Great Western Sugar Co. v. F.H. Gilcrest Lumber Co.
Decision Date | 10 November 1913 |
Citation | 25 Colo.App. 1,136 P. 553 |
Parties | GREAT WESTERN SUGAR CO. v. F.H. GILCREST LUMBER CO. |
Court | Colorado Court of Appeals |
Error to District Court, Weld County; Harry P. Gamble, Judge.
Action by the F.H. Gilcrest Lumber Company against the Great Western Sugar Company. Judgment for plaintiff, and defendant brings error. Affirmed.
H.N. Haynes, of Greeley (Charles W. Waterman, of Denver, of counsel), for plaintiff in error.
R.G Strong and C.E. Southard, both of Greeley, for defendant in error.
On rehearing, former opinion withdrawn and the following substituted; MORGAN, J., delivering the opinion of the court:
Writ of error to reverse a judgment of the Weld district court in an action against the sugar company hereinafter called the owner, and its principal contractor, Eggleston, to foreclose a mechanics' lien upon a building which the contractor agreed orally to construct for the owner, purchasing his material from the lumber company, hereinafter called the claimant, and which filed its lien statement and began this action within the required time thereafter. The lien law of 1899 is involved. No evidence was abstracted. There is some controversy over service by publication on the principal contractor and default thereupon, but the principal contention is over the court's ruling on two general demurrers: One to the complaint overruled, one to the answer sustained.
The owner contends that in case of a contract between the owner and contractor, regardless of the amount of the contract price, subcontractors and materialmen, in order to maintain a lien for any more than may be owing to the contractor when the lien statement is filed for record must serve on the owner a written notice that they have performed labor or furnished material, etc., independent of the service on the owner of a copy of the lien statement, and claims the right to pay the contractor, in the absence of such notice, or until such notice is served, at such times as the contract may provide, and in full, at the expiration of 35 days after the completion of the contract, if no such notice has been served prior thereto. The claimant contends that no such notice is required, in any case, if the contract price is $500 or less, and, as a broader contention, not in any case unless the contract or a memorandum thereof is filed with the county recorder. These contentions must be determined from the lien act of 1899, and particularly from sections 1 and 2, being sections 4025 and 4026 of the Revised Statutes 1908.
Section 4025, after providing generally that mechanics subcontractors, and materialmen, although dealing with the contractor alone, have a lien upon the property of the owner benefited, states:
Section 4026, after providing that the contract must provide for payments in installments after work is begun, that 15 per cent. must be held for 35 days after the completion, that any payments made prior to dates set shall not affect liens of subcontractors and materialmen, that as to them the amount of the contract shall be paid in money and shall not be affected by any indebtedness of the contractor to the owner, states:
Section 4033 provides that a lien statement must be filed for record, and that subcontractors and materialmen must file such statement within two months after completion of the building and serve a copy of the same upon the owner at or before the time of filing.
The provisions for filing the contract, service of notice, etc., were added to the law of 1889 by the act of 1893 and retained in 1899 to enable the owner to limit his liability to subcontractors and materialmen and to protect himself from the broad provisions of the law of 1889 and, with few changes, retained in the law of 1893 and 1899, which gave them a direct lien, regardless of the state of the account, except the limitation to the contract price, between the owner and his contractor. By filing his contract or a memorandum, as the law of 1893 and 1899 provides he may do, the owner may pay the contractor, in installments by the terms and provisions thereof, without fear of liens, unless the subcontractor give him written notice of intention or, as the statute says, written notice that he has "performed labor or furnished material *** or agreed to and will do so."
If the owner fail to file the contract or memorandum as the law provides he may do, or if the law does not require it to be filed, as in instances where the contract price is $500 or less, then, in either instance, there is no way for the owner to so limit his liability. The owner, in order to profit by these provisions in his behalf, must have a written contract, provide in it that payments will be made in installments at times named, that nothing shall be paid in advance of the work, that at least 15 per cent. of the price shall be made payable at least 35 days after completion of the contract, and then file it, or a memorandum thereof, so that subcontractors and materialmen may know that he intends to avail himself of the privilege given.
It has been held in the case of Willamette Co. v. Los Angeles Co., 94 Cal. 229, 237, 29 P. 629, 632, that: "Where the owner does not choose to avail himself of the mode of limiting his liabilities provided in this section, labor done and materials furnished shall be deemed to have been done and furnished at his personal instance."
In Small v. Foley, 8 Colo.App. 435, 451, 47 P. 64, 70, the court said: "It seems manifest that the provision [as to notice] was intended for the owner's personal benefit."
O...
To continue reading
Request your trial-
State ex rel. Pollock v. Becker
... ... persuasive, and indeed as entitled to very great weight, with ... the courts of the adopting ... Cas. 1914-C, 98, 41 L.R.A. 315; Western Terra Cotta Co ... v. Board Education, 39 ... 737, 138 C. C. A. 191; Gr. West Sugar ... Co. v. Gilcrest Lbr. Co., 25 Colo.App. 1, ... ...
-
State v. Becker
...v. Edwards, 89 N. J. Law, 507, 99 Atl. 136; Penn Br. Co. v. New Orleans, 222 Fed. 737, 138 C. C. A. 191; Gr. West. Sugar Co. v. Gilcrest Lbr. Co., 25 Colo. App. 1, 136 Pac. 553; Rhoads v. Chicago, etc., Co., 227 Ill. 328, 81 N. E. 371, 11 L. R. A. (N. S.) 623, 10 Ann. Cas. 111; People v. Gr......
-
Phoenix Title & Trust Co. v. Old Dominion Co.
... ... 369, 33 L.R.A. (N.S.) 606, 126 N.W. 611; Great Western ... Sugar Co. v. Lumber Co., 25 ... ...
-
Bushman Construction Co. v. Air Force Academy Housing, Inc., 7263.
...the contractor and subcontractor before a lien will lie therefor. The Colorado Supreme Court in Great Western Sugar Co. v. F. H. Gilcrest Lumber Co., 25 Colo.App. 1, 136 P. 553 (1913), had before it an interpretation of the lien statute in relation to the allowable amount of a lien and the ......