In re Montana-Dakota Utilities Co.

Decision Date17 October 2007
Docket NumberNo. 24448.,24448.
PartiesIn the Matter of the Petition of MONTANA-DAKOTA UTILITIES CO. for Approval to Provide Electrical Service for the New North Central Farmers Elevator to be Located Near Bowdle, South Dakota.
CourtSouth Dakota Supreme Court

Robert C. Riter, Jr., Margo D. Northrup, Darla Pollman Rogers of Riter, Rogers, Wattier & Brown, Pierre, South Dakota, Attorneys for appellee FEM Electric & SD Rural Elec. Assoc.

Carlyle Richards of Richards & Oliver, Aberdeen, South Dakota, Attorneys for appellee North Central Farmers Elev.

KONENKAMP, Justice.

[¶ 1.] The question we address in this administrative appeal is whether an electric utility may petition to provide service outside its statutorily assigned service territory to a "large load" customer in another utility's assigned service area. We conclude that SDCL 49-34A-56 allows only customers to petition for an outside provider. Thus, we affirm the Public Utilities Commission's ruling that an outside provider lacked standing to bring a petition under the statute.

Background

[¶ 2.] The Public Utilities Commission (PUC) regulates which utility provides a customer with service. SDCL Chapter 49-34A. Under SDCL 49-34A-42, the Legislature allotted each utility an exclusive right to provide service to all new and existing customers within its assigned territory.1 North Central Farmers Elevator decided to build a new facility in Bowdle, South Dakota. Montana-Dakota Utilities Company (MDU) and FEM Electric Association (FEM) both furnish power to customers in the vicinity, but FEM is statutorily assigned to provide power in the territory where the Bowdle facility would be built. North Central entered into discussions with both MDU and FEM to decide whether it would receive service from the incumbent provider, FEM, or seek permission from the PUC to use the outside provider, MDU. Ultimately, North Central executed a service agreement with FEM.

[¶ 3.] Disappointed with FEM's choice, MDU brought a petition under SDCL 49-34A-56 seeking to have the PUC assign MDU as the provider for power to the Bowdle facility. Despite the fact that FEM had exclusivity in serving the new facility, MDU asserted in its petition that "regardless of customer preference, MDU is the best suited to provide electric service to North Central under a service contract pursuant to the criteria established by SDCL 49-34A-56[.]" In particular, MDU averred that the Bowdle facility is a large load customer and MDU "is fully able to provide the electrical service requirements of the load to be served." It also alleged that it had an adequate power supply available and would expend fewer dollars than FEM to provide service. According to MDU, it would need only one half mile of additional line, while FEM's line would have to extend for four miles.

[¶ 4.] FEM, North Central, and the South Dakota Rural Electric Association successfully petitioned to intervene. North Central asserted that MDU's petition was improperly brought because, among other things, it was North Central's preference that FEM provide service. Correlatively, FEM argued that the new Bowdle facility is within its exclusive territory, and it was willing and able to furnish adequate services, and therefore, it should be the provider.

[¶ 5.] FEM moved for summary disposition, alleging that MDU did not have standing to bring a petition under SDCL 49-34A-56. The PUC granted summary disposition concluding that (1) because the Bowdle facility would be located in FEM's service territory, FEM had the exclusive right to provide service; and (2) MDU is not a customer, and therefore, it did not have standing under SDCL 49-34A-56 to bring a petition. The circuit court upheld the PUC's decision. MDU now appeals to this Court. The question hinges purely on statutory interpretation: did the Legislature intend to open the competition between utilities for "large load" customers, or did it intend to grant exclusive territories for utilities except when customers seek an outside provider.

Standard of Review

[¶ 6.] We review agency decisions the same as the circuit court; there is no presumption that the circuit court's decision was correct. U.S. West Communications, Inc. v. Public Util. Comm'n, 505 N.W.2d 115, 122-23 (S.D.1993) (citing Northwestern Bell v. Public Util. Comm'n, 467 N.W.2d 468, 469 (S.D.1991)). Neither do we defer "to the interpretation of the trial court, nor to the agency's conclusions of law." Id. Questions of statutory interpretation are reviewed de novo. Aspen Storage, Inc. v. Flanagan, 2007 SD 66, ¶ 9, 737 N.W.2d 277, 280 (citing Town Square Ltd. P'ship v. Clay County Bd. of Equalization, 2005 SD 99, ¶ 9 n. 1, 704 N.W.2d 896, 899 n. 1 (citing Fall River County v. S.D. Dep't of Rev., 1999 SD 139, ¶ 15, 601 N.W.2d 816, 821 (citations omitted))).

Analysis and Decision

[¶ 7.] In 1975, our Legislature adopted the "South Dakota Territorial Act." This Act gave the PUC the power to establish zones in which utilities would be assigned exclusively to provide service to all new and existing customers in their respective territories. In the case of In the Matter of Establishing Certain Territorial Elec. Boundaries (Mitchell Area), 281 N.W.2d 65, 70 (S.D.1979), we acknowledged that the Act was adopted to avoid duplication of facilities and wasteful spending. Although the Act gave utilities exclusive service areas, it also established limited exceptions whereby a customer might obtain service from an alternative provider. SDCL 49-34A-58; SDCL 49-34A-55; SDCL 49-34A-56.2 See also In the Matter of Northwestern Public Service Co. (Hub City), 1997 SD 35, ¶ 16, 560 N.W.2d 925, 928. The exception implicated in this case is found in SDCL 49-34A-56. It provides:

Notwithstanding the establishment of assigned service areas for electric utilities provided for in §§ 49-34A-43 and 49-34A-44, new customers at new locations which develop after March 21, 1975, ... and who require electric service with a contracted minimum demand of two thousand kilowatts or more shall not be obligated to take electric service from the electric utility having the assigned service area where the customer is located if, after notice and hearing, the Public Utilities Commission so determines after consideration of the following factors:

(1) The electric service requirements of the load to be served;

(2) The availability of an adequate power supply;

(3) The development or improvement of the electric system of the utility seeking to provide the electric service, including the economic factors relating thereto;

(4) The proximity of adequate facilities from which electric service of the type required may be delivered;

(5) The preference of the customer;

(6) Any and all pertinent factors affecting the ability of the utility to furnish adequate electric service to fulfill customers' requirements.

Id.

[¶ 8.] According to MDU, SDCL 49-34A-56 should not be interpreted to allow only a customer to bring a petition for alternative service, as that would defeat the intent of the Act, which is to avoid duplicative and wasteful spending. This statute states that a customer "shall not be obligated to take service from" the assigned provider if the "Commission so determines after consideration" of six factors. SDCL 49-34A-56. One factor is customer preference. Id. MDU asserts that because one of the considerations is customer choice, the Legislature did not intend that the customer be the only one allowed to bring a petition. Instead, customer preference is simply a consideration. MDU relies on language from Willrodt v. Northwestern Public Service Co., where we stated that "[a]n individual has no organic, economic, or political right to service by a particular utility merely because he deems it advantageous to himself." 281 N.W.2d 65, 72 (S.D.1979) (quoting Storey v. Mayo, 217 So.2d 304, 307-08 (Fla.1968)).

[¶ 9.] FEM agrees that the Act was adopted with the intent to avert wasteful spending. It contends, however, that a plain reading of SDCL 49-34A-56 demonstrates that only the customer has standing to bring a petition. Moreover, according to FEM, even though a customer does not have an "organic, economic or political right to service by a particular utility," subject to some exceptions, a utility does have an "exclusive right" to provide service to a "future customer in its assigned service area." See Willrodt, 281 N.W.2d at 72 (citation omitted); SDCL 49-34A-42. FEM believes that to allow "a competing electric service provider to petition the [PUC] under SDCL 49-34A-56 forces the customer to engage in a costly regulatory hearing process." It would also, FEM argues, lead to competing providers trying to "cherry pick large customers in another electrical provider's service area," which would render SDCL 49-34A-42 meaningless.

[¶ 10.] "The purpose of statutory construction is to discover the true intention of the law which is to be ascertained primarily from the language expressed in the statute." Esling v. Krambeck, 2003 SD 59, ¶ 6, 663 N.W.2d 671, 675-76 (citation omitted). When interpreting a statute, we give plain meaning and effect to words and phrases. Hay v. Bd. of Comm'rs for Grant County, 2003 SD 117, ¶ 9, 670 N.W.2d 376, 379 (citing Esling, 2003 SD 59, ¶ 6, 663 N.W.2d at 676 (citing Moss v. Guttormson, 1996 SD 76, ¶ 10, 551 N.W.2d 14, 17 (citations omitted))). We view the language of the statute as a whole, "`as well as enactments relating to the same subject.'" Moss, 1996 SD 76, ¶ 10, 551 N.W.2d at 17 (quoting U.S. West Communications, Inc., 505 N.W.2d at 122-23).

[¶ 11.] On careful examination of SDCL 49-34A-56, we ...

To continue reading

Request your trial
4 cases
  • Heinemeyer v. Heartland
    • United States
    • South Dakota Supreme Court
    • November 12, 2008
    ... ... West Communications, Inc. v. Public Utilities Com'n of State of S.D., 505 N.W.2d 115, 122-23 (1993)) ...          In re Montana-Dakota Utilities Co., 2007 SD 104, ¶ 10, 740 N.W.2d ... ...
  • Tucek v. Dept. of Social Services
    • United States
    • South Dakota Supreme Court
    • October 17, 2007
  • Leonard v. State ex rel. South Dakota Real EState Com'n
    • United States
    • South Dakota Supreme Court
    • December 15, 2010
    ...agency decisions the same as the circuit court; there is no presumption that the circuit court's decision was correct." In re Montana-Dakota Util. Co., 2007 S.D. 104, ¶ 6, 740 N.W.2d 873, 876 (citing U.S. West Commc'n, Inc. v. Pub. Util. Comm'n, 505 N.W.2d 115, 122-23 (S.D.1993) (citing Nor......
  • Leonard v. State Of South Dakota
    • United States
    • South Dakota Supreme Court
    • December 15, 2010
    ...agency decisions the same as the circuit court; there is no presumption that the circuit court's decision was correct." In re Montana-Dakota Util. Co., 2007 S.D. 104, ¶ 6, 740 N.W.2d 873, 876 (citing U.S. West Commc'n, Inc. v. Pub. Util. Comm'n, 505 N.W.2d 115, 12223 (S.D. 1993) (citing Nor......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT