Kleinschmidt v. Morrow

Decision Date18 May 1994
Citation642 A.2d 161
PartiesHazel A. KLEINSCHMIDT v. Maurice MORROW, d/b/a Maurice Morrow Construction.
CourtMaine Supreme Court

David M. Lipman, Peter B. Bickerman, Lipman & Katz, Augusta, for plaintiff.

Alan F. Harding, Hardings Law Offices, Presque Isle, for defendant.

Before WATHEN, C.J., ROBERTS, GLASSMAN, CLIFFORD, RUDMAN, and DANA, JJ., and COLLINS, A.R.J. *

GLASSMAN, Justice.

Maurice Morrow, d/b/a Maurice Morrow Construction, appeals and Hazel A. Kleinschmidt cross-appeals from the entry of a judgment after a jury-waived trial in the Superior Court (Lincoln County, Perkins, J.) awarding compensatory damages to Kleinschmidt on her complaint against Morrow. Morrow contends that the trial court erred in refusing to issue further findings of fact and conclusions of law and the evidence does not support the damages assessed against him. 1 By her cross-appeal, Kleinschmidt contends that the trial court erred in refusing to award punitive damages to her on her claim for abuse of process and in refusing to grant her attorney fees pursuant to the Maine Unfair Trade Practices Act (UTPA), 5 M.R.S.A. §§ 205-A to 214 (1989). For the reasons set forth herein we affirm the judgment.

I.

Based on the evidence, the trial court could have found the following facts: On April 6, 1989, the parties entered into a contract that provided Morrow would construct a new house adjacent to and on the same property as Kleinschmidt's existing house in Jefferson at a cost of $68,200. The contract acknowledged the receipt by Morrow of a $20,000 deposit and recited that the balance was "to be paid when house is sold or other arrangments [sic] are made." Although the contract did not state the completion date, Morrow told Kleinschmidt that it would take between two and three months to build a house.

In April 1989 Morrow began construction of the new home. By June 1989 Morrow had completed approximately one-half of the work and had depleted the $20,000 deposit. Despite the fact that the contract made no provision for progress payments, Morrow refused to perform further work on the new house until he received further payment. Because Morrow told her that it was important to get the windows and siding installed, Kleinschmidt paid an additional $2000 to Morrow for this work. When Morrow again requested further payment, Kleinschmidt refused and hired her own electrician to perform necessary electrical work. When the construction work ceased in late July or early August of 1989, the house was still not completed. On inquiry by Kleinschmidt to determine when Morrow was going to complete the house, Morrow stated that he would resume work on the house when Kleinschmidt obtained more money. Kleinschmidt contacted Morrow again in August 1989 to discuss completion of the roof, but Morrow stated, "I do not want anything more to do with the house, that's it, I am all done working for you."

In January 1990 Kleinschmidt had an opportunity to sell her old house, and after receiving a down payment on the purchase price, she contacted Morrow to request that he finish the new house. Morrow again refused. The sale of the old house did not materialize because the new house remained unfinished. Kleinschmidt contacted another contractor, Lawrence Terrio, to discuss completion of the new house. After examining the site, Terrio discovered numerous defects in Morrow's workmanship. According to Terrio, because of defects in the placement and quality of trusses, rafters, and studs, it would be necessary to "gut" the house and redo the work. Terrio estimated that the cost of completing the house according to the original plans would be $47,500.

On April 11, 1990, Morrow filed a statement of lien in the Registry of Deeds, claiming a lien on both the new and the old house. Although he had received full payment for all labor and materials furnished by him, Morrow claimed a lien for an outstanding balance for work performed in the amount of $48,200 and misrepresented the date on which services were last performed. His stated purpose for filing the lien was to encumber Kleinschmidt's title so that he could get paid, to prevent Kleinschmidt from getting anyone else to work on the house, and to prevent the sale of the old house. Although Morrow received a letter from Kleinschmidt's counsel requesting that the lien be released, Morrow took no action to perfect or release the lien. In October 1991 and again in April 1992, Kleinschmidt's applications for financing to complete the new house were rejected because of the statement of lien filed by Morrow.

II.

Kleinschmidt filed the instant action in the District Court (Wiscasset) seeking compensatory damages for Morrow's alleged breach of the construction contract and compensatory and punitive damages for Morrow's alleged abuse of process. For Morrow's alleged violation of the UTPA, she sought an injunctive order requiring Morrow to file a notice of release of the lien and payment of her attorney fees. After the matter was removed to the Superior Court, Morrow's counterclaim seeking damages for Kleinschmidt's alleged breach of the construction contract was dismissed with prejudice as a sanction for Morrow's failure to comply with the court's order relating to discovery. Following a jury-waived trial, the court awarded to Kleinschmidt $2300 in compensatory damages on her claim for Morrow's breach of contract, $8000 in compensatory damages on her claim for his abuse of process and declared the lien filed by Morrow to be null and void. The court found that Kleinschmidt was not entitled to punitive damages for Morrow's abuse of process and held that she was not entitled to recover her attorney fees pursuant to the UTPA because Kleinschmidt did not suffer a "loss" within the meaning of 5 M.R.S.A. § 213 (1989). Morrow's motion for findings of fact and conclusions of law was denied. From the judgment entered accordingly, Morrow appeals and Kleinschmidt cross-appeals.

III.

At the outset, we reject Morrow's contention that the trial court improperly denied Morrow's motion for findings of fact and conclusions of law. The trial court issued a six-page decision that includes detailed factual findings and conclusions of law. When, as here, a trial court's findings of fact and conclusions of law appear within the court's decision, the court need not grant a request for findings of fact and conclusions of law. Bayley v. Bayley, 602 A.2d 1152, 1153 (Me.1992); see also M.R.Civ.P. 52. Moreover, we note that Morrow did not move for specific findings of fact and conclusions of law. See Murray v. Murray, 529 A.2d 1366, 1368, n. 1 (Me.1987) ("It is ... incumbent on litigants to move for specific findings of fact and conclusions of law in those cases in which the development of the facts and statement of the rationale is ... not sufficiently developed in, the court's decision." (Emphasis added)).

Morrow next contends because he did not perfect the lien in accordance with 10 M.R.S.A. § 3255(1) (Supp.1993) 2 the filing of a statement of lien could not result in damages to Kleinschmidt. 3 We disagree. The tort of abuse of process requires "use of the process in a manner not proper in the regular conduct of the proceedings...." Nadeau v. State, 395 A.2d 107, 117 (Me.1978) (emphasis added). An award of damages will be set aside only "when the record presents no rational basis by which the factfinder could have arrived at the amount awarded." Titcomb v. Saco Mobile Home Sales, Inc., 544 A.2d 754, 758 (Me.1988). Morrow filed a lien statement that grossly misstated material facts as to the amount he was owed and the last date he performed services on the new house. He testified, inter alia, that by filing a statement of lien he intended to prevent completion of the new house by anyone else and the sale of the old house. He refused to comply with Kleinschmidt's request to release the lien. There is also evidence that the recorded lien statement filed by Morrow was the basis for the bank's denial of Kleinschmidt's requests for loans necessary to finance the completion of the new house.

Kleinschmidt's uncontroverted testimony was that if the new house had been completed by January 1990, she would have rented the old house for $400 a month. We reject Morrow's contention that Kleinschmidt is not competent to testify as to the rental value of her real estate. We have previously held that an owner of real estate is competent to express her opinion of the property's value. Dehahn v. Innes, 356 A.2d 711, 722 (Me.1976). Any objection raised by Morrow as to Kleinschmidt's "actual familiarity with the particular property ...

To continue reading

Request your trial
17 cases
  • Hamilton v. Fed. Home Loan Mortg. Corp.
    • United States
    • U.S. District Court — District of Maine
    • 15 Septiembre 2014
    ...in the operation of the machinery of the courts does not give rise to liability for abuse of process. Compare id. with Kleinschmidt v. Morrow, 642 A.2d 161, 164 (Me. 1994) (affirming liability for abuse of process where a builder filed a lien statement that "grossly misstated material facts......
  • Wachter v. Gratech Co., Ltd.
    • United States
    • North Dakota Supreme Court
    • 24 Marzo 2000
    ...inflated mechanic's liens. See, e.g., Display Fixtures Co. v. R.L. Hatcher, Inc., 438 N.E.2d 26, 31 (Ind.App.1982); Kleinschmidt v. Morrow, 642 A.2d 161, 164 (Me.1994). Claims of abuse of process based on allegedly inflated mechanic's liens generally have been unsuccessful when there is a l......
  • Morgan v. Criterium-Mooney Engineers
    • United States
    • Maine Superior Court
    • 16 Diciembre 2009
    ...have in fact been committed, unless those practices have not only harmed the consumer but also benefited the dealer." Kleinsdmidt v. Morrow, 642 A.2d 161, 165 (Me. 1994) (quoting Drinkwater v. Patten Realty Corp., 563 772, 777 (Me. 1989)). In Adelberg v. Guber the court applied this princip......
  • Advanced Const. Corp. v. Pilecki
    • United States
    • Maine Supreme Court
    • 13 Julio 2006
    ...708 A.2d 651, 655. Abuse of process claims can also arise from the misuse of the procedures for obtaining a lien. See Kleinschmidt v. Morrow, 642 A.2d 161, 164 (Me.1994). In Kleinschmidt, we affirmed an award of compensatory damages for abuse of process in part because the contractor's lien......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT