Masten Lumber and Supply Co., Inc. v. Brown

Decision Date11 July 1979
Citation405 A.2d 101
PartiesMASTEN LUMBER AND SUPPLY CO., INC., a Delaware Corporation, and Ray's Plumbing, Heating and Air Conditioning Service, Inc., a Delaware Corporation, Plaintiffs Below, Appellants, v. Timothy A. BROWN and Janet P. Brown, his wife, owner or reputed owners, and Reid and Lloyd, Inc., a Delaware Corporation, Defendants Below, Appellees.
CourtSupreme Court of Delaware

Upon appeal from Superior Court. Affirmed in part; reversed in part.

Harry H. Rhodes, III, of Brown, Shiels, & Barros, Dover, for plaintiff-appellant, Masten Lumber and Supply Co., Inc.

David D. Finocchiaro, Smyrna, for plaintiff-appellant, Ray's Plumbing, Heating and Air Conditioning Service, Inc.

N. Maxson Terry, Jr., of Terry, Terry, Jackson, Terry & Wright, Dover, for defendants-appellees.

Before HERRMANN, C. J., DUFFY and QUILLEN, JJ.

HERRMANN, Chief Justice:

In this consolidated appeal by two plaintiffs which supplied materials and labor for the construction of a residence, we must construe § 2707 of the Delaware Mechanic's Lien Statute, (25 Del.C. ch. 27) 1 governing residential housing. In determining the "balance due" under a contract to a general contractor who defaults prior to completion, we must decide whether it is proper to offset or deduct the cost of completion and liquidated damages for delay in completion. Our holding that the cost of completion may be deducted, while liquidated damages for delay may not, follows from both the words of the Statute and our conclusion that § 2707 modified, rather than repealed, the pre-existing Delaware Mechanic's Lien Law.

I.

Timothy A. and Janet P. Brown contracted with Reid and Lloyd, Inc. for the latter, as general contractor, to build a residence within 120 days for the contract price of $45,027.17. Prior to completion, Reid and Lloyd defaulted and were discharged, having already received $37,200 from the Browns. The Browns completed construction for an additional $3,912.97. Therefore, the total cash cost to the Browns was $41,112.97, rather than the contract price of $45,027.17. The contract provided a deduction of $25 for each day of delay beyond the 120 day limit, and the parties stipulated that a delay of 254 days had occurred. There was no evidence of actual additional expense caused by delay.

In the construction of the residence, the general contractor was supplied with materials and labor by Ray's Plumbing, Heating and Air Conditioning Service, Inc., in the amount of $3,005, and lumber and materials by Masten Lumber and Supply Co., Inc. in the amount of $10,185.49. Because Reid and Lloyd, the general contractor, defaulted and filed for bankruptcy without paying Ray's and Masten, these suppliers filed mechanics' liens against Reid and Lloyd, and the Browns.

II.

Our present Mechanic's Lien Statute has its origin in the Act passed by the General Assembly in 1861 "securing to Mechanics and others payment for labor and materials in erecting or repairing any building or structure within the State of Delaware." See 12 Del.Laws ch. 117 (1861). The clear purpose of that Act (and its recodifications) was to protect contractors against owners, and subcontractors and suppliers against both contractors and owners. See, e. g., J. G. Justis Co. v. Spicer, Del.Super., 95 A. 239 (1915). As noted by Judge Rodney in State v. Tabasso Homes, Del.Gen.Sess., 28 A.2d 248, 253 (1942), there are generally two types of mechanic's lien laws: "Under the New York System the lien of a sub-contractor or materialman depends upon or is limited by the amount remaining due to the contractor", and "the sub-contractor, laborer or materialman has only a derivative lien, being substituted to the right of the contractor." In contrast, "(u)nder the Pennsylvania System the right of sub-contractors, laborers or materialmen does not depend at all upon any indebtedness due from the owner to the contractor, but they get a direct lien as distinguished from a derivative one. * * * Delaware follows the Pennsylvania System." 28 A.2d at 253.

Under such system of direct liens, the owner may be subject to double liability. "(W)here the principal contractor has abandoned the work and the owner is compelled to pay an amount in excess of the original contract price in order to have the work completed according to the contract specifications, this does not preclude a subcontractor under the original contract from establishing his lien for the full amount of his claim." 53 Am.Jur.2d "Mechanics' Liens" § 242 (1970), citing Lyle v. Latourette, Ark.Supr., 209 Ark. 721, 192 S.W.2d 521, 525-26 (1946).

Thus in Delaware, prior to the passage of § 2707, a "person furnishing labor or materials to a contractor for the construction of any building may procure liens on the property for any unpaid amounts due from the contractor, though the debts were created without the owner's knowledge and the contractor has been paid the full agreed price." Maull v. Stokes, 31 Del.Ch. 188, 68 A.2d 200, 202 (1949). " § 2707 was added to the mechanics' lien law (in 1970) . . . to soften the harsh impact of the mechanics' lien law in the case of residential owners." Grier Lumber, Co. v. Tryon, Del.Super., 337 A.2d 323, 325 (1975). 2

Therefore, in analyzing the questions presented, we must bear in mind that § 2707 seeks to eliminate the harsh result of double liability against residential homeowners. However, because § 2707 is part of the larger mechanic's lien statutory scheme, it must be interpreted in a way consistent with the general purpose of that scheme, which is to protect suppliers of labor and material. We must uphold both purposes in our interpretation because, contrary to the Browns' contentions, the General Assembly did not repeal the existing Mechanic's Lien Law and adopt the New York System when it passed § 2707. Instead, the General Assembly sought to modify the existing Law to eliminate the harsh results that occurred under it. With these principles before us, we turn to the specific questions presented in this case.

III.

The first issue is whether the amount expended by the Browns to complete their house may be set-off in determining "the extent of the balance due such contractor" under § 2707.

The argument of the subcontractors, that when the Browns paid others to complete the house they were making bad faith payments to themselves, tortures the meaning and structure of the Statute and therefore must be rejected. The "payments" that § 2707 focuses upon for the "good faith" requirement are those made to the general contractor. It is explicitly stated in § 2707 that "(p)ayments made to the contractor by the owner after service of process, as provided in § 2715 of this title, 3 shall not be deemed to be 'in good faith'." Clearly, the purpose of the "good faith" requirement is to prevent an owner from attempting to defeat a supplier's lien through payments to the general contractor. Thus, where an owner pays a general contractor after service of process under § 2715, such bad faith payments will not operate to reduce the fund to which a supplier's lien may attach.

After consideration of "all of the relevant circumstances," Bedford v. Sussex Electrical Const. Co., Del.Supr., 382 A.2d 246, 248 (1978), we conclude that in this case payments for the cost of completion to a second general contractor after the first general contractor defaults do not constitute bad faith payments under § 2707.

Ray's and Masten argue that set-off for the cost of completion is improper under § 2707. Their arguments are unpersuasive because they ignore the intent of the General Assembly in the passage of § 2707. Although such argument may have been tenable prior to the passage of § 2707, since double liability was the evil the General Assembly tried to remove with the passage of § 2707, set-off for the cost of completion must be allowed, otherwise we will not be carrying out the clear present purpose of § 2707.

Appellants also contend that set-off for the cost of completion should not be permitted because the Browns assumed the role of general contractor when they terminated payments to Reid and Lloyd; that, therefore, they must hold the unpaid balance of the contract in trust for the benefit of the subcontractors under 6 Del.C. §§ 3502 and 3503. 4 We find this contention wholly unmeritorious in the light of § 2707.

Even prior to the passage of § 2707, our courts concluded that "set-off is a good and appropriate plea in an action of this kind." Voigtmann v. Wilmington Trust Bldg. Corp., Del.Super., 78 A. 920, 921 (1908). The passage of § 2707 should resolve any doubt about the validity of allowing a set-off for the cost of completion where a general contractor defaults.

For the foregoing reasons, we affirm the Superior Court's allowance of the cost of completion as a set-off. We hold that the "extent of the balance of the payment due such contractor" under § 2707 is to be computed as follows: the $37,200 paid to Reid and Lloyd, plus the $3,912.97 set-off for cost of completion, totalling $41,112.97, subtracted from the contract price of $45,027.17, producing a balance of $3,914.20 due the general contractor.

IV.

In the light of the Statute's dual purpose of protecting suppliers from losses and homeowners from double liability, a proper interpretation of § 2707 does not permit the Superior Court's decision to allow a liquidated damages...

To continue reading

Request your trial
3 cases
  • Resorts Intern. Shareholders Litigation Appeals, In re
    • United States
    • Supreme Court of Delaware
    • March 28, 1989
    ... ... , Wilmington, for appellees Resorts Intern., Inc., I.G. Davis, Robert D. Peloquin, H. Steven ... Cede & Co. v. Technicolor, Inc., Del.Supr., 542 A.2d 1182, ... ...
  • C & T Associates, Inc. v. Government of New Castle County
    • United States
    • Court of Chancery of Delaware
    • October 16, 1979
    ...of 'employees' appears in this very statute, though not in the . . . (same) . . . section." In Masten Lumber and Supply Co., Inc. et al. v. Brown et al., Del.Supr.1979, 405 A.2d 101, it was stated: "Because § 2707 is part of the larger mechanics' lien statutory scheme, it must be interprete......
  • S. G. Williams of Dover, Inc. v. Diamond State Vinyl, Inc.
    • United States
    • Delaware Superior Court
    • February 12, 1981
    ...§ 2715, such bad faith payments will not operate to reduce the fund to which a supplier's lien may attach. Masten Lumber and Supply Co., Inc. v. Brown, Del.Supr., 405 A.2d 101 (1979). There is little doubt that "... the legislature intended the phrase to require that the owner have no reaso......
1 books & journal articles
  • Mechanic's Liens
    • United States
    • ABA Archive Editions Library Construction Law
    • June 22, 2009
    ...v. Neal-Millard Co., 124 Ga. 884 (1906). 19. Collins v. Board of Trustees, 72 W. va. 583 (1913). 20. Masten Lumber & Supply Co. v. Brown, 405 A.2d 101 (Del. 1979). 21. LeGrand v. Hubbard, 216 Ala. 164 (1927). 22. See Bender , 2002 N.D. at 146. 23. Bloomington Hotel Co. v. Garthwait, 227 Ill......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT