Integrity Int'l, Inc. v. HP, Inc.

Decision Date08 December 2022
Docket Number532968
Citation211 A.D.3d 1194,180 N.Y.S.3d 320
Parties INTEGRITY INTERNATIONAL, INC., Doing Business as Tarrenpoint, Appellant—Respondent, v. HP, INC., et al., Respondents—Appellants.
CourtNew York Supreme Court — Appellate Division

Fairchild Law, LLC, New York City (Steven R. Fairchild of counsel), for appellant-respondent.

Woods Oviatt Gilman LLP, Rochester (F. Michael Ostrander of counsel), for respondents-appellants.

Before: Lynch, J.P., Aarons, Reynolds Fitzgerald, Fisher and McShan, JJ.

MEMORANDUM AND ORDER

Lynch, J.P. Cross appeals from an order of the Supreme Court (Denise A. Hartman, J.), entered February 8, 2021 in Albany County, which partially granted defendantsmotion for partial summary judgment dismissing certain causes of action.

Plaintiff, a corporation with its principal place of business in Texas, provided services to defendants and their predecessor, Compaq Computer Corporation, pursuant to written service contracts from 1994 to 2016. This matter pertains to two of those agreements between the parties: the Standard Service Agreement (hereinafter SSA), effective May 2011, and the Master Standard Service Agreement (hereinafter MSSA), effective July 2014, which superseded the SSA. Although the particulars differed, both agreements required defendants to make periodic payments to plaintiff for its services. According to plaintiff, defendants often failed to make timely payments, resulting in severe cash flow issues. Plaintiff, in turn, calculated interest on defendants’ outstanding balances, which was billed to defendants as late fees on plaintiff's invoices. Despite occasionally paying those fees, defendants disputed their liability for them under either the SSA or the MSSA (hereinafter collectively referred to as the agreements). The parties did not resolve their payment disputes, and eventually defendants withdrew their work from plaintiff.

Plaintiff commenced this action in October 2017 alleging five causes of action for (1) account stated, (2) breach of contract, (3) breach of the implied duty of good faith and fair dealing, (4) quantum meruit/unjust enrichment, and (5) fraudulent inducement. Plaintiff based its second cause of action for breach of contract on two theories: first, defendants failed to timely pay plaintiff's invoices, and, second, defendants failed to pay late fees. Following defendants’ unsuccessful pre-answer motion to dismiss, issue was joined and discovery ensued. Defendants moved for partial summary judgment, which Supreme Court partially granted, dismissing as time-barred so much of plaintiff's breach of contract action as was based on untimely payments allegedly made before October 13, 2013, and so much of plaintiff's action alleging breaches of the implied duty of good faith and fair dealing occurring before October 13, 2015. The court also dismissed so much of plaintiff's breach of contract action as was based on defendants’ failure to pay late fees, concluding that those fees were not contemplated by the agreements. Plaintiff appeals, and defendants cross appeal.1

Turning to plaintiff's appeal, a breach of contract cause of action "requires that the plaintiff show the existence of a contract, the performance of its obligations under the contract, the failure of the defendant to perform its obligations and damages resulting from the defendant's breach" ( Daire v. Sterling Ins. Co., 204 A.D.3d 1189, 1190, 167 N.Y.S.3d 197 [3d Dept. 2022] [internal quotation marks, brackets and citation omitted]; see Connors v. Jannuzzo, 195 A.D.3d 1101, 1101, 144 N.Y.S.3d 874 [3d Dept. 2021] ). The parties dispute whether the agreements confer an obligation on defendants to pay late fees. In this respect, whether the terms of a contract are ambiguous is a question of law for the court in the first instance, and the answer must be derived from within the four corners of the document (see Daire v. Sterling Ins. Co., 204 A.D.3d at 1190–1191, 167 N.Y.S.3d 197 ). Importantly, "an ambiguity never arises out of what was not written at all, but only out of what was written so blindly and imperfectly that its meaning is doubtful" ( Donohue v. Cuomo, 38 N.Y.3d 1, 13, 164 N.Y.S.3d 39, 184 N.E.3d 860 [2022] [internal quotation marks and citations omitted]). Indeed, "where a contract was negotiated between sophisticated, counseled business people negotiating at arm's length, courts should be especially reluctant to interpret an agreement as impliedly stating something which the parties have neglected to specifically include" ( 2138747 Ontario, Inc. v. Samsung C & T Corp., 31 N.Y.3d 372, 381, 78 N.Y.S.3d 703, 103 N.E.3d 774 [2018] [internal quotation marks and citation omitted]; see Donohue v. Cuomo, 38 N.Y.3d at 12, 164 N.Y.S.3d 39, 184 N.E.3d 860 ).

Applying these principles, Supreme Court correctly concluded that the terms of the agreements are clear, unambiguous and do not contemplate late fees. The agreements specify that charges to defendants are determined according to rate schedules attached to the agreements, and such rates include "all fees ..., costs of operation, fringe benefits attributable to payroll, overhead, profit, social charges and all [n]on[-r]ecoverable taxes." Although the agreements afforded defendants a 2% discount for early payment, neither contained terms providing for the assessment of late fees, precluding plaintiff from claiming otherwise. As such, Supreme Court appropriately dismissed so much of defendants’ second cause of action as was based on defendants’ failure to pay late fees (see 2138747 Ontario, Inc. v. Samsung C & T Corp., 31 N.Y.3d at 381, 78 N.Y.S.3d 703, 103 N.E.3d 774 ).

Next, plaintiff contends that Supreme Court erred in dismissing as time-barred so much of its breach of contract action as was based on claims accruing before October 13, 2013. The parties agree that plaintiff's breach of contract claims are governed by Texas’ four-year statute of limitations (see Tex Civ Prac & Rem § 16.051 ; Stine v. Stewart, 80 S.W.3d 586, 592 [Tex. 2002] ). Under Texas law, where an agreement contemplates fixed periodic payments for services, a breach of contract claim accrues each time a defendant misses a payment (see Davis Apparel v. Gale–Sobel, a Div. of Angelica Corp., 117 S.W.3d 15, 18 [Tex. Ct. App. 2003] ). Where, however, an "agreement contemplates a continuing contract for performance, the limitations period usually does not commence until the contract is fully performed" ( Trelltex, Inc. v. Intecx, L.L.C., 494 S.W.3d 781, 786 [Tex. Ct. App. 2016] ).

Plaintiff points out that it kept performing under the agreements despite defendants’ delinquency or nonpayment. Here, the agreements governed payments for services performed by plaintiff over periods of years and according to separate statements of work (hereinafter SOW) between plaintiff and defendants. According to the model SOW accompanying the agreements, each SOW would specify the objectives and due dates for the services contracted. Paragraph 1.1 of both agreements specifies that each SOW and the relevant agreement — the SSA or MSSA — comprise an integrated contract. Each integrated SOW and relevant agreement may be continuing in the vein of a construction contract (see Integrated of Amarillo, Inc. v. Pinkston–Hollar Constr. Servs., Inc., 2013 WL 1324580, *3, 2013 Tex. App. LEXIS 4216 [Tex. Ct. App. Apr. 2, 2013, No. 07–11–0422–CV] ), but the agreements on their own just set out the fixed schedule of invoicing and payment according to rates contained therein (see Hart v. International Tel. & Tel. Corp., 546 S.W.2d 660, 662 [Tex. Ct. Civ. App. 1977] ). As such, the agreements are not continuing contracts, and Supreme Court appropriately dismissed as untimely so much of plaintiff's second cause of action as was based on payments due before October 13, 2013.

Moving on to defendants’ contentions, we first note that they did not timely perfect their cross appeal within six months of filing their notice of same, nor did they seek an extension of time to do so (see Rules of App.Div., All Depts [ 22 NYCRR] § 1250.9 [a]). Unless granted an extension by this Court, "an appellant must perfect its appeal within six months of the date of the notice of appeal or the appeal will be deemed dismissed" ( New York Mun. Power Agency v. Town of Massena, 197 A.D.3d 83, 86, 151 N.Y.S.3d 714 [3d Dept. 2021] ; see Rules of App.Div., All Depts [ 22 NYCRR] §§ 1250.9 [b]; 1250.10[a]). Notably, plaintiff similarly failed to perfect its appeal, but this Court granted plaintiff's motion to vacate the automatic dismissal (see Rules of App.Div., All Depts [ 22 NYCRR] § 1250.10 [c]), and it ultimately perfected by the new deadline. It appears that defendants were waiting for plaintiff to perfect. Yet, only when plaintiff perfected its appeal was it denominated the appellant-respondent. "Until such time as either party has perfected, the identity of a party as either an appellant-respondent or a respondent-appellant remains to be determined" ( New York Mun. Power Agency v. Town of Massena, 197 A.D.3d at 86, 151 N.Y.S.3d 714 ). As defendants were not respondents-appellants until plaintiff perfected, they were required to maintain their position, either by applying for extensions or perfecting first (see id. at 86–87, 151 N.Y.S.3d 714 ).

However, in November 2021 the parties did stipulate to a briefing schedule, and, although the stipulation was itself untimely, its existence indicates that the parties consulted and determined which of them would perfect first (see Rules of App.Div., All Depts [ 22 NYCRR] § 1250.9 [f][1][i]; compare New York Mun. Power Agency v. Town of Massena, 197 A.D.3d at 87, 151 N.Y.S.3d 714 ). We therefore exercise our prerogative to "waive defendants’ noncompliance and deem the cross appeal properly before us" ( New York Mun. Power Agency v. Town of Massena, 197 A.D.3d at 87, 151 N.Y.S.3d 714 ).

Turning to the merits, defendants contend that ...

To continue reading

Request your trial
1 cases
  • Bucci v. Dinapoli
    • United States
    • New York Supreme Court — Appellate Division
    • 8 Diciembre 2022

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT