Donco 3 Constr., LLC v. Conway Contracting, Inc.
Decision Date | 14 June 2022 |
Docket Number | SD 36897 |
Citation | 646 S.W.3d 449 |
Parties | DONCO 3 CONSTRUCTION, LLC, Plaintiff-Respondent, v. CONWAY CONTRACTING, INC., Defendant-Appellant, and David Jones Construction, L.L.C. et al., Defendant. |
Court | Missouri Court of Appeals |
CRAIG A. SMITH, St. Louis, Mo, for Appellant.
RICHARD L. SCHNAKE, Springfield, Mo, for Respondent.
Conway Contracting, Inc. ("Contractor") appeals a judgment that awarded $38,672.48 to Donco 3 Construction, LLC ("Subcontractor") on its successful suit to enforce a mechanic's lien. Because Contractor is not liable to pay any part of the judgment at issue, Contractor is not an aggrieved party and thereby lacks the standing necessary to appeal the judgment.
Contractor was the general contractor selected by Theta Xi Fraternity ("Fraternity") to build its "frat house" in Rolla. Contractor hired David Jones Construction, L.L.C. ("Jones") as a subcontractor or "construction broker." Jones performed little or no actual labor on the project. At the request of both Contractor and Jones, Subcontractor began performing work at the project in February 2018.
Subcontractor submitted its first pay request to Contractor and Jones in the amount of $32,679 ("Pay Application 1"). Thereafter, Contractor sent a check for $34,085.10 to Jones, but Jones did not pass any of that money on to Subcontractor.
Not having been paid for its work, Subcontractor filed a statement of mechanic's lien in the amount of $43,862.491 against Contractor and Jones. When the lien remained unsatisfied, Subcontractor filed the instant lawsuit against Contractor, Jones, Fraternity, Phelps County Bank ("Bank"), and J. Kent Robinson.2
Early in the litigation process, counsel for Fraternity tendered a check to the trial court in the amount of $53,000, drawn on Phelps County Bank, to be used to pay any mechanic's lien judgment that might be entered in the case. All parties agreed that "[t]he $53,000 payment shall be a dollar-for-dollar offset against any amount owed by [Contractor] on the mechanic lien."3
The case proceeded to trial before the court with Subcontractor as the plaintiff and Contractor and Jones as defendants. Jones was in default and did not appear at trial or present any evidence. Contractor asserted that Subcontractor had affirmatively waived its lien, but the trial court resolved that dispute in favor of Subcontractor. After the bench trial, the trial court entered judgment in favor of Subcontractor for $38,672.48, plus interest, against Contractor and Jones. In accordance with the parties’ agreement, the judgment entered by the trial court included the following recitation:
IT IS FURTHER ORDERED, ADJUDGED, AND DECREED that pursuant to the agreement of the parties, the sum of $38,672.48, plus interest on this amount at 9% per annum from August 27, 2020 until the date of payment, shall be paid out of the Court's registry to [Subcontractor] in order to satisfy the Judgment.[4 ] After receiving the funds, [Subcontractor] must file a Satisfaction of Judgment. All remaining amounts in the Court's registry shall be returned to [Bank].
"The right to appeal is purely statutory, and where a statute provides no right to appeal, none exists." Aldridge v. First Fin. Ins. Co. , 828 S.W.2d 734, 735 (Mo. App. S.D. 1992). Before we can reach the merits of an appeal, we must determine whether we have the statutory authority to do so. Meyers v. Johnson , 182 S.W.3d 278, 280 (Mo. App. S.D. 2006). Section 512.020, grants a right to appeal from a final judgment to "[a]ny party to a suit aggrieved by any judgment of any trial court in any civil cause from which an appeal is not prohibited by the constitution[.]"
Wooldridge v. Hull , 604 S.W.3d 364, 368 (Mo. App. S.D. 2020).
"[G]enerally, ‘[a] party is ‘aggrieved’ when the judgment operates prejudicially and directly on his personal or property rights or interest and such is an immediate and not merely a possible remote consequence.’ " Id. at 368 (quoting Stockman v. Safe-Skin, Corp. , 36 S.W.3d 447, 449 (Mo. App. E.D. 2001) ).
Here, when the parties agreed that Fraternity's $53,000 deposit with the trial court would be used as "a dollar-for-dollar offset against any amount owed by [Contractor] on the mechanic lien[,]" Contractor could not be aggrieved by any judgment that did not...
To continue reading
Request your trial