Meccon, Inc. v. Univ. Of Akron

Decision Date09 April 2009
Docket NumberNo. 08AP-727.,08AP-727.
Citation182 Ohio App.3d 85,2009 Ohio 1700,911 N.E.2d 933
PartiesMECCON, INC., et al., Appellants, v. UNIVERSITY OF AKRON, Appellee.
CourtOhio Court of Appeals

Thompson Hine L.L.P., Peter D. Welin, and Andrew R. Fredelake, Columbus, for appellants.

Richard Cordray, Attorney General, and William C. Becker and Lisa J. Conomy, Assistant Attorneys General, for appellee.

TYACK, Judge.

{¶ 1} This is an appeal from the Ohio Court of Claims. At issue is whether the Court of Claims has subject-matter jurisdiction over a competitive-bidding dispute between plaintiffs-appellants, Meccon, Inc., and Ronald R. Bassak ("Meccon"), and defendant-appellee, University of Akron.

{¶ 2} In April 2008, the University of Akron invited bids for the University of Akron's Football Stadium Project. Ohio's public-bidding laws require that contracts be awarded to the lowest responsive and responsible bidder. R.C. 153.08, 9.312. Meccon submitted a bid for the heating, ventilation, and air conditioning ("HVAC") contract. Another contractor, S.A. Comunale, submitted four bids for the project: three separate bids for the stand-alone prime-plumbing, fire-protection, and HVAC contracts, and a fourth combined bid for a package of the individual contracts.

{¶ 3} When the bids were opened, S.A. Comunale was the low bidder for each of the stand-alone plumbing, fire-protection, and HVAC contracts. Meccon's bid for the stand-alone HVAC package was the second lowest bid. Additionally, S.A. Comunale's combined bid was more than $1.2 million lower than the next lowest bid.

{¶ 4} After it discovered the large disparity in its low bids from the next lowest bidders, S.A. Comunale withdrew its combined bid and withdrew its stand-alone plumbing bid. Despite language in the bid documents themselves and statutory language that prohibits withdrawal of a bid "when the result would be the awarding of the contract on another bid of the same bidder," the University of Akron awarded the stand-alone HVAC and fire-protection contracts to S.A. Comunale. R.C. 9.31.

{¶ 5} On August 6, 2008, Meccon filed suit in the Court of Claims, seeking a temporary restraining order, a declaratory judgment, preliminary and permanent injunctive relief, damages for its bid-preparation costs, and other such damages and relief resulting from the University of Akron's failure to award the HVAC contract to Meccon.

{¶ 6} Before the court could hold an evidentiary hearing on the temporary restraining order ("TRO"), the University of Akron filed a motion to dismiss for lack of subject-matter jurisdiction. The university argued that an Ohio Supreme Court case limited disappointed bidders to injunctive relief only. The Court of Claims granted the motion, finding that Meccon's claim for bid-preparation costs and other money damages was not cognizable due to the decision in Cementech, Inc. v. Fairlawn, 109 Ohio St.3d 475, 2006-Ohio-2991, 849 N.E.2d 24. Without a legally cognizable claim for money damages, the complaint was for equitable relief only. Therefore, the Court of Claims decided that it lacked subject-matter jurisdiction. The Court of Claims then denied the motion for a TRO, dismissed the claim, and denied all remaining motions as moot. This appeal followed, with Meccon assigning as error the following:

1. The Trial Court erred when it dismissed Appellants' case for lack of Subject-Matter Jurisdiction.

2. The Trial Court erred when it failed to rule on Appellants' Motion for Temporary Restraining Order.

{¶ 7} We review an appeal of a dismissal for lack of subject-matter jurisdiction under a de novo standard of review. Reynoldsburg City School Dist. Bd. of Edn. v. Licking Hts. Local School Dist., 10th Dist. No. 08AP-415, 2008-Ohio-5969, 2008 WL 4927406. The question we must decide is whether any cause of action cognizable by the forum has been raised in the complaint. Id. Here, the issue turns on whether Meccon's complaint states a legally cognizable claim for money damages, for without a claim for money damages, the Court of Claims lacks subject-matter jurisdiction.

{¶ 8} It is undisputed that Meccon's complaint requests bid-preparation costs and any additional costs and damages incurred due to the failure of the University of Akron to award the HVAC contract to Meccon. This court has concluded that if an action in the Court of Claims is one for money damages against the state coupled with a request for declaratory and injunctive relief, the appropriate forum is the Court of Claims. Tiemann v. Univ. of Cincinnati (1998), 127 Ohio App.3d 312, 318, 712 N.E.2d 1258. In Tiemann, the plaintiffs sought to enjoin the university from proceeding with a construction project that bypassed Ohio's public-works and bidding requirements. The plaintiffs stated in their complaint that their suit was without a claim for monetary damages, but this court found that the Court of Claims did have jurisdiction because the complaint asked for declaratory, injunctive, and "any further" relief. Id. at 319, 712 N.E.2d 1258.

{¶ 9} Some years later, the Ohio Supreme Court decided Cementech. Cementech came before the Ohio Supreme Court as a certified conflict. The issue before the court was:

Does the availability of injunctive relief, if timely filed but denied, preclude an award of lost profits in a municipal contract case?

Cementech, Inc. v. Fairlawn, 106 Ohio St.3d 1479, 2005-Ohio-3978, 832 N.E.2d 733.

{¶ 10} In the ensuing opinion, the Ohio Supreme Court held:

When a municipality violates competitive-bidding laws in awarding a competitively bid project, the rejected bidder cannot recover its lost profits as damages.

Cementech, Inc. v. Fairlawn, 109 Ohio St.3d 475, 2006-Ohio-2991, 849 N.E.2d 24, syllabus.

{¶ 11} At the trial level, the trial court had awarded Cementech its bid-preparation costs, and that award was not appealed. Consequently, the issue of whether a rejected bidder could recover its bid-preparation costs was not squarely before the Ohio Supreme Court. However, in resolving the certified conflict and holding that a rejected bidder cannot recover its lost profits as damages, the Ohio Supreme Court went further and stated, "[A] rejected bidder is limited to injunctive relief." Id. at ¶ 10.

{¶ 12} The Ohio Supreme Court then discussed the rationale for injunctive relief:

It is clear that in the context of competitive bidding for public contracts, injunctive relief provides a remedy that prevents excessive costs and corrupt practices, as well as protects the integrity of the bidding process, the public, and the bidders. Moreover, the injunctive process and the resulting delays serve as a sufficient deterrent to a municipality's violation of competitive-bidding laws.

Id. at ¶ 11.

{¶ 13} Meccon characterizes the Ohio Supreme Court's statement limiting relief as dicta beyond the scope of the syllabus and the narrow issue that was before the court. Meccon argues that this court should not interpret Cementech in such a way that an isolated statement on an issue that was not before the court would preclude recovery of bid-preparation costs.

{¶ 14} The University of Akron takes the position that the language and meaning of Cementech is clear and that the only relief available to a disappointed bidder is an injunction.

{¶ 15} Here, because Cementech precludes recovery for lost profits by an unsuccessful bidder, only Meccon's claim for its bid-preparation expenses remains as a claim for money damages in the Court of Claims.1 If bid-preparation expenses are not allowed as damages in this type of action, then the action must be dismissed for lack of subject-matter jurisdiction.

{¶ 16} The cases certified as being in conflict with the appellate decision in Cementech disallowed recovery for lost profits, but neither case discussed bid-preparation costs as an element of damages. The statement that an unsuccessful bidder is limited to injunctive relief is nearly identical in Cementech and Cavanaugh Bldg. Corp. v. Bd. of Cuyahoga Cty. Commrs. (Jan. 27, 2000), 8th Dist. No. 75607, 2000 WL 86554.

{¶ 17} In the other case cited as being in conflict with Cementech, the Court of Appeals for Trumbull County cited policy considerations that militate in favor of injunctive relief. The court stated:

Thus, if we were to allow appellant to receive monetary damages, only the bidders would be protected because the public would have to pay the contract price of the successful bidder plus the lost profits of an aggrieved bidder. However, if injunction is the sole remedy both the public and the bidders themselves are protected. Accordingly, we conclude that injunction is the only remedy available.

(Emphasis added.) Hardrives Paving & Constr., Inc. v. Niles (1994), 99 Ohio App.3d 243, 247-248, 650 N.E.2d 482. Again, the language in this case is quite similar to that used by the Ohio Supreme Court in Cementech.

{¶ 18} Despite the fact that the issue of recovery of bid-preparation costs was not part of the certified question, the Ohio Attorney General argued that damages for bid preparations should not be an available remedy to a disappointed bidder going against a public entity. In an amicus curiae brief filed in Cementech, the Attorney General stated:

The Attorney General recognizes that the question of whether damages in the form of bid-preparation costs is awardable to a disappointed bidder was not presented to the Court in either the discretionary appeal or the certified conflict case here. However, it is appropriate to consider whether this measure of damages is proper, incident to deciding the correct form of relief for a disappointed bidder in a competitive bidding case. Accordingly, even though a decision on this point will not necessarily affect the trial court's judgment against Fairlawn for $3,725.54 in bid-preparation costs, the Attorney General urges the Court to address this issue as part of its overall analysis of what remedies are...

To continue reading

Request your trial
13 cases
  • State EX. REL. NORTHERN Ohio CHAPTER of Assoc.D BUILDERS v. BARBERTON City Sch. Dist. Bd. of Educ.
    • United States
    • Ohio Court of Appeals
    • 28 Abril 2010
    ... ... REL. NORTHERN OHIO CHAPTER OF ASSOCIATED BUILDERS & CONTRACTORS, INC. et al., Appellants, v. BARBERTON CITY SCHOOL DISTRICT BOARD OF EDUCATION ... Tamzin Kelly O'Neil and Patrick S. Vrobel, Akron, for appellees Barberton City School District Board of Education. Richard ... Univ. of Cincinnati (1998), 127 Ohio App.3d 312, 325, 712 N.E.2d 1258. An ... Under the authority of Meccon, Inc. v. Univ. of Akron, 182 Ohio App.3d 85, 2009-Ohio-1700, 911 N.E.2d ... ...
  • Stubbs v. Dep't of Rehab. & Corr.
    • United States
    • Ohio Court of Appeals
    • 29 Marzo 2012
    ... ... Id., citing Meccon, Inc. v. Univ. of Akron, 182 Ohio App.3d 85, 2009-Ohio-1700 (10th Dist.).{ ... ...
  • State ex rel. Glidepath, LLC v. Columbus Reg'l Airport Auth.
    • United States
    • Ohio Court of Appeals
    • 5 Enero 2012
    ... ... 's Claim for Bid Preparation Costs Without Consideration of the Meccon Decision. ASSIGNMENT OF ERROR #4 - The Trial Court Erred in Finding that ... 1 In support, it cites Meccon, Inc. v. Univ. of Akron, 126 Ohio St.3d 231, 2010-Ohio-3297, in which the ... ...
  • Lucki v. Ohio Dep't of Rehab. & Corr.
    • United States
    • Ohio Court of Appeals
    • 20 Octubre 2011
    ... ... Crable at 8, citing Meccon, Inc. v. Univ. of Akron, 182 Ohio App.3d 85, 2009-Ohio-1700, 911 N.E.2d ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT