The appellee then brought this action for breach of contract to recover the fair market value of the drag racing car, if it had been complete. Judgment was entered for the appellee in the amount of $12,000.00. 1

In his complaint the appellee alleged that the appellant breached the oral contract "by attempting to hold Plaintiff (appellee) liable for the materials used to construct said car and by threatening to sell said car." The appellant in its answer moved to dismiss the complaint for failure to state a claim upon which relief can be granted. M.R.Civ.P., Rule 12(b)(6). The motion was denied in the pretrial order. The appellant contends that the presiding justice erred in denying its motion because the complaint fails to apprise it of the manner in which it allegedly breached the contract.

"It is not necessary to state all the facts necessary to constitute a good cause of action. The United States Supreme Court has gone so far as to say that the motion should not be granted 'unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.' Conley v. Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 102, 2 L.Ed.2d 80 (1957). . . . What is intended, as demonstrated by the cases cited, is that if fair notice of the claim is given, the complaint is not fatally defective because of the failure to allege in nonconclusory form every fact essential to recovery." Field, McKusick, Wroth, Maine Civil Practice, § 12.11.

We conclude that the appellee's complaint gave the appellant "fair notice of the claim." We come to this conclusion for two reasons. First, the appellant's attempt to hold the appellee liable for the costs of construction was a breach of the contract as described in the appellee's testimony. Since the appellant promised to pay for the cost of all needed parts, its attempt to hold the appellee liable was a breach. Second, even if the attempt to hold the appellee liable was not itself a breach, the complaint should survive a Rule 12(b)(6) motion because the complaint puts the appellant on notice that its conduct with regard to payment of the cost of construction was considered a breach. Although the actual breach may have been the refusal to provide further funds rather than "attempting to hold Plaintiff liable ", we conclude that the complaint was specific enough to provide "fair notice " to the appellant. 2 Therefore, the denial of appellant's motion to dismiss was not error.

During the trial, the appellant moved for a directed verdict on the ground of failure of consideration. See M.R.Civ.P., Rule 50(a). Following the entry of judgment, the appellant moved for a judgment notwithstanding the verdict on the same ground. 3 See M.R.Civ.P., Rule 50(b). Both motions were denied. The appellant contends that the presiding justice erred in denying its motions because the agreement called for completion of the car in time to race the car during 1973, which the appellant claims was impossible at the time it refused to continue funding the car.

When reviewing the denial of a motion for a directed verdict or a judgment notwithstanding the verdict, this court must view the evidence in a light most favorable to the nonmoving party. Boetsch v. Rockland Jaycees, Me., 288 A.2d 102 (1972); Manchester v. Dugan, Me., 247 A.2d 827 (1968). We must accept the appellee's version of the contract terms, as the jury apparently did.

In exchange for planning and building the car, the appellee was to receive money from the appellant to purchase the parts needed for the car. The appellee kept his part of the bargain. The appellant breached the contract first when it refused to provide more money or parts to the appellee. There was no failure of consideration prior to the appellant's breach because, according to the appellee, the parties had not set a time limit for completion of the car.

Finally, the appellant contends that the presiding justice erred in denying its motion for a new trial on the grounds that the damages were excessive and without evidentiary support. When reviewing the denial of a motion for a new trial we must again view the evidence in a light most favorable to the nonmoving party. Compare Symonds v. Free Street Corp., 135 Me. 501, 200 A. 801 (1938) with Boetsch v. Rockland Jaycees, supra.

The appellee, who had a limited amount of experience in the construction...

To continue reading

Request your trial
13 cases
  • Nadeau v. State
    • United States
    • Maine Supreme Court
    • December 1, 1978
    ...doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief." Doane v. Pine State Volkswagen, Inc., Me., 377 A.2d 481, 484 (1977). Otherwise stated, if a complaint alleges either "the necessary elements of a cause of action or facts which wou......
  • Davis v. Rodriguez
    • United States
    • Maine Superior Court
    • July 16, 2010
    ...on the basis of the complaint alone that "the plaintiff can prove no set of facts in support of his claim which would entitle him to relief." Id. invocation of the MLLA's exclusivity provision is appropriately raised as an affirmative defense, which would more appropriately be determined in......
  • Merrill Trust Co. v. State
    • United States
    • Maine Supreme Court
    • July 21, 1980
    ...129 Me. 488, 150 A. 538 (1930); Gottesman & Co. v. Portland Terminal Co., 139 Me. 90, 27 A.2d 394 (1942); Doane v. Pine State Volkswagen, Inc., Me., 377 A.2d 481 (1977). The triers of the facts, here the presiding Justice, may act upon probable and inferential as well as direct and positive......
  • Gagne v. Cianbro Corp.
    • United States
    • Maine Supreme Court
    • July 13, 1981
    ...in favor of the pleader. See, e. g., Richards v. Ellis, Me., 233 A.2d 37, 38 (1967). As we observed in Doane v. Pine State Volkswagen, Inc., Me., 377 A.2d 481, 484 (1977), the United States Supreme Court has emphasized that a Rule 12(b)(6) motion should not be granted "unless it appears bey......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT